1 DRAFT LAW ON AMENDMENTS TO THE GENERAL LAW ON TAXATION TO BE SUBMITTED TO PARLIAMENT WWW.MONTSAME.MN PUBLISHED:2025/06/05      2 THE FALL OF MONGOLIA’S COALITION GOVERNMENT WWW.THEDIPLOMAT.COM  PUBLISHED:2025/06/05      3 REVISED DRAFT LAW ON VALUE ADDED TAX TO BE SUBMITTED TO PARLIAMENT WWW.MONTSAME.MN PUBLISHED:2025/06/05      4 MONGOLIA SOLAR TENDER: 19.8 MW SOLAR PLANT FOR A STUNNING FUTURE WWW.PVKNOWHOW.COM  PUBLISHED:2025/06/05      5 GOLD PURCHASE BY MONGOLIA'S CENTRAL BANK DOWN 29.3 PCT IN 1ST 5 MONTHS OF 2025 WWW.XINHUANET.COM PUBLISHED:2025/06/05      6 FOOD AND AGRICULTURE ORGANIZATION OF THE UNITED NATIONS APPOINTS NEW REPRESENTATIVE IN MONGOLIA WWW.GOGO.MN PUBLISHED:2025/06/05      7 MONGOLIA:REGULATORY SANDBOX FRAMEWORK HAS BEEN AMENDED AND APPROVED WWW.ASIAINSURANCEREVIEW.COM  PUBLISHED:2025/06/05      8 RESOURCE-RICH MONGOLIA FACES POLITICAL UNCERTAINTY AFTER THE PRIME MINISTER RESIGNS WWW.APNEWS.COM PUBLISHED:2025/06/04      9 WHY MONGOLIA’S PRIME MINISTER RESIGNED WWW.TIME.COM PUBLISHED:2025/06/04      10 MONGOLIA PM RESIGNS AFTER SON'S LUXURY HOLIDAY STIRS PUBLIC FURY WWW.BBC.COM PUBLISHED:2025/06/04      ЕРӨНХИЙ САЙДАД НЭР ДЭВШИГЧДИЙГ МАРГААШ ТОДРУУЛНА WWW.ZINDAA.MN  НИЙТЭЛСЭН:2025/06/05     МОНГОЛЫН ИРГЭД ОХУ РУУ ЗОРЧИХДОО ШИНЭ ЖУРАМ МӨРДӨНӨ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/06/05     АЛБАДАН ГАРГАСАН ГАДААДЫН ИРГЭДИЙН ТОО ӨМНӨХ ОНЫ МӨН ҮЕЭС 71 ХУВИАР ӨСЖЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2025/06/05     МОНГОЛБАНК ЗАСГИЙН ГАЗРЫН “ХАМЖИГЧ”-ААР АЖИЛЛАСНЫ АЛДАГДАЛ 3.6 ИХ НАЯД ТӨГРӨГТ ХҮРЧЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2025/06/05     НИЙГМИЙН ДААТГАЛЫН БАГЦ ХУУЛЬ: АЖИЛ ОЛГОГЧДЫН ТӨЛДӨГ НДШ-ЭЭС 2 ХҮРТЭЛХ ХУВИЙГ ХӨНГӨЛНӨ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/05     ДОТООДЫН МАХ, МАХАН БҮТЭЭГДЭХҮҮНИЙ ҮНЭ ЖИЛИЙН 18.2 ХУВИАР ӨССӨН НЬ ИНФЛЯЦИД НӨЛӨӨЛЖЭЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/05     2026 ОНЫ АЗИ ТИВИЙН ШАТРЫН АВАРГА ШАЛГАРУУЛАХ ТЭМЦЭЭНИЙГ МОНГОЛ УЛСАД ЗОХИОН БАЙГУУЛНА WWW.EAGLE.MN НИЙТЭЛСЭН:2025/06/05     ШИНЭ ЕРӨНХИЙ САЙД ТОМИЛОХ МАН-ЫН БАГА ХУРАЛ МАРГААШ БОЛНО WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/04     Н.УЧРАЛ: ТӨК-ИЙН ЗАХИРГААНЫ ОРОН ТОО, ТУЗ-ИЙН ТООГ БУУРУУЛНА WWW.NEWS.MN НИЙТЭЛСЭН:2025/06/04     ТАТВАРАА ТӨЛӨӨГҮЙ 103 МЯНГАН ЭЗЭМШИГЧ БАЙНА, БАРАГДУУЛААГҮЙ ТОХИОЛДОЛД ЗАМЫН ХӨДӨЛГӨӨНД ОРОЛЦУУЛАХГҮЙ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/04    

Petro Matad signs rig contracts for 2019 drilling program in Mongolia www.energy-pedia.com

Petro Matad, the AIM-quoted Mongolian oil explorer, has signed contracts for two rigs for its upcoming 2019 four well drilling programme.

Highlights:

Four well fully-funded programme remains on track for completion in 2019
Two rig contracts signed and both rigs in close proximity to Block XX
Heron 1 and Red Deer 1 wells expected to spud in July
Spudding of Gazelle 1 will follow completion of drilling at Heron 1
Rig contracts allow for possibility of immediate appraisal of any discovery
Rig contracts signed

The Company has contracted DQE International, Mongolia's most experienced and active drilling operator, for its Rig 40105, to drill the Heron 1 and Gazelle 1 wells in the north of Block XX. The contract gives the Company the option to drill an additional well to allow for immediate appraisal of any discovery made during the 2019 drilling programme. Any discovery will be tested using a separate workover rig. The rig was drilling in neighbouring Block XIX up until the end of the last drilling season, so mobilisation will be short and logistically straightforward.

The second contract is with Daton Petroleum Engineering and Oilfield Service LLC, for their Rig DXZ1, to drill the Red Deer 1 well in the south of Block XX. The contract gives Petro Matad the option to drill a second well, to either appraise any discovery made in Red Deer 1 or for drilling in Block V in western Mongolia. Any testing operations will be performed by a separate workover rig. Daton's rig was working until the end of 2018 and is currently located approx. 125km east of the Red Deer location, so mobilisation to Block XX will be relatively short.

Updated drilling schedule

The Company expects to spud Heron 1 in early July. The spud date has been moved back to allow for certain electrical and safety modifications to the rig ahead of drilling.

Heron 1 will be drilled to a planned total depth (TD) of 3,050m and will take approx. 40 days to drill and log. On completion of operations at Heron, the rig will immediately move to the Gazelle 1 location. Gazelle 1 will take approx. 35 days to drill and log. The planned TD is 2,500m.

Red Deer 1 is expected to spud in July and is forecast to take 35 days to drill and log. The planned TD of the well is 2,100m. On completion of drilling and depending on the success of the well, the Company will then take the decision to either drill a further well at Red Deer; move the rig to drill a well in Block V; or focus on activities in the north of Block XX.

Running two rigs, with a separate workover rig for any testing operations, gives the Company sufficient time to complete its 2019 four well drilling campaign before the winter operational shutdown late in Q4.

Heron Prospect

The Company has recently secured access to a high-quality 3D seismic data set which covers the northern part of Block XX. This data, along with recently reprocessed 2D seismic data, clearly shows the Heron Prospect to be a southerly extension of the proven oil-bearing structure drilled by the T19-46-3 discovery well in Block XIX. The latest mapping shows the majority of the structure, including the crest of the trap, lying in Block XX. The Heron Prospect is estimated to have mean recoverable prospective resource potential of 25 MMbo. Heron 1 will be located 1.1km south of the T19-46-3 oil well and is prognosed to encounter the top of the primary reservoir targets at approx. 2800m.

Gazelle Prospect

The Gazelle Prospect is located on the south-western flank of the Tamsag Basin, which is the primary source kitchen charging the Block XIX discoveries. The Gazelle 1 well will be drilled 5km west of Heron 1 and 4.5km southwest of the T19-46-1 oil well. The mean prospective recoverable resource assessment for the Gazelle Prospect is 13 MMbo.

Red Deer Prospect

The Red Deer 1 well will target a basin centre, fault bounded, structural closure in the southern part of Block XX. The mean prospective recoverable resource assessment for the Red Deer Prospect is 48 MMbo.

Mike Buck, the CEO of Petro Matad said:

'We are pleased to announce the signing of the two rig contracts which marks a major milestone for the four well drilling programme scheduled for 2019. The contracts secured allow for simultaneous drilling of prospects and immediate appraisal in the event of a discovery which could be transformational for the company. It is an exciting year ahead for Petro Matad and we look forward to working with our contractors to deliver value for our shareholders.'

Original article link

Source: Petro Matad



Published Date:2019-04-16