1 CONSTRUCTION BEGINS ON POWER PLANT, WASTEWATER TREATMENT FACILITY AT EMEELT ECO INDUSTRIAL PARK WWW.MONTSAME.MN PUBLISHED:2026/09/22      2 B.NAIDALAA: THERMAL ENERGY SHORTAGE EXPECTED THIS WINTER WWW.GOGO.MN PUBLISHED:2026/09/22      3 MONGOLIA'S INTERNATIONAL BOND MARKET: A STRONG 2026, BUT THE NEXT TEST LIES AHEAD WWW.CAPITALMARKETS.MN PUBLISHED:2026/09/22      4 STATE ENTERPRISE LISTINGS PITCHED TO 150 INVESTORS IN LONDON WWW.UBPOST.MN PUBLISHED:2026/09/22      5 MONGOLIAN STOCK MARKET MAIN INDICES SHOW POSITIVE MOVEMENT WWW.MONTSAME.MN PUBLISHED:2026/09/22      6 ARVAIKHEER THERMAL POWER PLANT FUNDING TO BE INCLUDED IN 2027 BUDGET WWW.GOGO.MN PUBLISHED:2026/09/22      7 PRESIDENT U.KHURELSUKH TO MEET WITH MONGOLIANS IN CHICAGO WWW.GOGO.MN PUBLISHED:2026/09/22      8 50 AVIATION PROFESSIONALS TO RECEIVE TRAINING IN CHINA WWW.MONTSAME.MN PUBLISHED:2026/09/21      9 CONTRACT FOR POWER PLANT EXPANSION TO BE CONCLUDED SOON WWW.MONTSAME.MN PUBLISHED:2026/09/21      10 MONGOLIAN FUEL IMPORTER SHUNKHAI OPENS 100 BILLION TUGRIK BOND SALE WWW.STREAMLINEFEED.CO.KE PUBLISHED:2026/09/21      Г.ТЭМҮҮЛЭНГ ХУУЛЬ ЗҮЙ, ДОТООД ХЭРГИЙН САЙДААР ТОМИЛЛОО WWW.EAGLE.MN НИЙТЭЛСЭН:2026/09/22     БОХИР УСНЫ ШУГАМ ХООЛОЙГ ШУУДУУ УХАЛГҮЙГЭЭР ДОТОРЛОХ, ШИНЭЧЛЭХ ТЕХНОЛОГИЙГ НЭВТРҮҮЛНЭ WWW.GOGO.MN НИЙТЭЛСЭН:2026/09/22     САМАР ТҮҮВЭЛ 5.4-27 САЯАР ТОРГОХ, 1-5 ЖИЛ ХОРИХ ЯЛААР ШИЙТГЭНЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/09/22     "СЭЛБЭ УХААЛАГ ХОТ”-ЫН БАРИЛГУУД ЭНЭ ОНД ХАЛААЛТАА АВНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/22     АВСТРАЛИЙН ПАРЛАМЕНТЫН ТӨЛӨӨЛӨГЧДИЙН ТАНХИМЫН ДАРГА МОНГОЛД АЛБАН ЁСНЫ АЙЛЧЛАЛ ХИЙХЭЭР ХҮРЭЛЦЭН ИРЛЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/09/22     НҮҮРС ТЭЭВРИЙН ХАМТЫН АЖИЛЛАГААГ ЭРЧИМЖҮҮЛНЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/09/22     ХАСБАНК ЕСБХБ-ТАЙ ЗЭЭЛИЙН ЭРСДЭЛ ХУВААЛЦАХ ГЭРЭЭНД ГАРЫН ҮСЭГ ЗУРЛАА WWW.GOGO.MN НИЙТЭЛСЭН:2026/09/22     ЭМЭЭЛТ ЭКО АЖ ҮЙЛДВЭРИЙН ПАРКИЙН ДЦС-ЫН БҮТЭЭН БАЙГУУЛАЛТЫН АЖИЛ ЭХЭЛЛЭЭ WWW.NEWS.MN НИЙТЭЛСЭН:2026/09/21     ЭРЧИМ ХҮЧНИЙ САЙД Б.НАЙДАЛАА: ЭНЭ ӨВӨЛ ДУЛААНЫ ЭРЧИМ ХҮЧ ДУТАГДАНА WWW.GOGO.MN НИЙТЭЛСЭН:2026/09/21     БОТАНИКИЙН ЦЭЦЭРЛЭГТ ХҮРЭЭЛЭНГИЙН ОРЧИМД БААВГАЙ ОРЖ ИРСЭН МЭДЭЭЛЭЛ БҮРТГЭГДЖЭЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2026/09/21    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

B.Naidalaa: Thermal energy shortage expected this winter www.gogo.mn

The HUN Party caucus in Parliament heard and discussed a presentation on preparations for the upcoming winter season in the energy sector and the implementation of future energy policies.

Minister of Energy B.Naidalaa said the energy sector is working around the clock to ensure adequate preparations for the winter.

“Of the 20 boilers at thermal power plants scheduled for maintenance, nine have been fully repaired, while the remaining 11 are between 35% and 85% complete. Of the 12 turbogenerators scheduled for maintenance, eight have been fully repaired and the remaining four are 85% complete.

Overall, winter preparations in the energy sector are currently 79% complete on average.

Citizens frequently ask whether electricity restrictions will be imposed this coming winter. Experts project that peak electricity demand will reach 1,956 MW next year.

Installed generation capacity currently stands at 1,836 MW. To meet peak demand, 1,410 MW will be supplied by thermal power plants, 30 MW by wind power, 5 MW by hydropower, and 150 MW by battery energy storage systems. The remaining demand will be covered through electricity imports from our southern and northern neighbors.

There will be a shortage of thermal energy this winter. Thermal power plants are operating under excessive strain and at levels significantly above their current capacity. They are operating under heavy load and struggling to meet heating demand.

Ulaanbaatar is facing a shortage of thermal power capacity. The situation has reached a point where even the construction of several small buildings is difficult, let alone entire residential districts. Therefore, funding for the construction of Thermal Power Plant No. 5 has been included in next year’s budget.”



Published Date:2026-09-22