1 DRAFT LAW ON AMENDMENTS TO THE GENERAL LAW ON TAXATION TO BE SUBMITTED TO PARLIAMENT WWW.MONTSAME.MN PUBLISHED:2025/06/05      2 THE FALL OF MONGOLIA’S COALITION GOVERNMENT WWW.THEDIPLOMAT.COM  PUBLISHED:2025/06/05      3 REVISED DRAFT LAW ON VALUE ADDED TAX TO BE SUBMITTED TO PARLIAMENT WWW.MONTSAME.MN PUBLISHED:2025/06/05      4 MONGOLIA SOLAR TENDER: 19.8 MW SOLAR PLANT FOR A STUNNING FUTURE WWW.PVKNOWHOW.COM  PUBLISHED:2025/06/05      5 GOLD PURCHASE BY MONGOLIA'S CENTRAL BANK DOWN 29.3 PCT IN 1ST 5 MONTHS OF 2025 WWW.XINHUANET.COM PUBLISHED:2025/06/05      6 FOOD AND AGRICULTURE ORGANIZATION OF THE UNITED NATIONS APPOINTS NEW REPRESENTATIVE IN MONGOLIA WWW.GOGO.MN PUBLISHED:2025/06/05      7 MONGOLIA:REGULATORY SANDBOX FRAMEWORK HAS BEEN AMENDED AND APPROVED WWW.ASIAINSURANCEREVIEW.COM  PUBLISHED:2025/06/05      8 RESOURCE-RICH MONGOLIA FACES POLITICAL UNCERTAINTY AFTER THE PRIME MINISTER RESIGNS WWW.APNEWS.COM PUBLISHED:2025/06/04      9 WHY MONGOLIA’S PRIME MINISTER RESIGNED WWW.TIME.COM PUBLISHED:2025/06/04      10 MONGOLIA PM RESIGNS AFTER SON'S LUXURY HOLIDAY STIRS PUBLIC FURY WWW.BBC.COM PUBLISHED:2025/06/04      ЕРӨНХИЙ САЙДАД НЭР ДЭВШИГЧДИЙГ МАРГААШ ТОДРУУЛНА WWW.ZINDAA.MN  НИЙТЭЛСЭН:2025/06/05     МОНГОЛЫН ИРГЭД ОХУ РУУ ЗОРЧИХДОО ШИНЭ ЖУРАМ МӨРДӨНӨ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/06/05     АЛБАДАН ГАРГАСАН ГАДААДЫН ИРГЭДИЙН ТОО ӨМНӨХ ОНЫ МӨН ҮЕЭС 71 ХУВИАР ӨСЖЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2025/06/05     МОНГОЛБАНК ЗАСГИЙН ГАЗРЫН “ХАМЖИГЧ”-ААР АЖИЛЛАСНЫ АЛДАГДАЛ 3.6 ИХ НАЯД ТӨГРӨГТ ХҮРЧЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2025/06/05     НИЙГМИЙН ДААТГАЛЫН БАГЦ ХУУЛЬ: АЖИЛ ОЛГОГЧДЫН ТӨЛДӨГ НДШ-ЭЭС 2 ХҮРТЭЛХ ХУВИЙГ ХӨНГӨЛНӨ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/05     ДОТООДЫН МАХ, МАХАН БҮТЭЭГДЭХҮҮНИЙ ҮНЭ ЖИЛИЙН 18.2 ХУВИАР ӨССӨН НЬ ИНФЛЯЦИД НӨЛӨӨЛЖЭЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/05     2026 ОНЫ АЗИ ТИВИЙН ШАТРЫН АВАРГА ШАЛГАРУУЛАХ ТЭМЦЭЭНИЙГ МОНГОЛ УЛСАД ЗОХИОН БАЙГУУЛНА WWW.EAGLE.MN НИЙТЭЛСЭН:2025/06/05     ШИНЭ ЕРӨНХИЙ САЙД ТОМИЛОХ МАН-ЫН БАГА ХУРАЛ МАРГААШ БОЛНО WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/04     Н.УЧРАЛ: ТӨК-ИЙН ЗАХИРГААНЫ ОРОН ТОО, ТУЗ-ИЙН ТООГ БУУРУУЛНА WWW.NEWS.MN НИЙТЭЛСЭН:2025/06/04     ТАТВАРАА ТӨЛӨӨГҮЙ 103 МЯНГАН ЭЗЭМШИГЧ БАЙНА, БАРАГДУУЛААГҮЙ ТОХИОЛДОЛД ЗАМЫН ХӨДӨЛГӨӨНД ОРОЛЦУУЛАХГҮЙ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/04    

Operational update - 3D seismic campaign www.petromatadgroup.com

Seismic Acquisition Campaign

· The Company has signed the contract with BGP Inc (a divisions of China National Petroleum Company) for 3D and 2D seismic work in Blocks IV and V

· Preliminary mobilization and camp construction is already underway, allowing for immediate preparatory and long lead work to begin

· The 218km2 3D survey in Blocks IV and V will be the first ever 3D seismic acquired in western Mongolia

Further to its announcement of 4 October 2017, the Company is pleased to provide the timelines and details regarding the planned seismic work programme following the signing of the BGP contract, as detailed further below. The 220km2 3D survey will be the first ever 3D seismic acquired in western Mongolia. It will be conducted over the Tugrug Basin of eastern Block V, a longstanding priority basin for Petro Matad with a proven working petroleum system including mature source rock, reservoir rocks with good porosity & permeability and live hydrocarbon staining found in previous stratigraphic coring operations. 

The survey in the Tugrug Basin of Block V is expected to begin 3D data recording operations by mid-November and to be completed by mid-December, 2017. The crew will then begin a 150 line km infill 2D survey in the same area, extending outward from the 3D, to cover surrounding prospects and leads. No camp move is required so the 2D acquisition can begin seamlessly after completion of the 3D. As such, the estimated completion date of the Tugrug Basin 2D program will be two weeks after the 3D. 

Following completion of the Tugrug Basin 2D, the crew and camp will move 350km NW into Block IV to acquire a new 205 line km 2D seismic grid over the Khangai Basin. The Khangai Basin is a deep and prospective basin in north-central Block IV. It has been high graded following the results of the airborne FTG/HRAM survey of 2015. Whilst only two regional 2D seismic lines currently cross the Khangai Basin, these lines show adequate basinal depths (3500M-4000M) and prospective structural and stratigraphic configurations. The Khangai Basin 2D survey is projected to start in late December, and complete before the end of January 2018. 

Processing of both the 3D and 2D data has been contracted to Western GeCo (a division of Schlumberger Limited). The data will be delivered to the processors in near real time to allow maximum efficiency and return of processed data to the Company. Both the 3D and 2D programs are focused on high grading specific leads and prospects to potential drilling targets for the 2018/19 operational seasons.



Published Date:2017-10-25