1 OYU TOLGOI SAYS DIVIDENDS WILL BEGIN IN 2027 WWW.MONTSAME.MN PUBLISHED:2026/11/11      2 ULAANBAATAR TO CUT MUNICIPAL TAX RATE ON SERVICES FROM 2% TO 1% WWW.MONTSAME.MN PUBLISHED:2026/11/11      3 ALASKA GUARDSMEN, MONGOLIAN FIRST RESPONDERS CONQUER RUGGED TERRAIN DURING UVS 2026 DISASTER RESPONSE EXERCISE WWW.AK.NG.MIL PUBLISHED:2026/11/11      4 PGL ANNOUNCES 2027 $1 MILLION TOURNAMENT IN MONGOLIA WWW.DUST2.US PUBLISHED:2026/11/11      5 STATE FLAG RAISED, NINE WHITE BANNERS DISPLAYED TO MARK CHINGGIS KHAAN’S BIRTH ANNIVERSARY WWW.MONTSAME.MN PUBLISHED:2026/11/11      6 MONGOLIAN ACADEMY OF SCIENCES RECEIVES THE ORDER OF CHINGGIS KHAAN WWW.MONTSAME.MN PUBLISHED:2026/11/11      7 CABINET TO DISCUSS WHISTLEBLOWER PROTECTION AMONG 20 AGENDA ITEMS WWW.MONTSAME.MN PUBLISHED:2026/11/11      8 TRUMP-BACKED CRITICAL MINERALS DEALS FACE GROWING PRESSURE AFTER BLUE WAVE WWW.BLOOMBERG.COM PUBLISHED:2026/11/09      9 TDB INVESTS USD 30 MILLION IN A THREE-YEAR TECHNOLOGY TRANSFORMATION WWW.MONTSAME.MN PUBLISHED:2026/11/09      10 MONGOLIA, US DISCUSS EXPANDING COOPERATION IN VOCATIONAL EDUCATION WWW.MONTSAME.MN PUBLISHED:2026/11/09      ХҮННҮ ХОТЫН ДЭД БҮТЦИЙГ БАРЬЖ БАЙНА WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/11/11     "АВЛИГА АЛБАН ТУШААЛ, ТӨРИЙН ӨМЧ ХӨРӨНГӨ, ТӨСӨВТЭЙ ХОЛБООТОЙ ЗҮЙЛИЙГ БАРИМТАД ТУЛГУУРЛАН ШҮГЭЛ ҮЛЭЭСЭН БОЛ ГҮТГЭХ ГЭМТ ХЭРЭГТ ХАМААРАХГҮЙ" WWW.IKON.MN НИЙТЭЛСЭН:2026/11/11     ИНФЛЯЦ АРАВДУГААР САРД 13.4 ХУВЬТАЙ ГАРЧ, ЭНЭ ОНЫ ХАМГИЙН ӨНДӨР ТҮВШИНД ХҮРЛЭЭ WWW.IKON.MN НИЙТЭЛСЭН:2026/11/11     ЕСӨН УЛСЫН 129 ИРГЭНИЙГ МОНГОЛ УЛСААС АЛБАДАН ГАРГАЖЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/11/11     ЕС, АРАВДУГААР САРД УЛСЫН ХЭМЖЭЭНД ДӨРВӨН ИРГЭН СУРАГГҮЙ АЛГА БОЛЖЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/11/11     РИО ТИНТО 2027 ОНД ОЮУ ТОЛГОЙГООС НОГДОЛ АШИГ ХУВААРИЛНА ГЭДГЭЭ БАТЛАВ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/11/11     ДУЛААН ГАРААШИЙГ ТАТВАРААС ЧӨЛӨӨЛӨХ ХУУЛИЙН ТӨСЛИЙГ ЗАСГИЙН ГАЗАР ДЭМЖЛЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/11/11     УЛААНБААТАР ХОТЫН ЗУРГААН ТӨРЛИЙН ТАТВАРЫГ 50 ХУВЬ БУУРУУЛАХ ХОТЫН ДАРГЫН САНААЧИЛГЫГ НИТХ ДЭМЖЛЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/11/09     “ЭРДЭНЭС ТАВАНТОЛГОЙ” ХК НЭГ ИХ НАЯД ТӨГРӨГИЙН НООГДОЛ АШИГ ТӨВЛӨРҮҮЛЭВ WWW.NEWS.MN НИЙТЭЛСЭН:2026/11/09     100 САЯАС ДЭЭШ ХАХУУЛЬ АВБАЛ БҮХ НАСААР ХОРИХ САНАЛЫГ 100 МЯНГАН ИРГЭН ДЭМЖЖЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/11/09    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

Oyu Tolgoi releases Q3 2017 results setting three operational records www.ot.mn

Ulaanbaatar, Mongolia - Oyu Tolgoi today released the latest edition of its scorecard updating its performance for the third quarter of 2017.

The All Injury Frequency Rate personal safety measure was 0.25 per 200,000 hours worked in the third quarter, including operations and the underground project. Maintaining its focus on safety, Oyu Tolgoi invested in 174,179 hours of safety training across its workforce of over 11,000 employees and contractors over the period.

Oyu Tolgoi continued its world class environmental performance, achieving water use performance at 0.406 cubic metres of water per tonne of ore processed, and a recycling rate of 86.5 per cent – the best among its peers in the industry.

Over the quarter, Oyu Tolgoi continued its positive contribution to the Umnugobi region, and Mongolia overall, through tax and other payments, procurement activities and investment in sustainable development projects. National procurement spend reached US$234mn in the third quarter of 2017, tax payments US$120.5mn and, cumulative in-country spend between 2010, when major construction on the mine began, to the end of September 2017 crossed US$6.7bn.

Gobi Oyu Development Support Fund continued to support sustainable development projects in Umnugobi. An expansion of the Khanbogd Heating Plant commenced to further support improvements in facilities and infrastructure in the local community.

Q3’17 Production

During the third quarter, Oyu Tolgoi set three operational records for total material mined, ore treated and average daily concentrator throughput.

In Q3’17, material mined increased 9.0 per cent over Q2’17, and ore treated increased 10.1 per cent over Q2’17. During Q2’17, the concentrator underwent a scheduled maintenance shutdown. Average daily concentrator throughput for Q3’17 of 115,400 tonnes increased 8.9 per cent over Q2’17. Copper production in Q3’17 was essentially flat, compared to Q2’17, while Q3’17 gold production increased 29.2 per cent over Q2’17 due to higher head grades from the medium-grade stockpile and Phase 4A. Higher gold grades during Q3’17 resulted in a 26.1 per cent increase in gold sales compared to Q2’17.

Turquoise Hill expects Oyu Tolgoi to produce 130,000 to 160,000 tonnes of copper and 100,000 to 140,000 ounces of gold in concentrates for 2017. Open-pit operations are expected to mine in Phases 4 and 6 during the year. In addition, stockpiled ore will continue to be processed during 2017.



Published Date:2017-10-27