1 CONSTRUCTION BEGINS ON POWER PLANT, WASTEWATER TREATMENT FACILITY AT EMEELT ECO INDUSTRIAL PARK WWW.MONTSAME.MN PUBLISHED:2026/09/22      2 B.NAIDALAA: THERMAL ENERGY SHORTAGE EXPECTED THIS WINTER WWW.GOGO.MN PUBLISHED:2026/09/22      3 MONGOLIA'S INTERNATIONAL BOND MARKET: A STRONG 2026, BUT THE NEXT TEST LIES AHEAD WWW.CAPITALMARKETS.MN PUBLISHED:2026/09/22      4 STATE ENTERPRISE LISTINGS PITCHED TO 150 INVESTORS IN LONDON WWW.UBPOST.MN PUBLISHED:2026/09/22      5 MONGOLIAN STOCK MARKET MAIN INDICES SHOW POSITIVE MOVEMENT WWW.MONTSAME.MN PUBLISHED:2026/09/22      6 ARVAIKHEER THERMAL POWER PLANT FUNDING TO BE INCLUDED IN 2027 BUDGET WWW.GOGO.MN PUBLISHED:2026/09/22      7 PRESIDENT U.KHURELSUKH TO MEET WITH MONGOLIANS IN CHICAGO WWW.GOGO.MN PUBLISHED:2026/09/22      8 50 AVIATION PROFESSIONALS TO RECEIVE TRAINING IN CHINA WWW.MONTSAME.MN PUBLISHED:2026/09/21      9 CONTRACT FOR POWER PLANT EXPANSION TO BE CONCLUDED SOON WWW.MONTSAME.MN PUBLISHED:2026/09/21      10 MONGOLIAN FUEL IMPORTER SHUNKHAI OPENS 100 BILLION TUGRIK BOND SALE WWW.STREAMLINEFEED.CO.KE PUBLISHED:2026/09/21      Г.ТЭМҮҮЛЭНГ ХУУЛЬ ЗҮЙ, ДОТООД ХЭРГИЙН САЙДААР ТОМИЛЛОО WWW.EAGLE.MN НИЙТЭЛСЭН:2026/09/22     БОХИР УСНЫ ШУГАМ ХООЛОЙГ ШУУДУУ УХАЛГҮЙГЭЭР ДОТОРЛОХ, ШИНЭЧЛЭХ ТЕХНОЛОГИЙГ НЭВТРҮҮЛНЭ WWW.GOGO.MN НИЙТЭЛСЭН:2026/09/22     САМАР ТҮҮВЭЛ 5.4-27 САЯАР ТОРГОХ, 1-5 ЖИЛ ХОРИХ ЯЛААР ШИЙТГЭНЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/09/22     "СЭЛБЭ УХААЛАГ ХОТ”-ЫН БАРИЛГУУД ЭНЭ ОНД ХАЛААЛТАА АВНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/22     АВСТРАЛИЙН ПАРЛАМЕНТЫН ТӨЛӨӨЛӨГЧДИЙН ТАНХИМЫН ДАРГА МОНГОЛД АЛБАН ЁСНЫ АЙЛЧЛАЛ ХИЙХЭЭР ХҮРЭЛЦЭН ИРЛЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/09/22     НҮҮРС ТЭЭВРИЙН ХАМТЫН АЖИЛЛАГААГ ЭРЧИМЖҮҮЛНЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/09/22     ХАСБАНК ЕСБХБ-ТАЙ ЗЭЭЛИЙН ЭРСДЭЛ ХУВААЛЦАХ ГЭРЭЭНД ГАРЫН ҮСЭГ ЗУРЛАА WWW.GOGO.MN НИЙТЭЛСЭН:2026/09/22     ЭМЭЭЛТ ЭКО АЖ ҮЙЛДВЭРИЙН ПАРКИЙН ДЦС-ЫН БҮТЭЭН БАЙГУУЛАЛТЫН АЖИЛ ЭХЭЛЛЭЭ WWW.NEWS.MN НИЙТЭЛСЭН:2026/09/21     ЭРЧИМ ХҮЧНИЙ САЙД Б.НАЙДАЛАА: ЭНЭ ӨВӨЛ ДУЛААНЫ ЭРЧИМ ХҮЧ ДУТАГДАНА WWW.GOGO.MN НИЙТЭЛСЭН:2026/09/21     БОТАНИКИЙН ЦЭЦЭРЛЭГТ ХҮРЭЭЛЭНГИЙН ОРЧИМД БААВГАЙ ОРЖ ИРСЭН МЭДЭЭЛЭЛ БҮРТГЭГДЖЭЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2026/09/21    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

Damage to TPP-4’s eighth boiler repaired www.gogo.mn

After a temporary malfunction that cut generation, the eighth boiler at TPP-4 has been repaired and the plant has returned to full operation, officials said.
A fault affecting TPP-4’s eighth boiler, combined with coal freezing on the feeder side at the Buuruljuut power plant, previously reduced generation capacity, reportedly dropping output from 300 MW to 120 MW and prompting two days of electricity restrictions in Ulaanbaatar.
As of January 21, 2026, the repair work on the eighth boiler was completed and TPP-4 is now operating at its rated capacity of 670 MW. All turbines and generators are running at full output, authorities said.
Officials warned the public that the plant has limited backup equipment and that any new damage to the aging facility could again force supply restrictions. The eighth boiler’s repair had originally been scheduled for summer 2026.



Published Date:2026-01-22