1 PLAN PRESENTED TO REACH USD 5.5 BILLION FOREIGN INVESTMENT WWW.MONTSAME.MN PUBLISHED:2026/09/23      2 COAL PYROLYSIS PLANT TO BE BUILT IN BAGANUUR THROUGH PUBLIC-PRIVATE PARTNERSHIP WWW.MONTSAME.MN PUBLISHED:2026/09/23      3 TEMUULEN APPOINTED MINISTER OF JUSTICE AND INTERNAL AFFAIRS WWW.MONTSAME.MN PUBLISHED:2026/09/23      4 MONGOLIAN HERDERS ENLIST NEW TECH AGAINST HARSHER, DRIER CLIMATE WWW.FRANCE24.COM PUBLISHED:2026/09/23      5 PETRO MATAD HALTS MONGOLIAN OIL PRODUCTION AMID ONGOING DISPUTE WITH PETROCHINA WWW.PLUANG.COM PUBLISHED:2026/09/23      6 RUSSIA LIMITS DIESEL EXPORTS AS MONGOLIA DETAILS ITS CONFIRMED ORDERS WWW.ENERGYNEWS.PRO PUBLISHED:2026/09/23      7 MONGOLIAN, AUSTRALIAN SPEAKERS HOLD OFFICIAL TALKS WWW.MONTSAME.MN PUBLISHED:2026/09/23      8 CONSTRUCTION BEGINS ON POWER PLANT, WASTEWATER TREATMENT FACILITY AT EMEELT ECO INDUSTRIAL PARK WWW.MONTSAME.MN PUBLISHED:2026/09/22      9 B.NAIDALAA: THERMAL ENERGY SHORTAGE EXPECTED THIS WINTER WWW.GOGO.MN PUBLISHED:2026/09/22      10 MONGOLIA'S INTERNATIONAL BOND MARKET: A STRONG 2026, BUT THE NEXT TEST LIES AHEAD WWW.CAPITALMARKETS.MN PUBLISHED:2026/09/22      Т.ДОРЖХАНД: СЭРГЭЭГДЭХ ЭРЧИМ ХҮЧ, ДАТА ТӨВ ЗЭРЭГ 5 САЛБАРТ ГАДНЫН ХӨРӨНГӨ ОРУУЛАЛТ ТАТАХ БОДЛОГО БАРИМТАЛНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/23     Ц.САНДАГ-ОЧИР: 2028 ОНД 600 МЯНГАН ТОНН САЙЖРУУЛСАН ТҮЛШ НИЙЛҮҮЛЭХ ХҮЧИН ЧАДАЛТАЙ ҮЙЛДВЭР АШИГЛАЛТАД ОРУУЛНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/23     “МОНГОЛЫН ТӨМӨР ЗАМ” ТӨХК ЗҮТГҮҮР, ВАГОНЫ ХҮЧИН ЧАДЛАА НЭМЭГДҮҮЛНЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/23     ЧИНГИС ХААН ОЛОН УЛСЫН НИСЭХ БУУДЛЫГ 3.4 ИХ НАЯД ТӨГРӨГӨӨР ӨРГӨТГӨНӨ WWW.GOGO.MN НИЙТЭЛСЭН:2026/09/23     ХЯТАДЫН НҮҮРСНИЙ ШИНЭ БОДЛОГО МОНГОЛД ЭЕРГЭЭР НӨЛӨӨЛЖ МАГАДГҮЙ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/23     МОНГОЛ УЛСАД НЭГ САЯ ГАРУЙ АЙЛ ӨРХ БАЙНА WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/09/23     СУРВАЛЖЛАГА: НИЙСЛЭЛИЙН ШИНЭ ЭХ ҮҮСВЭР ТЭЦ-5-ЫН БҮТЭЭН БАЙГУУЛАЛТ 20 ХУВЬД ХҮРЧЭЭ WWW.NEWS.MN НИЙТЭЛСЭН:2026/09/23     Г.ТЭМҮҮЛЭНГ ХУУЛЬ ЗҮЙ, ДОТООД ХЭРГИЙН САЙДААР ТОМИЛЛОО WWW.EAGLE.MN НИЙТЭЛСЭН:2026/09/22     БОХИР УСНЫ ШУГАМ ХООЛОЙГ ШУУДУУ УХАЛГҮЙГЭЭР ДОТОРЛОХ, ШИНЭЧЛЭХ ТЕХНОЛОГИЙГ НЭВТРҮҮЛНЭ WWW.GOGO.MN НИЙТЭЛСЭН:2026/09/22     САМАР ТҮҮВЭЛ 5.4-27 САЯАР ТОРГОХ, 1-5 ЖИЛ ХОРИХ ЯЛААР ШИЙТГЭНЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/09/22    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

Railway extension from Erdenet to Ovoot coal mine www.news.mn

Aspire Mining Ltd has received an 18-month extension until 18 September 2021 to prepare the legal and other necessary actions required prior to the construction of the Erdenet to Ovoot railway. This railway is considered critical infrastructure for the full-scale development of the Ovoot Coking Coal Project in Mongolia.

Aspire’s focus remains the Ovoot Early Development Project by developing a special-purpose haul road to deliver up to 4 million tonnes per annum from the Ovoot Coking Coal Project to the existing rail head at Erdenet.

In August 2015, Aspire’s 80%-owned subsidiary Northern Railways LLC was awarded a 30-year concession to build, operate and transfer to the Mongolian Government the Erdenet to Ovoot Railway.

Northern Railways LLC along with its nominated EPC partners, China Gezhouba Group International Company Limited and China Railways 20 Bureau Group Corporation, completed a definitive feasibility study in March 2018 and are in discussions with the Mongolian Government regarding the preferred rail alignment.

While these discussions continue, the time frame to clear conditions precedent prior to the construction commencement of the railway has now been extended 18 months through to 18 September 2021.

Proactive last caught up with Aspire in November 2019 following a well-supported capital raising.



Published Date:2020-03-27