1 D. DALAIJARGAL: URANIUM MINING PROJECT ADVANCES FAST WITH FRENCH FUNDING WWW.MONGOLIANMININGJOURNAL.COM  PUBLISHED:2025/12/05      2 MONGOLIA, INDIA TO ADVANCE STRATEGIC PARTNERSHIP IN DIGITAL DEVELOPMENT AND INNOVATION WWW.MONTSAME.MN PUBLISHED:2025/12/05      3 POPE LEO MEETS WITH THE PRESIDENT OF MONGOLIA WWW.VATICANNEWS.VA PUBLISHED:2025/12/05      4 NATIONAL PROTECTED AREA CONSULTATION TARGETS STRONGER RANGER SYSTEM WWW.MONTSAME.MN PUBLISHED:2025/12/05      5 RIO TINTO REVISES UP 2025 COPPER PRODUCTION FORECAST AS MONGOLIAN PROJECT ACCELERATES OPERATIONS WWW.NEWS.METAL.COM  PUBLISHED:2025/12/05      6 MONGOLIA CALLS PUBLIC HEARINGS AHEAD OF LIKELY PUSH TO RENEGOTIATE RIO TINTO TERMS ON GIANT COPPER MINE WWW.INTELLINEWS.COM PUBLISHED:2025/12/05      7 MONGOLIA RECEIVES HIGHEST NUMBER OF FOREIGN TOURISTS SINCE THE BEGINNING OF 2025 WWW.XINHUANET.COM PUBLISHED:2025/12/05      8 MONGOLIA SIGNALS READINESS TO CONTRIBUTE TO GLOBAL FIGHT AGAINST DESERTIFICATION WWW.QAZINFORM.COM PUBLISHED:2025/12/04      9 MONGOLIA’S FOREIGN EXCHANGE RESERVES REACH USD 6 BILLION WWW.MONTSAME.MN PUBLISHED:2025/12/04      10 FUEL SUPPLY STRENGTHENED AS DECEMBER PURCHASE ORDERS CONFIRMED WWW.MONTSAME.MN PUBLISHED:2025/12/04      МАЛ, ТЭЖЭЭВЭР АМЬТНЫ ТООЛЛОГО НЯМ ГАРАГТ ЭХЭЛНЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/12/05     Ш.РАДНААСЭД ЕРӨНХИЙ САЙДЫН АХЛАХ ЗӨВЛӨХ БОЛОВ WWW.NEWS.MN НИЙТЭЛСЭН:2025/12/05     АШИГТ МАЛТМАЛЫН 8 ЗӨВШӨӨРЛИЙН ХАРИУД ₮2.7 ТЭРБУМЫГ АВСАН Ш.ГАНХУЯГ, ӨГСӨН ЭДВАРД СҮРЭН НАРЫГ 1 САР ХОРИВ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/12/05     ЕРӨНХИЙЛӨГЧ У.ХҮРЭЛСҮХ ГЭГЭЭН ШИРЭЭТ УЛСЫН ТӨРИЙН ТЭРГҮҮНТЭЙ УУЛЗЛАА WWW.EAGLE.MN НИЙТЭЛСЭН:2025/12/05     ТАВАНТОЛГОЙ-ГАШУУНСУХАЙТ ЧИГЛЭЛИЙН ТӨМӨР ЗАМААР ТАВАН САРД 3 САЯ ТОНН НҮҮРС ТЭЭВЭРЛЭВ WWW.EGUUR.MN  НИЙТЭЛСЭН:2025/12/05     MONGOLIA FOCUS: МОНГОЛД ӨӨРИЙГӨӨ ЦЕНЗУРДЭХ ҮЗЭГДЭЛ НЭМЭГДСЭН НЬ АРДЧИЛЛЫН ЧАНАР ДОРОЙТОЖ БУЙН ИЛРЭЛ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/12/05     11575 АЙЛЫН ОРОН СУУЦ БАРИХ БОЛОМЖ БҮРДЭВ WWW.NEWS.MN  НИЙТЭЛСЭН:2025/12/05     Н.ЦЭРЭНСАМБУУ: ГАДААДЫН ХӨРӨНГӨ ОРУУЛАЛТААР БОР ТЭЭГИЙН ОРДЫГ ЭДИЙН ЗАСГИЙН ЭРГЭЛТЭД ОРУУЛНА WWW.EAGLE.MN НИЙТЭЛСЭН:2025/12/04     С.БЯМБАЦОГТ: ЗЭС ХАЙЛУУЛАХ ҮЙЛДВЭРИЙГ БАРИХ ХӨРӨНГӨ ОРУУЛАГЧИЙГ НЭЭЛТТЭЙ СОНГОН ШАЛГАРУУЛНА WWW.ITOIM.MN НИЙТЭЛСЭН:2025/12/04     NETFLIX-ИЙН МОНГОЛД ХИЙХ ШИНЭ НЭВТРҮҮЛГИЙН НӨЛӨӨ БА АЛГАН ДЭЭР ТАВЬСАН БОЛОМЖОО АШИГЛАХУЙ WWW.ITOIM.MN НИЙТЭЛСЭН:2025/12/04    

Largest underground chamber excavated in OT mine www.montsame.mn

An excavation work to create 12 800 cubic meter chamber or room in Oyu Tolgoi underground mine was completed in seven months of period, performed by 15 people. It laid a foundation to install ‘PC-1’ primary crusher in the underground mine.

On April 14, a ribbon cutting ceremony for the chamber was held with attendance of Armando Torres, CEO of Oyu Tolgoi LLC, Sh.Lkhamsuren, Deputy Minister of Construction and Urban Development, Arnaud Soirat, CEO of ‘Copper and Diamonds’ Company and B.Bayartsengel, Deputy Director of ‘Dayan Contract Mining’ Company, announcing its official launch.

When the underground mine starts its full operation, 4000 tons of ore will pass through the room daily. The primary crusher, the third strongest in the world underground mines with its capacity, has 9 meters in height and 300 tons in weight. The room will be central crushing site where rocks from underground mining fields are crashed to the size possible to carry them to the surface through a conveyor.

Mr N.Uuganbaatar, Mining engineer of Oyu Tolgoi underground mine said two crushers will work in the underground mine and the primary crusher will play crucial role to expand the underground mine.

The excavation work of underground mine is expected to be completed in December, 2018 and the installation work of the crusher will be performed in the first months of 2019. OT company plans to commence its underground production starting from June 20, 2020. Currently, more than 400 people are working in one shift in the underground mine.