1 PRIME MINISTER UCHRAL NYAM-OSOR DEPARTS FOR OFFICIAL VISIT TO JAPAN WWW.MONTSAME.MN PUBLISHED:2026/09/27      2 JAPAN TO LEND MONGOLIA ¥150 BILLION FOR AIRPORT EXPANSION WWW.JAPANTIMES.CO.JP PUBLISHED:2026/09/27      3 EUROPEAN PRESS CRITICIZES MONGOLIA'S ENERGY DEPENDENCY AND BUSINESS ENVIRONMENT WWW.OPEN.KG PUBLISHED:2026/09/27      4 SECURITIES TRADING REACHES MNT 1 TRILLION WWW.MONTSAME.MN PUBLISHED:2026/09/27      5 MINISTRIES MEET ICC DELEGATION WWW.UBPOST.MN PUBLISHED:2026/09/27      6 VERIFICATION DEMANDED OVER CITIZENSHIP OF CONTESTANT REPRESENTING MONGOLIA AT MISS GRAND INTERNATIONAL WWW.GOGO.MN PUBLISHED:2026/09/27      7 ULAANBAATAR DESIGNATES EIGHT SITES FOR AUTUMN TREE PLANTING WWW.GOGO.MN PUBLISHED:2026/09/27      8 OUTSTANDING BANK LOANS RISE 14.3 PERCENT WWW.MONTSAME.MN PUBLISHED:2026/09/24      9 CENTRAL ASIA AND MONGOLIA GROWTH TO REMAIN ROBUST WWW.EBRD.COM PUBLISHED:2026/09/24      10 A NEW OIL STORAGE FACILITY WITH A CAPACITY OF 16,000 CUBIC METERS HAS BEEN PUT INTO OPERATION IN MONGOLIA WWW.OPEN.KG PUBLISHED:2026/09/24      ЕРӨНХИЙ САЙД Н.УЧРАЛ ЯПОН УЛСАД АЛБАН ЁСНЫ АЙЛЧЛАЛ ХИЙХЭЭР МОРДЛОО WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/09/27     MININGWEEK 2026: НИЙТ ГАЗАР НУТГИЙНХАА 21 ХУВЬД АШИГТ МАЛТМАЛЫН ЛИЦЕНЗ ОЛГОХ БОЛОМЖТОЙ WWW.GOGO.MN НИЙТЭЛСЭН:2026/09/27     ДҮНЖИНГАРАВЫН УУЛЗВАРТ БОЛСОН ДЭЛБЭРЭЛТИЙН ХЭРГИЙГ НЭМЭЛТ МӨРДӨН БАЙЦААЛТ ХИЙЛГЭХЭЭР ПРОКУРОРТ БУЦААВ WWW.IKON.MN НИЙТЭЛСЭН:2026/09/27     “МОНГОЛЫН НОГООН, ХҮРТЭЭМЖТЭЙ ХОТУУД” ТӨСЛИЙГ ХЭРЭГЖҮҮЛЖ ЭХЭЛЛЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/09/27     АГААРЫН ТЭЭВРИЙН ХАМТЫН АЖИЛЛАГААГ ӨРГӨЖҮҮЛНЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/09/27     26 МЯНГАН ХҮН УРГАЦ ХУРААЛТАД ОРОЛЦОЖ БАЙНА WWW.NEWS.MN НИЙТЭЛСЭН:2026/09/27     ШҮҮХЭЭС НАЙРУУЛАГЧ Б.БААТАРТ ХИЛИЙН ХОРИГ ТАВЬЖЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/26     "ХӨРӨНГӨ ОРУУЛАГЧДЫН ГОМДЛЫГ 30 ХОНОГТ ШИЙДВЭРЛЭХ ШИНЭ ЗОХИЦУУЛАЛТ ХЭРЭГЖИЖ ЭХЭЛСЭН" WWW.NEWS.MN НИЙТЭЛСЭН:2026/09/24     “МЯНГАД НАР” 19.8 МВТ-ЫН НАРНЫ ЦАХИЛГААН СТАНЦЫН ГҮЙЦЭТГЭЛ 40 ХУВЬТАЙ БАЙНА WWW.EAGLE.MN НИЙТЭЛСЭН:2026/09/24     ГОВИЙН БҮСЭД ЗАРЛАСАН СЭРГЭЭГДЭХ ЭРЧИМ ХҮЧНИЙ АУКЦИОНД ГУРВАН КОМПАНИЙН ХАМТАРСАН ТҮНШЛЭЛ ШАЛГАРЛАА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/24    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

EBRD and EU support first transmission project in Mongolia www.ebrd.com

The European Bank for Reconstruction and Development (EBRD) is improving the flexibility and reliability of the electrical grid in Mongolia and increasing its ability to absorb energy produced by renewable sources.
An EBRD sovereign loan of up to US$ 62.8 million and capital grant of up to €5 million will help build and commission a 220-kilometre double-circuit 220kV transmission line between the towns of Sainshand and Choir. They will also fund a new 220/110/35 kV substation in Sainshand and increase the capacity of a similar substation in Choir. The project is also being supported by the European Union (EU) Asia and Pacific Investment Facility, which is expected to provide a capital grant of up to €8 million.
The project will contribute to the decarbonisation of Mongolia, where fossil fuel-based power generation remains dominant. Once up and running, the transmission line will help cut annual CO2 emissions by 140,000 tonnes by reducing electricity transmission losses and increasing the absorption of renewable energy.
Within the context of the project, Mongolia will develop a new training programme that will enable young women and men to gain electrical engineering skills, boosting their employment opportunities.
To date, the EBRD has invested almost €2.2 billion in Mongolia’s economy through 126 projects.
 
 
 