1 OYU TOLGOI SAYS DIVIDENDS WILL BEGIN IN 2027 WWW.MONTSAME.MN PUBLISHED:2026/11/11      2 ULAANBAATAR TO CUT MUNICIPAL TAX RATE ON SERVICES FROM 2% TO 1% WWW.MONTSAME.MN PUBLISHED:2026/11/11      3 ALASKA GUARDSMEN, MONGOLIAN FIRST RESPONDERS CONQUER RUGGED TERRAIN DURING UVS 2026 DISASTER RESPONSE EXERCISE WWW.AK.NG.MIL PUBLISHED:2026/11/11      4 PGL ANNOUNCES 2027 $1 MILLION TOURNAMENT IN MONGOLIA WWW.DUST2.US PUBLISHED:2026/11/11      5 STATE FLAG RAISED, NINE WHITE BANNERS DISPLAYED TO MARK CHINGGIS KHAAN’S BIRTH ANNIVERSARY WWW.MONTSAME.MN PUBLISHED:2026/11/11      6 MONGOLIAN ACADEMY OF SCIENCES RECEIVES THE ORDER OF CHINGGIS KHAAN WWW.MONTSAME.MN PUBLISHED:2026/11/11      7 CABINET TO DISCUSS WHISTLEBLOWER PROTECTION AMONG 20 AGENDA ITEMS WWW.MONTSAME.MN PUBLISHED:2026/11/11      8 TRUMP-BACKED CRITICAL MINERALS DEALS FACE GROWING PRESSURE AFTER BLUE WAVE WWW.BLOOMBERG.COM PUBLISHED:2026/11/09      9 TDB INVESTS USD 30 MILLION IN A THREE-YEAR TECHNOLOGY TRANSFORMATION WWW.MONTSAME.MN PUBLISHED:2026/11/09      10 MONGOLIA, US DISCUSS EXPANDING COOPERATION IN VOCATIONAL EDUCATION WWW.MONTSAME.MN PUBLISHED:2026/11/09      ХҮННҮ ХОТЫН ДЭД БҮТЦИЙГ БАРЬЖ БАЙНА WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/11/11     "АВЛИГА АЛБАН ТУШААЛ, ТӨРИЙН ӨМЧ ХӨРӨНГӨ, ТӨСӨВТЭЙ ХОЛБООТОЙ ЗҮЙЛИЙГ БАРИМТАД ТУЛГУУРЛАН ШҮГЭЛ ҮЛЭЭСЭН БОЛ ГҮТГЭХ ГЭМТ ХЭРЭГТ ХАМААРАХГҮЙ" WWW.IKON.MN НИЙТЭЛСЭН:2026/11/11     ИНФЛЯЦ АРАВДУГААР САРД 13.4 ХУВЬТАЙ ГАРЧ, ЭНЭ ОНЫ ХАМГИЙН ӨНДӨР ТҮВШИНД ХҮРЛЭЭ WWW.IKON.MN НИЙТЭЛСЭН:2026/11/11     ЕСӨН УЛСЫН 129 ИРГЭНИЙГ МОНГОЛ УЛСААС АЛБАДАН ГАРГАЖЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/11/11     ЕС, АРАВДУГААР САРД УЛСЫН ХЭМЖЭЭНД ДӨРВӨН ИРГЭН СУРАГГҮЙ АЛГА БОЛЖЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/11/11     РИО ТИНТО 2027 ОНД ОЮУ ТОЛГОЙГООС НОГДОЛ АШИГ ХУВААРИЛНА ГЭДГЭЭ БАТЛАВ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/11/11     ДУЛААН ГАРААШИЙГ ТАТВАРААС ЧӨЛӨӨЛӨХ ХУУЛИЙН ТӨСЛИЙГ ЗАСГИЙН ГАЗАР ДЭМЖЛЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/11/11     УЛААНБААТАР ХОТЫН ЗУРГААН ТӨРЛИЙН ТАТВАРЫГ 50 ХУВЬ БУУРУУЛАХ ХОТЫН ДАРГЫН САНААЧИЛГЫГ НИТХ ДЭМЖЛЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/11/09     “ЭРДЭНЭС ТАВАНТОЛГОЙ” ХК НЭГ ИХ НАЯД ТӨГРӨГИЙН НООГДОЛ АШИГ ТӨВЛӨРҮҮЛЭВ WWW.NEWS.MN НИЙТЭЛСЭН:2026/11/09     100 САЯАС ДЭЭШ ХАХУУЛЬ АВБАЛ БҮХ НАСААР ХОРИХ САНАЛЫГ 100 МЯНГАН ИРГЭН ДЭМЖЖЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/11/09    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

Railway extension from Erdenet to Ovoot coal mine www.news.mn

Aspire Mining Ltd has received an 18-month extension until 18 September 2021 to prepare the legal and other necessary actions required prior to the construction of the Erdenet to Ovoot railway. This railway is considered critical infrastructure for the full-scale development of the Ovoot Coking Coal Project in Mongolia.

Aspire’s focus remains the Ovoot Early Development Project by developing a special-purpose haul road to deliver up to 4 million tonnes per annum from the Ovoot Coking Coal Project to the existing rail head at Erdenet.

In August 2015, Aspire’s 80%-owned subsidiary Northern Railways LLC was awarded a 30-year concession to build, operate and transfer to the Mongolian Government the Erdenet to Ovoot Railway.

Northern Railways LLC along with its nominated EPC partners, China Gezhouba Group International Company Limited and China Railways 20 Bureau Group Corporation, completed a definitive feasibility study in March 2018 and are in discussions with the Mongolian Government regarding the preferred rail alignment.

While these discussions continue, the time frame to clear conditions precedent prior to the construction commencement of the railway has now been extended 18 months through to 18 September 2021.

Proactive last caught up with Aspire in November 2019 following a well-supported capital raising.



Published Date:2020-03-27