Erdenet Mining Corporation raises its thermal power station capacity by 48 MW www.gogo.mn
To increase domestic energy production, Erdenet Mining Corporation (EMC) has upgraded the production capacity of its thermal power station by 48 MW. The company used to pay 225 billion MNT per year for 100 MW of electricity per hour.
EMC financed the installation of the four turbine generators powering the upgrade. The company expects to save 18.3 billion MNT with the capacity upgrade and lower its operational costs by 18.1 billion MNT.
Analysts also say that the upgrade will also help keep Ulaanbaatar’s energy system sustainable and consistently operational.
Published Date:2018-01-23