1 OVERNIGHT TEMPERATURE DIPS TO MINUS 43 DEGREES CELSIUS IN W.MONGOLIA WWW.XINHUANET.COM PUBLISHED:2025/12/02      2 MONGOLIA, RUSSIA AGREE ON INTERREGIONAL COOPERATION UNTIL 2030 WWW.MONTSAME.MN PUBLISHED:2025/12/02      3 PRODUCTION OF KEY EQUIPMENT FOR MONGOLIA’S OIL REFINERY NEARS COMPLETION IN INDIA WWW.MONTSAME.MN PUBLISHED:2025/12/02      4 MONGOLIA AND CHINA STEP UP COOPERATION ON MEAT TRADE WWW.MONTSAME.MN PUBLISHED:2025/12/02      5 PRESIDENT KHURELSUKH WELCOMED BY PRESIDENT SERGIO MATTARELLA WWW.MONTSAME.MN PUBLISHED:2025/12/02      6 REAL ESTATE BROKERAGE FIRMS FACILITATE MNT 2.25 TRILLION IN PROPERTY SALES IN Q3 2025 WWW.MONTSAME.MN PUBLISHED:2025/12/02      7 TEAM MONGOLIA’S ATHLETIC PROWESS MAKES A SPLASH ON NETFLIX WWW.THEDIPLOMAT.COM PUBLISHED:2025/12/02      8 RUSSIA EXPECTS RATIFICATION OF EAEU TRADE AGREEMENT WITH MONGOLIA NO LATER THAN MID-2026 WWW.INTERFAX.COM PUBLISHED:2025/12/02      9 PRESIDENT KHURELSUKH ARRIVES IN ITALY FOR STATE VISIT WWW.MONTSAME.MN PUBLISHED:2025/12/01      10 INDIA WEIGHS MONGOLIAN COKING COAL IMPORTS DESPITE TRANSPORT HURDLES, SOURCE SAYS WWW.REUTERS.COM PUBLISHED:2025/12/01      ТЭЭВРИЙН ХЭРЭГСЛИЙН ШИЛЖИЛТ ХӨДӨЛГӨӨНИЙГ ЦАХИМААР ХИЙДЭГ БОЛЛОО WWW.ITOIM.MN НИЙТЭЛСЭН:2025/12/02     МОНГОЛ УЛС КАРЕК ХӨТӨЛБӨРИЙГ 2026 ОНД ДАРГАЛНА WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/12/02     "ЗЭЭЛ ТӨЛӨӨД ӨГӨӨЧ, ҮНЭ НЭМЭЭД ӨГӨӨЧ ГЭЭД СУУЖ БАЙНА. ӨӨРСДӨӨ ЮУ ХИЙХ ВЭ ГЭДЭГ НЬ ТОДОРХОЙГҮЙ" WWW.GOGO.MN НИЙТЭЛСЭН:2025/12/02     ЧГД, СБД-Т ЧӨЛӨӨЛСӨН ТАЛБАЙД БАРИХ 3800 АЙЛЫН ОРОН СУУЦЫГ 2027 ОНЫ III УЛИРАЛД ДУУСГАНА WWW.GOGO.MN НИЙТЭЛСЭН:2025/12/02     ИТАЛИ УЛСЫН ЕРӨНХИЙЛӨГЧ СЭРЖО МАТТАРЭЛЛА ИРЭХ ЖИЛ МОНГОЛД АЙЛЧИЛНА WWW.EAGLE.MN НИЙТЭЛСЭН:2025/12/02     ЕАЭЗХ-НЫ МОНГОЛТОЙ БАЙГУУЛСАН ХУДАЛДААНЫ ТҮР ХЭЛЭЛЦЭЭРИЙГ ИРЭХ ОНЫ ДУНД ҮЕЭС ХЭТРҮҮЛЭХГҮЙ БАТАЛНА WWW.ITOIM.MN НИЙТЭЛСЭН:2025/12/02     АВЛИГЫН АСУУДЛААР ГАДНЫН БАНКНЫ ХОРИГТ ОРСОН АХ, ДҮҮ ХОЁРЫН ОХИН КОМПАНИУД АЛТ, ГАЗРЫН ХОВОР ЭЛЕМЕНТИЙН ОРД ЭЗЭМШДЭГ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/12/02     РОЙТЕРС: ТЭЭВРИЙН ХҮНДРЭЛТЭЙ Ч МОНГОЛООС КОКСЖИХ НҮҮРСИЙГ ИМПОРТЛОХ АСУУДЛЫГ ЭНЭТХЭГ СУДАЛЖ БАЙНА WWW.ITOIM.MN НИЙТЭЛСЭН:2025/12/01     "ЭРДЭНЭС ТАВАНТОЛГОЙ" ХК ӨНГӨРСӨН САРД 2.4 ТОНН НҮҮРС БОРЛУУЛЖ, ТҮҮХЭН ДЭЭД АМЖИЛТАА ТОГТООЖЭЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/12/01     "ЦАГААН АЛТ" ХӨДӨЛГӨӨНӨӨР НООЛУУРЫН САЛБАРТ ₮28.7 ТЭРБУМЫН ХӨНГӨЛӨЛТТЭЙ ЗЭЭЛ ОЛГОЖЭЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/12/01    

RJP-Power vacuum: Rio Tinto scours for electricity to run giant Mongolia copper mine www.reuters.com

LONDON/ULAANBAATAR, Sept x (Reuters) - Mining giant Rio Tinto is racing against time to find the electricity needed to run its giant copper-gold mine in Mongolia, as wrangles with the government threaten a further setback for the flagship project.

Oyu Tolgoi, located in the South Gobi region near landlocked Mongolia’s southern border with China, is scheduled to complete a $5.3 billion underground expansion by 2022, creating one of the world’s biggest copper suppliers.

The project is set to transform Mongolia’s tiny economy and is key for Rio as the sole potential growth area for its copper business, but it has been beset by squabbles over cost overruns, claims of unpaid taxes and corruption allegations.

Now, Rio Tinto and the government are engaged in brinksmanship, not only about the location of the power plant required to run the mine, but also who should pay for it, risking further delays. (Can we explain the brinksmanship?, or else maybe drop it)

Oyu Tolgoi currently pays about $100 million a year to buy electricity from China for its open pit mine, but according to a landmark 2009 agreement, a domestic power source must be found for the project by 2022.

The Anglo-Australian miner has invited three state-owned Chinese contractors to submit bids to build a $1.5 billion power station, but has yet to make a final decision on a go-ahead or receive permits from the Mongolian government.

Even if Rio Tinto made a decision immediately, it would be virtually impossible to complete construction before 2023, said an industry source said on condition of anonymity.

HOW RELIABLE IS THIS SOURCE? CAN WE GET A QUOTE HERE OR GIVE MORE DETAILS?

PARTNERS AT ODDS
The complication for the power project is the Mongolian government’s desire to kickstart the nearby Tavan Tolgoi coking coal project, a massive resources that would xxxx xxxx, and which lies just xxxx km from Oyu Tolgoi.

Rio had originally planned to build its own power capacity, but it was encouraged by the government in 2014 to switch to a proposed plant at Tavan Tolgoi, where it would be an off-taker rather than investor.

Mongolia hoped Oyu Tolgoi’s involvement as a guaranteed customer would encourage investors to back the long-delayed coal mine, and this remains its preferred option, a government source familiar with the situation said.

However, in February this year, the government cancelled a 2014 agreement setting up a framework for co-operation on a shared power plant (why did they do this?)

Oyu Tolgoi, which pays about $100 million a year to buy electricity from China, is looking at options for a domestic power source, said Luke Colton, chief financial officer at Turquoise Hill Resources, the Rio-controlled unit that owns 66 percent of the project.

“An Oyu Tolgoi-based plant is currently the most feasible option that could deliver a domestic power source within the shortest timeframe,” said Colton, although he added that a Tavan Tolgoi plant remains an “important option”.

LOCAL POLITICS
Whatever Rio does, Mongolia is still determined to go ahead with the Tavan Tolgoi plant.

Otgochuluu Chuluuntseren, a former government official who also served as an Oyu Tolgoi board member, said it was the best option, although politics were getting in the way. (what does this mean? can we say briefly?)

“The main challenge remains the same: political instability and unpredictability,” he said.

Some government officials have expressed impatience about the delays, saying plant construction (at Oyu Tolgoi or Tavan Tolgoi?) could have started years ago.

“Oyu Tolgoi should stop playing with the Mongolian state!” Mongolia’s energy minister Davaasuren Tserenpil said on the ministry’s official Twitter account last month.

Mongolia’s cabinet will soon discuss how to deliver electricity to the scarcely-populated South Gobi. (how do we know this? Will this push the story forward?)

Rio, meanwhile, says its plan for a power plant at Oyu Tolgoi could add another $1.5 billion to the project’s total costs, far higher than originally envisaged back in xxxx. With the Mongolian government owning 34 percent of the project, it would also have to stump up $500 million.

Sun Jianli, spokesman with the Power Construction Corporation of China, one of the contractors, told Reuters the bid was “preliminary” and the project was still “very far away”. The others, China Machinery Engineering Corporation and Harbin Electric International , declined to comment.

If nothing his built on time Rio and Mongolia would face a decision on the domestic power requirement to keep Oyu Tolgoi running. Even if it continue dto take Chinese power, the bill would soar once underground operations get underway. (why? Source?) (Additional reporting by David Stanway in SHANGHAI and Melanie Burton in MELBOURNE Editing by XXXXX)



Published Date:2018-09-11