1 RIO TINTO SHARES MOVE RED ON YEAR: MINING PAUSE ADDS TO PULLBACK WWW.THEBULL.COM.AU PUBLISHED:2026/11/02      2 10TH MEETING OF THE MONGOLIA-SOUTH KOREA INTERGOVERNMENTAL JOINT COMMITTEE HELD WWW.MONTSAME.MN PUBLISHED:2026/11/02      3 NIGHTTIME ELECTRICITY TARIFF DISCOUNTS BEGIN FOR GER DISTRICT HOUSEHOLDS WWW.MONTSAME.MN PUBLISHED:2026/11/02      4 KHUSTAI PARK RECOGNIZED IN GREEN DESTINATIONS TOP 100 STORIES WWW.UBPOST.MN PUBLISHED:2026/11/02      5 FIRE DEVASTATED A MONGOLIAN NATURE RESERVE. WHO’S TO BLAME? WWW.THEDIPLOMAT.COM PUBLISHED:2026/11/01      6 PRIME MINISTER UCHRAL MEETS UK AMBASSADOR EDWIN SAMUEL WWW.MONTSAME.MN PUBLISHED:2026/11/01      7 MONGOLIA ON TRACK TO MEET TOURIST ARRIVAL TARGET THIS YEAR WWW.XINHUANET.COM PUBLISHED:2026/11/01      8 ON-SITE INSPECTION UNDERWAY FOLLOWING ROCKFALL ACCIDENT AT OYU TOLGOI UNDERGROUND MINE WWW.MONTSAME.MN PUBLISHED:2026/11/01      9 PRIME MINISTER REVIEWS POWER PLANT UPGRADES AHEAD OF 2026–2027 WINTER WWW.MONTSAME.MN PUBLISHED:2026/11/01      10 FINAL CONTINGENT OF MONGOLIAN PEACEKEEPERS RETURNS HOME FROM SOUTH SUDAN WWW.MONTSAME.MN PUBLISHED:2026/11/01      НЭГ БАЙРЫГ 65 ХҮНД ХУДАЛДСАН ЗАЛИЛАНГИЙН ХЭРЭГ БҮРТГЭГДЖЭЭ WWW.NEWS.MN НИЙТЭЛСЭН:2026/11/02     КАЗАХСТАН УЛСЫН ХИЛ ДЭЭР УРТ ДАРААЛАЛ ҮҮССЭНИЙ УЛМААС ОРОСЫН ТЭЭВЭРЛЭГЧИД МОНГОЛООР ДАЙРСАН ЗАМЫГ СОНГОХ БОЛЖЭЭ WWW.IKON.MN НИЙТЭЛСЭН:2026/11/02     УЛААНБААТАРЫН АГААРЫН БОХИРДЛЫГ ₮14.9 ИХ НАЯДЫН САНХҮҮЖИЛТЭЭР ТАВАН ЖИЛИЙН ДОТОР 55% БУУРУУЛАХ ТӨЛӨВЛӨГӨӨГ ТАНИЛЦУУЛАВ WWW.IKON.MN НИЙТЭЛСЭН:2026/11/02     ДУЛААНЫ V ЦАХИЛГААН СТАНЦЫН БАРИЛГА УГСРАЛТЫН АЖИЛ 35 ХУВЬД ХҮРЛЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/11/02     “ЭРДЭНЭТ ҮЙЛДВЭР”-ИЙН УРТ ХУГАЦААНЫ ХӨГЖЛИЙН ТЭЗҮ-Г ХҮЛЭЭЛГЭН ӨГЛӨӨ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/11/02     МАХНЫ ҮНЭ 50 ГАРУЙ ХУВИАР ӨСЧ, ҮЙЛДВЭРЛЭГЧДИЙГ ШАХАЛТАД ОРУУЛЛАА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/11/02     УЛААНБАДРАХ СУМААС ЗӨӨВЧ-ОВОО ХҮРТЭЛХ 60 КМ АВТО ЗАМЫН БАРИЛГЫН АЖИЛ ЭХЭЛЛЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/11/02     ДЭЛХИЙН ЭНХИЙН ҮЙЛСЭД ХУВЬ НЭМРЭЭ ОРУУЛСАН МОНГОЛ ЦЭРГҮҮД ЭХ ОРОНДОО ИРЛЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/11/01     МОНГОЛ, СОЛОНГОСЫН ИРГЭД ХАРИЛЦАН ЗОРЧИХОД ҮҮСЭЖ БУЙ АСУУДЛЫГ ШИЙДВЭРЛЭХ ШИНЭ МЕХАНИЗМЫГ ОЙРЫН ХУГАЦААНД ЭХЛҮҮЛНЭ WWW.IKON.MN НИЙТЭЛСЭН:2026/11/01     С.МӨНХСҮХ: ОСЛЫГ НУХАЦТАЙ АВЧ ҮЗЭЖ, ОЛОН ТАЛЫН ШАЛГАЛТ ХИЙНЭ. ДАХИН ОСОЛ ГАРГАХГҮЙ БАЙХАД АНХААРНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/11/01    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

Railway extension from Erdenet to Ovoot coal mine www.news.mn

Aspire Mining Ltd has received an 18-month extension until 18 September 2021 to prepare the legal and other necessary actions required prior to the construction of the Erdenet to Ovoot railway. This railway is considered critical infrastructure for the full-scale development of the Ovoot Coking Coal Project in Mongolia.

Aspire’s focus remains the Ovoot Early Development Project by developing a special-purpose haul road to deliver up to 4 million tonnes per annum from the Ovoot Coking Coal Project to the existing rail head at Erdenet.

In August 2015, Aspire’s 80%-owned subsidiary Northern Railways LLC was awarded a 30-year concession to build, operate and transfer to the Mongolian Government the Erdenet to Ovoot Railway.

Northern Railways LLC along with its nominated EPC partners, China Gezhouba Group International Company Limited and China Railways 20 Bureau Group Corporation, completed a definitive feasibility study in March 2018 and are in discussions with the Mongolian Government regarding the preferred rail alignment.

While these discussions continue, the time frame to clear conditions precedent prior to the construction commencement of the railway has now been extended 18 months through to 18 September 2021.

Proactive last caught up with Aspire in November 2019 following a well-supported capital raising.



Published Date:2020-03-27