1 OUTSTANDING BANK LOANS RISE 14.3 PERCENT WWW.MONTSAME.MN PUBLISHED:2026/09/24      2 CENTRAL ASIA AND MONGOLIA GROWTH TO REMAIN ROBUST WWW.EBRD.COM PUBLISHED:2026/09/24      3 A NEW OIL STORAGE FACILITY WITH A CAPACITY OF 16,000 CUBIC METERS HAS BEEN PUT INTO OPERATION IN MONGOLIA WWW.OPEN.KG PUBLISHED:2026/09/24      4 RUSSIA, MONGOLIA FORM WORKING GROUP TO EXAMINE FEASIBILITY OF A WESTERN RAIL CORRIDOR WWW.RUSSIASPIVOTTOASIA.COM PUBLISHED:2026/09/24      5 MONGOLIA SUBMITS CANDIDACY FOR UN SECURITY COUNCIL NON-PERMANENT SEAT FOR 2048–2049 WWW.MONTSAME.MN PUBLISHED:2026/09/24      6 ‘GASOLINE DISRUPTION MAY LAST 2 TO 3 YEARS’ WWW.UBPOST.MN PUBLISHED:2026/09/24      7 MONGOLIA, AUSTRALIA DISCUSS INCREASING OYU TOLGOI RETURNS AND LOCALIZING TECHNOLOGY WWW.GOGO.MN PUBLISHED:2026/09/24      8 PLAN PRESENTED TO REACH USD 5.5 BILLION FOREIGN INVESTMENT WWW.MONTSAME.MN PUBLISHED:2026/09/23      9 COAL PYROLYSIS PLANT TO BE BUILT IN BAGANUUR THROUGH PUBLIC-PRIVATE PARTNERSHIP WWW.MONTSAME.MN PUBLISHED:2026/09/23      10 TEMUULEN APPOINTED MINISTER OF JUSTICE AND INTERNAL AFFAIRS WWW.MONTSAME.MN PUBLISHED:2026/09/23      ШҮҮХЭЭС НАЙРУУЛАГЧ Б.БААТАРТ ХИЛИЙН ХОРИГ ТАВЬЖЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/26     "ХӨРӨНГӨ ОРУУЛАГЧДЫН ГОМДЛЫГ 30 ХОНОГТ ШИЙДВЭРЛЭХ ШИНЭ ЗОХИЦУУЛАЛТ ХЭРЭГЖИЖ ЭХЭЛСЭН" WWW.NEWS.MN НИЙТЭЛСЭН:2026/09/24     “МЯНГАД НАР” 19.8 МВТ-ЫН НАРНЫ ЦАХИЛГААН СТАНЦЫН ГҮЙЦЭТГЭЛ 40 ХУВЬТАЙ БАЙНА WWW.EAGLE.MN НИЙТЭЛСЭН:2026/09/24     ГОВИЙН БҮСЭД ЗАРЛАСАН СЭРГЭЭГДЭХ ЭРЧИМ ХҮЧНИЙ АУКЦИОНД ГУРВАН КОМПАНИЙН ХАМТАРСАН ТҮНШЛЭЛ ШАЛГАРЛАА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/24     ОРОН СУУЦНЫ ЗАЛИЛАГЧИД 2,779 ХҮНД 211.1 ТЭРБУМ ТӨГРӨГИЙН ХОХИРОЛ УЧРУУЛЖЭЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2026/09/24     ИПОТЕКИЙН ЗЭЭЛИЙН ХҮСЭЛТҮҮД 7-8 ЖИЛ ХҮЛЭЭХ ООЧЕР ҮҮСЧЭЭ WWW.NEWS.MN НИЙТЭЛСЭН:2026/09/24     ХӨРӨНГӨ ОРУУЛАГЧДЫН ГОМДОЛ ШИЙДВЭРЛЭЛТИЙГ ХӨРӨНГӨ ОРУУЛАЛТ, ХУДАЛДААНЫ ГАЗАРТ ШИЛЖҮҮЛЛЭЭ WWW.GOGO.MN НИЙТЭЛСЭН:2026/09/24     ЕРӨНХИЙЛӨГЧ У.ХҮРЭЛСҮХ НҮБ-ЫН ЕРӨНХИЙ НАРИЙН БИЧГИЙН ДАРГАТАЙ УУЛЗЛАА WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/09/24     Т.ДОРЖХАНД: СЭРГЭЭГДЭХ ЭРЧИМ ХҮЧ, ДАТА ТӨВ ЗЭРЭГ 5 САЛБАРТ ГАДНЫН ХӨРӨНГӨ ОРУУЛАЛТ ТАТАХ БОДЛОГО БАРИМТАЛНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/23     Ц.САНДАГ-ОЧИР: 2028 ОНД 600 МЯНГАН ТОНН САЙЖРУУЛСАН ТҮЛШ НИЙЛҮҮЛЭХ ХҮЧИН ЧАДАЛТАЙ ҮЙЛДВЭР АШИГЛАЛТАД ОРУУЛНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/23    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

Operational update - 3D seismic campaign www.petromatadgroup.com

Seismic Acquisition Campaign

· The Company has signed the contract with BGP Inc (a divisions of China National Petroleum Company) for 3D and 2D seismic work in Blocks IV and V

· Preliminary mobilization and camp construction is already underway, allowing for immediate preparatory and long lead work to begin

· The 218km2 3D survey in Blocks IV and V will be the first ever 3D seismic acquired in western Mongolia

Further to its announcement of 4 October 2017, the Company is pleased to provide the timelines and details regarding the planned seismic work programme following the signing of the BGP contract, as detailed further below. The 220km2 3D survey will be the first ever 3D seismic acquired in western Mongolia. It will be conducted over the Tugrug Basin of eastern Block V, a longstanding priority basin for Petro Matad with a proven working petroleum system including mature source rock, reservoir rocks with good porosity & permeability and live hydrocarbon staining found in previous stratigraphic coring operations. 

The survey in the Tugrug Basin of Block V is expected to begin 3D data recording operations by mid-November and to be completed by mid-December, 2017. The crew will then begin a 150 line km infill 2D survey in the same area, extending outward from the 3D, to cover surrounding prospects and leads. No camp move is required so the 2D acquisition can begin seamlessly after completion of the 3D. As such, the estimated completion date of the Tugrug Basin 2D program will be two weeks after the 3D. 

Following completion of the Tugrug Basin 2D, the crew and camp will move 350km NW into Block IV to acquire a new 205 line km 2D seismic grid over the Khangai Basin. The Khangai Basin is a deep and prospective basin in north-central Block IV. It has been high graded following the results of the airborne FTG/HRAM survey of 2015. Whilst only two regional 2D seismic lines currently cross the Khangai Basin, these lines show adequate basinal depths (3500M-4000M) and prospective structural and stratigraphic configurations. The Khangai Basin 2D survey is projected to start in late December, and complete before the end of January 2018. 

Processing of both the 3D and 2D data has been contracted to Western GeCo (a division of Schlumberger Limited). The data will be delivered to the processors in near real time to allow maximum efficiency and return of processed data to the Company. Both the 3D and 2D programs are focused on high grading specific leads and prospects to potential drilling targets for the 2018/19 operational seasons.



Published Date:2017-10-25