1 OYU TOLGOI SAYS DIVIDENDS WILL BEGIN IN 2027 WWW.MONTSAME.MN PUBLISHED:2026/11/11      2 ULAANBAATAR TO CUT MUNICIPAL TAX RATE ON SERVICES FROM 2% TO 1% WWW.MONTSAME.MN PUBLISHED:2026/11/11      3 ALASKA GUARDSMEN, MONGOLIAN FIRST RESPONDERS CONQUER RUGGED TERRAIN DURING UVS 2026 DISASTER RESPONSE EXERCISE WWW.AK.NG.MIL PUBLISHED:2026/11/11      4 PGL ANNOUNCES 2027 $1 MILLION TOURNAMENT IN MONGOLIA WWW.DUST2.US PUBLISHED:2026/11/11      5 STATE FLAG RAISED, NINE WHITE BANNERS DISPLAYED TO MARK CHINGGIS KHAAN’S BIRTH ANNIVERSARY WWW.MONTSAME.MN PUBLISHED:2026/11/11      6 MONGOLIAN ACADEMY OF SCIENCES RECEIVES THE ORDER OF CHINGGIS KHAAN WWW.MONTSAME.MN PUBLISHED:2026/11/11      7 CABINET TO DISCUSS WHISTLEBLOWER PROTECTION AMONG 20 AGENDA ITEMS WWW.MONTSAME.MN PUBLISHED:2026/11/11      8 TRUMP-BACKED CRITICAL MINERALS DEALS FACE GROWING PRESSURE AFTER BLUE WAVE WWW.BLOOMBERG.COM PUBLISHED:2026/11/09      9 TDB INVESTS USD 30 MILLION IN A THREE-YEAR TECHNOLOGY TRANSFORMATION WWW.MONTSAME.MN PUBLISHED:2026/11/09      10 MONGOLIA, US DISCUSS EXPANDING COOPERATION IN VOCATIONAL EDUCATION WWW.MONTSAME.MN PUBLISHED:2026/11/09      ХҮННҮ ХОТЫН ДЭД БҮТЦИЙГ БАРЬЖ БАЙНА WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/11/11     "АВЛИГА АЛБАН ТУШААЛ, ТӨРИЙН ӨМЧ ХӨРӨНГӨ, ТӨСӨВТЭЙ ХОЛБООТОЙ ЗҮЙЛИЙГ БАРИМТАД ТУЛГУУРЛАН ШҮГЭЛ ҮЛЭЭСЭН БОЛ ГҮТГЭХ ГЭМТ ХЭРЭГТ ХАМААРАХГҮЙ" WWW.IKON.MN НИЙТЭЛСЭН:2026/11/11     ИНФЛЯЦ АРАВДУГААР САРД 13.4 ХУВЬТАЙ ГАРЧ, ЭНЭ ОНЫ ХАМГИЙН ӨНДӨР ТҮВШИНД ХҮРЛЭЭ WWW.IKON.MN НИЙТЭЛСЭН:2026/11/11     ЕСӨН УЛСЫН 129 ИРГЭНИЙГ МОНГОЛ УЛСААС АЛБАДАН ГАРГАЖЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/11/11     ЕС, АРАВДУГААР САРД УЛСЫН ХЭМЖЭЭНД ДӨРВӨН ИРГЭН СУРАГГҮЙ АЛГА БОЛЖЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/11/11     РИО ТИНТО 2027 ОНД ОЮУ ТОЛГОЙГООС НОГДОЛ АШИГ ХУВААРИЛНА ГЭДГЭЭ БАТЛАВ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/11/11     ДУЛААН ГАРААШИЙГ ТАТВАРААС ЧӨЛӨӨЛӨХ ХУУЛИЙН ТӨСЛИЙГ ЗАСГИЙН ГАЗАР ДЭМЖЛЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/11/11     УЛААНБААТАР ХОТЫН ЗУРГААН ТӨРЛИЙН ТАТВАРЫГ 50 ХУВЬ БУУРУУЛАХ ХОТЫН ДАРГЫН САНААЧИЛГЫГ НИТХ ДЭМЖЛЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/11/09     “ЭРДЭНЭС ТАВАНТОЛГОЙ” ХК НЭГ ИХ НАЯД ТӨГРӨГИЙН НООГДОЛ АШИГ ТӨВЛӨРҮҮЛЭВ WWW.NEWS.MN НИЙТЭЛСЭН:2026/11/09     100 САЯАС ДЭЭШ ХАХУУЛЬ АВБАЛ БҮХ НАСААР ХОРИХ САНАЛЫГ 100 МЯНГАН ИРГЭН ДЭМЖЖЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/11/09    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

Oyu Tolgoi provides update on Mongolian domestic power solution www.gogo.mn

Ulaanbaatar, Mongolia - Oyu Tolgoi LLC wishes to clarify how it will deliver a long-term domestic power solution for Oyu Tolgoi in response to recent commentary.

On 15 February 2018 the Government of Mongolia cancelled the Southern Region Power Sector Cooperation Agreement (PSCA). The PSCA laid out a framework for cooperation between the Government of Mongolia and Oyu Tolgoi LLC to deliver a comprehensive energy plan for the South Gobi region. The Government of Mongolia’s primary intention was to develop the Tavan Tolgoi Power Project (TTPP), a new independent power plant at the Tavan Tolgoi coalfields, with Oyu Tolgoi as off-taker rather than owner.

The cost of building a power plant by Oyu Tolgoi is not included in the $5.3 billion investment approved for the development of the underground in May 2016.

The formation of the PCSA and prioritisation of discussions and evaluation of TTPP, at the specific request of the Government of Mongolia, resulted in the suspension of Oyu Tolgoi’s plans to start construction its own power plant in 2012. It also suspended Oyu Tolgoi’s obligation under the 2009 Investment Agreement to source power from within Mongolia by 2017 because it was recognised by the Government that the TTPP process would take longer than four years.

While TTPP is moving forward and despite considerable efforts by the Government’s Project Implementation Unit, MCS (TTPP’s domestic shareholder), Rio Tinto and Oyu Tolgoi to progress the project, its development has been slow due to limited investors and lenders appetite. TTPP currently lacks a lead investor to develop a viable technical and commercial proposal for Oyu Tolgoi to consider and it is unable to secure financing without a credible lead investor. Extensive negotiations and lender due diligence would still be required once those key issues are resolved. TTPP would therefore not be operational within four years.

Oyu Tolgoi has been reviewing other options that can be implemented within the four year timeframe, including refreshing previous plans to develop its own power plant at the Oyu Tolgoi mine site. In this context, Oyu Tolgoi will be engaging with the Minister of Energy to ensure the necessary permits and approvals are in place, including the application of permits that were submitted for renewal in January 2017, but which have not been granted, and to ensure overall alignment on the way forward.

The cost of building a power plant by Oyu Tolgoi is not included in the $5.3 billion investment approved for the development of the underground in May 2016.



Published Date:2018-02-23