1 D. DALAIJARGAL: URANIUM MINING PROJECT ADVANCES FAST WITH FRENCH FUNDING WWW.MONGOLIANMININGJOURNAL.COM  PUBLISHED:2025/12/05      2 MONGOLIA, INDIA TO ADVANCE STRATEGIC PARTNERSHIP IN DIGITAL DEVELOPMENT AND INNOVATION WWW.MONTSAME.MN PUBLISHED:2025/12/05      3 POPE LEO MEETS WITH THE PRESIDENT OF MONGOLIA WWW.VATICANNEWS.VA PUBLISHED:2025/12/05      4 NATIONAL PROTECTED AREA CONSULTATION TARGETS STRONGER RANGER SYSTEM WWW.MONTSAME.MN PUBLISHED:2025/12/05      5 RIO TINTO REVISES UP 2025 COPPER PRODUCTION FORECAST AS MONGOLIAN PROJECT ACCELERATES OPERATIONS WWW.NEWS.METAL.COM  PUBLISHED:2025/12/05      6 MONGOLIA CALLS PUBLIC HEARINGS AHEAD OF LIKELY PUSH TO RENEGOTIATE RIO TINTO TERMS ON GIANT COPPER MINE WWW.INTELLINEWS.COM PUBLISHED:2025/12/05      7 MONGOLIA RECEIVES HIGHEST NUMBER OF FOREIGN TOURISTS SINCE THE BEGINNING OF 2025 WWW.XINHUANET.COM PUBLISHED:2025/12/05      8 MONGOLIA SIGNALS READINESS TO CONTRIBUTE TO GLOBAL FIGHT AGAINST DESERTIFICATION WWW.QAZINFORM.COM PUBLISHED:2025/12/04      9 MONGOLIA’S FOREIGN EXCHANGE RESERVES REACH USD 6 BILLION WWW.MONTSAME.MN PUBLISHED:2025/12/04      10 FUEL SUPPLY STRENGTHENED AS DECEMBER PURCHASE ORDERS CONFIRMED WWW.MONTSAME.MN PUBLISHED:2025/12/04      МАЛ, ТЭЖЭЭВЭР АМЬТНЫ ТООЛЛОГО НЯМ ГАРАГТ ЭХЭЛНЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/12/05     Ш.РАДНААСЭД ЕРӨНХИЙ САЙДЫН АХЛАХ ЗӨВЛӨХ БОЛОВ WWW.NEWS.MN НИЙТЭЛСЭН:2025/12/05     АШИГТ МАЛТМАЛЫН 8 ЗӨВШӨӨРЛИЙН ХАРИУД ₮2.7 ТЭРБУМЫГ АВСАН Ш.ГАНХУЯГ, ӨГСӨН ЭДВАРД СҮРЭН НАРЫГ 1 САР ХОРИВ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/12/05     ЕРӨНХИЙЛӨГЧ У.ХҮРЭЛСҮХ ГЭГЭЭН ШИРЭЭТ УЛСЫН ТӨРИЙН ТЭРГҮҮНТЭЙ УУЛЗЛАА WWW.EAGLE.MN НИЙТЭЛСЭН:2025/12/05     ТАВАНТОЛГОЙ-ГАШУУНСУХАЙТ ЧИГЛЭЛИЙН ТӨМӨР ЗАМААР ТАВАН САРД 3 САЯ ТОНН НҮҮРС ТЭЭВЭРЛЭВ WWW.EGUUR.MN  НИЙТЭЛСЭН:2025/12/05     MONGOLIA FOCUS: МОНГОЛД ӨӨРИЙГӨӨ ЦЕНЗУРДЭХ ҮЗЭГДЭЛ НЭМЭГДСЭН НЬ АРДЧИЛЛЫН ЧАНАР ДОРОЙТОЖ БУЙН ИЛРЭЛ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/12/05     11575 АЙЛЫН ОРОН СУУЦ БАРИХ БОЛОМЖ БҮРДЭВ WWW.NEWS.MN  НИЙТЭЛСЭН:2025/12/05     Н.ЦЭРЭНСАМБУУ: ГАДААДЫН ХӨРӨНГӨ ОРУУЛАЛТААР БОР ТЭЭГИЙН ОРДЫГ ЭДИЙН ЗАСГИЙН ЭРГЭЛТЭД ОРУУЛНА WWW.EAGLE.MN НИЙТЭЛСЭН:2025/12/04     С.БЯМБАЦОГТ: ЗЭС ХАЙЛУУЛАХ ҮЙЛДВЭРИЙГ БАРИХ ХӨРӨНГӨ ОРУУЛАГЧИЙГ НЭЭЛТТЭЙ СОНГОН ШАЛГАРУУЛНА WWW.ITOIM.MN НИЙТЭЛСЭН:2025/12/04     NETFLIX-ИЙН МОНГОЛД ХИЙХ ШИНЭ НЭВТРҮҮЛГИЙН НӨЛӨӨ БА АЛГАН ДЭЭР ТАВЬСАН БОЛОМЖОО АШИГЛАХУЙ WWW.ITOIM.MN НИЙТЭЛСЭН:2025/12/04    

President visits Zuunbayan for upcoming railroad project www.zgm.mn

President Battulga Khaltmaa visited the Zuunbayan railway station in Dornogovi province to get an au fait with the construction of the railroad. The 336th Armed forces have received the president. The Zuunbayan station was built in 1984 and has three lanes that are 8501,100 meters in length and operates with eight staff.

The total length of the Tavantolgoi-Zuunbayan railroad is 414.6 km and the opening was held at its 290th km checkpoint. From this point, the first 50 km railway in the Tsogttsetsii direction of Umnugovi province construction will be situated, said the Chief Executive Officer of the Mongolian Railways SOE.

However, due to the increased traffic pressure caused by the Tavantolgoi railroad, it is necessary to reform the Sainshand-Zuunbayan 47 km railroad. According to the development plan, it will start its maintenance next year. Ulaanbaatar Railway JV will fund the required MNT 37.7 billion of the construction.

The groundbreaking ceremony of the Tavantolgoi-Zuunbayan railway that will be built under the “State railway policy” in Mandakh soum, Dornogobi province took place on Friday. President of Mongolia emphasized at the ceremony, “In this land-locked country, this infrastructure is important to the economy. Erdenes Tavan Tolgoi JSC is investing in this project from its profits of 2018. This investment is not a foreign project, it is our income earned without a burden on foreign workers. This is what we are giving to ourselves.”

Zuunbayan is a village in Dornogovi province and is one of Sainshand soum's administrative districts. Currently, more than 3,000 people live in the area. It is expected that the population will grow 2-3 times and will become a major settlement center when the railway is completed.



Published Date:2019-05-27