1 43,000 PASSENGER CARS IMPORTED IN THE FIRST HALF OF 2026 WWW.GOGO.MN PUBLISHED:2026/08/12      2 OIL REFINERY CONSTRUCTION TO BE INTENSIFIED AND LEGISLATIVE BOTTLENECKS REMOVED WWW.MONTSAME.MN PUBLISHED:2026/08/12      3 TEN YEARS OF 'HUNNU ROCK': THE HU LAUNCHES NEW WORLD TOUR WWW.MONTSAME.MN PUBLISHED:2026/08/12      4 NATIONAL AI COUNCIL ESTABLISHED TO DRIVE DIGITAL ECONOMY WWW.MONTSAME.MN PUBLISHED:2026/08/12      5 THE MAGIC OF MONGOLIA: WHY PEOPLE VISIT THE MOST SPARSELY POPULATED COUNTRY IN THE WORLD WWW.JACKSFLIGHTCLUB.COM PUBLISHED:2026/08/12      6 THE MOST EXPENSIVE MISTAKE MONGOLIAN COMPANIES KEEP MAKING AND CALLING IT A HIRING DECISION (BLOG) WWW.LAMBDA.GLOBAL PUBLISHED:2026/08/12      7 MONGOLIA SUCCESSFULLY TESTS INTERCITY FREIGHT TRANSPORT WITH HEAVY ELECTRIC TRUCKS FOR THE FIRST TIME WWW.OPEN.KG PUBLISHED:2026/08/12      8 MONGOLIA RATIONS GASOLINE AS FUEL SHORTAGES SEND DRIVERS INTO LONG LINES WWW.INTELLINEWS.COM PUBLISHED:2026/08/12      9 VIEWS EXCHANGED WITH ADB ON EDUCATION SECTOR REFORM AND COOPERATION WWW.MONTSAME.MN PUBLISHED:2026/08/12      10 “FOREIGNERS WHO LEARN ABOUT CHINGGIS KHAAN THROUGH HISTORY AND THE HU THROUGH MUSIC ARE BECOMING MORE INTERESTED IN THE MONGOLIAN LANGUAGE” WWW.GOGO.MN PUBLISHED:2026/08/12      Ц.САНДАГ-ОЧИР: МОНГОЛ УЛСЫН НИЙТ ГАЗАР НУТГИЙН 81.9 ХУВЬ ЦӨЛЖИЛТӨД ӨРТСӨН БАЙНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/08/12     МӨНГӨНИЙ БОДЛОГЫН ХҮҮГ 0.5 ХУВИАР ӨСГӨВ WWW.NEWS.MN НИЙТЭЛСЭН:2026/08/12     ШАТАХУУН ОЛГОДОГ ЗОХИЦУУЛАЛТЫГ БЯМБА ГАРАГААР ТАСАЛБАР БОЛГОНО WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/08/12     БАГАХАНГАЙ-ХӨШИГИЙН ХӨНДИЙ-ЭМЭЭЛТ ЧИГЛЭЛИЙН 214.9 КМ ТӨМӨР ЗАМ ИРЭХ САРД АШИГЛАЛТАД ОРНО WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/08/12     "НЕФТЬ БОЛОВСРУУЛАХ ҮЙЛДВЭРИЙГ ТҮШИГЛЭН ТЕХНОЛОГИЙН ПАРК БАЙГУУЛНА" WWW.NEWS.MN НИЙТЭЛСЭН:2026/08/12     “БАЯНХОШУУ ДЭД ТӨВ”-ИЙН ДАРААГИЙН 150 АЙЛЫН БАРИЛГЫН АЖИЛ 92 ХУВЬТАЙ БАЙНА WWW.GOGO.MN НИЙТЭЛСЭН:2026/08/12     НАЙМДУГААР САРЫН ШАТАХУУНЫ ХЭРЭГЛЭЭГ БҮРЭН ХАНГАХ НӨХЦӨЛ БҮРДЖЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/08/12     БАГАХАНГАЙ -ХӨШИГИЙН ХӨНДИЙ - ЭМЭЭЛТ ЧИГЛЭЛИЙН ТӨМӨР ЗАМЫН ТӨСЛИЙГ ХЭЛЭЛЦЭНЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/08/12     МОНГОЛ ДАХЬ ГАДААД АЖИЛЧДЫН ТОО 43 ХУВИАР ӨСЖЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/08/12     "ШАТАХУУНЫ НӨӨЦГҮЙ БОЛСОН УЛС, ОРНУУД ЗАЙНААС АЖИЛЛАХ БОДЛОГО ХЭРЭГЖҮҮЛЖ ЭХЭЛСЭН" WWW.GOGO.MN НИЙТЭЛСЭН:2026/08/12    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

Mongolia mining minister rules out Oyu Tolgoi deal changes www.ft.com

Mongolia’s minister of mining and heavy industry has appeared to rule out making changes to the investment agreements that underpin the development of the giant Oyu Tolgoi copper project.

Dolgorsürengiin Sumyaabazar told the country’s leading TV channel MNB that the $5.3bn underground expansion of the mine should be based on the existing contracts between the government and Anglo Australian miner Rio Tinto.

“As the minister of this sector I see that further investment in the mining sector directly depends on this project,” according to a translation of the TV transcript. “Various people with various backgrounds express their own opinions related to Oyu Tolgoi agreements. But we won’t terminate the Oyu Tolgoi agreement.”

His comments come after a parliamentary working group delivered a report on Oyu Tolgoi to the country’s National Security Council that recommended scrapping one of the agreements and amending another.

The deals in question set the initial ground rules for the development of the project in the Gobi desert and the underground expansion, which is running behind schedule.

“For our country whose fragile economy is based on the mining, we need to improve, sit behind the table and negotiate, make proper steps to support each other to successfully carry this large project,” said Mr Sumyaabazar.

He added that the expansion of Oyu Tologi needed to be seen in a wider context, citing Mongolia’s plans to float its Tavan Tolgoi coal project on a foreign stock exchange.

“During this delicate time along with current issues, we need to properly think and deliver the decision on Tavan Tolgoi project and Oyu Tolgoi project,” he said.

Arnaud Soirat, the head of Rio’s copper and diamonds business, welcomed the decision by the ministry of mining. Separately, he also provided some more details on the delays to the underground expansion at Oyu Tolgoi.

“In a $5.3bn construction project you can expect some challenges, and difficult ground conditions have slowed progress in some areas of the underground development,” he told delegates at a major copper conference in Chile.

“We’re adjusting our mine design as we progress — integrating new geotechnical data than was available during surface drilling. This data reveals there are areas where the strength of the rock is more variable than anticipated in the feasibility study requiring potentially significant design changes.”

“We welcome the Mongolian Government’s recognition of the importance of these agreements, with the Minister of Mining highlighting in comments overnight that they not only underpin the OT project but the strong economic future mining can deliver for the country.”

Rio is expected to provide an update on the underground expansion, detailing the length and cost of the overrun, when it reports interim results in August.

Oyu Tolgoi is one of Rio’s most important growth assets. It controls the mine through a majority stake in a Canadian-listed company called Turquoise Hill.



Published Date:2019-04-10