1 EARTHMOVING WORK FOR THERMAL POWER PLANT-V TO BEGIN ON FEBRUARY 15 WWW.GOGO.MN PUBLISHED:2026/02/04      2 KH.NYAMBAATAR: SERGELEN SUBSTATION TO ENTER SERVICE THIS YEAR WWW.GOGO.MN PUBLISHED:2026/02/04      3 G.DAMDINNYAM: MONGOLIA-MADE STEEL COULD REACH EUROPE IN 10 DAYS WWW.GOGO.MN PUBLISHED:2026/02/04      4 MAJILIS RATIFIES EAEU-MONGOLIA INTERIM TRADE AGREEMENT WWW.QAZINFORM.COM PUBLISHED:2026/02/04      5 ALL-PARTY PARLIAMENTARY GROUP (APPG) ON MONGOLIA ESTABLISHED IN THE UK PARLIAMENT WWW.EMBASSYOFMONGOLIA.CO.UK PUBLISHED:2026/02/04      6 MONGOLIA RANKS AMONG ASIA’S SAFEST COUNTRIES WWW.INSIDEMONGOLIA.MN PUBLISHED:2026/02/04      7 MONGOLIA’S TRUMP ‘BOARD OF PEACE’ MEMBERSHIP REVIVES ITS ‘THIRD NEIGHBOUR’ PLAYBOOK WWW.INTELLINEWS.COM PUBLISHED:2026/02/04      8 ABOUT 50,000 CHILDREN HAVE DOMESTIC ACCIDENTS EVERY YEAR WWW.GOGO.MN PUBLISHED:2026/02/03      9 FROM MONGOLIA TO TEAM USA, OPENING CEREMONY FASHION TAKES CENTRE STAGE AT MILANO CORTINA 2026 WWW.OLYMPICS.COM PUBLISHED:2026/02/03      10 MONGOLIA’S HUNNU AIR EYES NETWORK GAINS FOLLOWING E2-BASED FLEET MODERNISATION WWW.FLIGHTGLOBAL.COM PUBLISHED:2026/02/03      МОНГОЛ-ХЯТАДЫН БАНК, САНХҮҮГИЙН САЛБАРЫН ДУГУЙ ШИРЭЭНИЙ УУЛЗАЛТ БОЛЛОО WWW.ITOIM.MN НИЙТЭЛСЭН:2026/02/04     НИЙСЛЭЛИЙН АВТО ЗАМЫН 19 УУЛЗВАРААС ЦАГДААГИЙН БИЕТ ЗОХИЦУУЛАЛТЫГ ХАСЖЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/02/04     БРИТАНИЙН ПАРЛАМЕНТАД БҮХ НАМЫН МОНГОЛЫН БҮЛЭГ БАЙГУУЛАГДАВ WWW.EMBASSYOFMONGOLIA.CO.UK НИЙТЭЛСЭН:2026/02/04     “СЭРГЭЛЭН” ДЭД СТАНЦЫН ГҮЙЦЭТГЭЛ 92 ХУВЬТАЙ ҮРГЭЛЖИЛЖ БАЙНА WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/02/04     ДУЛААНЫ 5-Р ЦАХИЛГААН СТАНЦЫН ГАЗАР ШОРООНЫ АЖЛЫГ ЭНЭ САРЫН 15-НД ЭХЛҮҮЛНЭ WWW.GOGO.MN НИЙТЭЛСЭН:2026/02/03     IQ-ИЙН ДУНДАЖ ҮЗҮҮЛЭЛТЭЭР МОНГОЛЧУУД НАЙМДУГААРТ ЭРЭМБЭЛЭГДЖЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/02/03     МОНГОЛБАНК 1.9 ТОНН ҮНЭТ МЕТАЛЛ ХУДАЛДАН АВЧЭЭ WWW.NEWS.MN НИЙТЭЛСЭН:2026/02/03     НИЙСЛЭЛД ХИЙ ЦЭНЭГЛЭХ 33 ЦЭГ БАЙГУУЛНА WWW.EAGLE.MN НИЙТЭЛСЭН:2026/02/03     УГААРЫН ХИЙД 169 ИРГЭН ХОРДОЖ, ЭМНЭЛГИЙН ТУСЛАМЖ АВЧЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/02/03     НЭГДҮГЭЭР САРД 2 САЯ ТОНН НҮҮРС ЭКСПОРТОЛЖЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/02/03    

Earthmoving work for Thermal Power Plant-V to begin on February 15 www.gogo.mn

Prime Minister G.Zandanshatar visited the site of the Thermal Power Plant V project on February 3, 2026, a development intended to meet Ulaanbaatar’s growing electricity and heat demand and reduce pressure on the central energy system.
The plant will be built on the former ash pond of TPP-2 in Bayangol district and is planned to have a generation capacity of 300 MW of electricity and 340 Gcal of heat. The design incorporates environmentally friendly technologies, including an air-cooling system that reduces water use and wastewater-reuse solutions.
Officials say the plant will supply electricity to about 100,000 households and heat to 40,000 households. 90% of electricity produced will be fed into the central grid; the remaining 10% will cover the plant’s internal needs.
Earthmoving work will begin on February 15, starting with removal of ash accumulated since TPP-2 began operating in 1961. Main construction work is scheduled to start in April after completion of preparatory works. The construction period is estimated at 2.5 years.
The project is structured as a public–private partnership with a total cost of USD 658.5 million: the private sector will provide 80% of the financing and the capital city 20%.



Published Date:2026-02-04