1 OUTSTANDING BANK LOANS RISE 14.3 PERCENT WWW.MONTSAME.MN PUBLISHED:2026/09/24      2 CENTRAL ASIA AND MONGOLIA GROWTH TO REMAIN ROBUST WWW.EBRD.COM PUBLISHED:2026/09/24      3 A NEW OIL STORAGE FACILITY WITH A CAPACITY OF 16,000 CUBIC METERS HAS BEEN PUT INTO OPERATION IN MONGOLIA WWW.OPEN.KG PUBLISHED:2026/09/24      4 RUSSIA, MONGOLIA FORM WORKING GROUP TO EXAMINE FEASIBILITY OF A WESTERN RAIL CORRIDOR WWW.RUSSIASPIVOTTOASIA.COM PUBLISHED:2026/09/24      5 MONGOLIA SUBMITS CANDIDACY FOR UN SECURITY COUNCIL NON-PERMANENT SEAT FOR 2048–2049 WWW.MONTSAME.MN PUBLISHED:2026/09/24      6 ‘GASOLINE DISRUPTION MAY LAST 2 TO 3 YEARS’ WWW.UBPOST.MN PUBLISHED:2026/09/24      7 MONGOLIA, AUSTRALIA DISCUSS INCREASING OYU TOLGOI RETURNS AND LOCALIZING TECHNOLOGY WWW.GOGO.MN PUBLISHED:2026/09/24      8 PLAN PRESENTED TO REACH USD 5.5 BILLION FOREIGN INVESTMENT WWW.MONTSAME.MN PUBLISHED:2026/09/23      9 COAL PYROLYSIS PLANT TO BE BUILT IN BAGANUUR THROUGH PUBLIC-PRIVATE PARTNERSHIP WWW.MONTSAME.MN PUBLISHED:2026/09/23      10 TEMUULEN APPOINTED MINISTER OF JUSTICE AND INTERNAL AFFAIRS WWW.MONTSAME.MN PUBLISHED:2026/09/23      ШҮҮХЭЭС НАЙРУУЛАГЧ Б.БААТАРТ ХИЛИЙН ХОРИГ ТАВЬЖЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/26     "ХӨРӨНГӨ ОРУУЛАГЧДЫН ГОМДЛЫГ 30 ХОНОГТ ШИЙДВЭРЛЭХ ШИНЭ ЗОХИЦУУЛАЛТ ХЭРЭГЖИЖ ЭХЭЛСЭН" WWW.NEWS.MN НИЙТЭЛСЭН:2026/09/24     “МЯНГАД НАР” 19.8 МВТ-ЫН НАРНЫ ЦАХИЛГААН СТАНЦЫН ГҮЙЦЭТГЭЛ 40 ХУВЬТАЙ БАЙНА WWW.EAGLE.MN НИЙТЭЛСЭН:2026/09/24     ГОВИЙН БҮСЭД ЗАРЛАСАН СЭРГЭЭГДЭХ ЭРЧИМ ХҮЧНИЙ АУКЦИОНД ГУРВАН КОМПАНИЙН ХАМТАРСАН ТҮНШЛЭЛ ШАЛГАРЛАА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/24     ОРОН СУУЦНЫ ЗАЛИЛАГЧИД 2,779 ХҮНД 211.1 ТЭРБУМ ТӨГРӨГИЙН ХОХИРОЛ УЧРУУЛЖЭЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2026/09/24     ИПОТЕКИЙН ЗЭЭЛИЙН ХҮСЭЛТҮҮД 7-8 ЖИЛ ХҮЛЭЭХ ООЧЕР ҮҮСЧЭЭ WWW.NEWS.MN НИЙТЭЛСЭН:2026/09/24     ХӨРӨНГӨ ОРУУЛАГЧДЫН ГОМДОЛ ШИЙДВЭРЛЭЛТИЙГ ХӨРӨНГӨ ОРУУЛАЛТ, ХУДАЛДААНЫ ГАЗАРТ ШИЛЖҮҮЛЛЭЭ WWW.GOGO.MN НИЙТЭЛСЭН:2026/09/24     ЕРӨНХИЙЛӨГЧ У.ХҮРЭЛСҮХ НҮБ-ЫН ЕРӨНХИЙ НАРИЙН БИЧГИЙН ДАРГАТАЙ УУЛЗЛАА WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/09/24     Т.ДОРЖХАНД: СЭРГЭЭГДЭХ ЭРЧИМ ХҮЧ, ДАТА ТӨВ ЗЭРЭГ 5 САЛБАРТ ГАДНЫН ХӨРӨНГӨ ОРУУЛАЛТ ТАТАХ БОДЛОГО БАРИМТАЛНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/23     Ц.САНДАГ-ОЧИР: 2028 ОНД 600 МЯНГАН ТОНН САЙЖРУУЛСАН ТҮЛШ НИЙЛҮҮЛЭХ ХҮЧИН ЧАДАЛТАЙ ҮЙЛДВЭР АШИГЛАЛТАД ОРУУЛНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/23    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

Russia & China to ink deal for construction of two nuclear reactors www.rt.com

A contract for the development of two new units at China’s Xudabao nuclear power plant will soon be signed by Moscow and Beijing. It is part of the biggest nuclear energy deal between the two countries in a decade.
Under the deal, two Russian VVER-1200 units worth a total of $1.7 billion will be built by China National Nuclear Corporation (CNNC) and Russia’s State Atomic Energy Corporation (Rosatom).

Construction of Unit 3 of the Xudabao nuclear power plant is expected to start in October 2021, according to CNNC. It will be followed by Unit 4 in August 2022. The single unit construction period lasts 69 months, and the construction interval between the two units is 10 months.

Russia and China have been strengthening ties in the nuclear energy sector lately. Apart from the Xudabao nuclear plant units, Rosatom is building nuclear units for the Tianwan nuclear power plant, which is one of the biggest joint projects of Russian-Chinese economic cooperation. The first two of its units, each with a capacity of 1,000MW, were launched in 2007. Unit 3 began operations in 2017, and the reactor at the latest, fourth unit was launched at minimum capacity in September last year after the fuel loading was finished ahead of schedule.

The nuclear plants will help to meet China’s goal of reducing greenhouse gas emissions, according to Joseph Jacobelli, an independent energy analyst and Asia-Pacific CEO of clean energy producer Joule Power. They will provide air pollution-free energy at a lower cost to consumers, he explained to China Daily.



Published Date:2019-05-16