1 DRAFT LAW ON AMENDMENTS TO THE GENERAL LAW ON TAXATION TO BE SUBMITTED TO PARLIAMENT WWW.MONTSAME.MN PUBLISHED:2025/06/05      2 THE FALL OF MONGOLIA’S COALITION GOVERNMENT WWW.THEDIPLOMAT.COM  PUBLISHED:2025/06/05      3 REVISED DRAFT LAW ON VALUE ADDED TAX TO BE SUBMITTED TO PARLIAMENT WWW.MONTSAME.MN PUBLISHED:2025/06/05      4 MONGOLIA SOLAR TENDER: 19.8 MW SOLAR PLANT FOR A STUNNING FUTURE WWW.PVKNOWHOW.COM  PUBLISHED:2025/06/05      5 GOLD PURCHASE BY MONGOLIA'S CENTRAL BANK DOWN 29.3 PCT IN 1ST 5 MONTHS OF 2025 WWW.XINHUANET.COM PUBLISHED:2025/06/05      6 FOOD AND AGRICULTURE ORGANIZATION OF THE UNITED NATIONS APPOINTS NEW REPRESENTATIVE IN MONGOLIA WWW.GOGO.MN PUBLISHED:2025/06/05      7 MONGOLIA:REGULATORY SANDBOX FRAMEWORK HAS BEEN AMENDED AND APPROVED WWW.ASIAINSURANCEREVIEW.COM  PUBLISHED:2025/06/05      8 RESOURCE-RICH MONGOLIA FACES POLITICAL UNCERTAINTY AFTER THE PRIME MINISTER RESIGNS WWW.APNEWS.COM PUBLISHED:2025/06/04      9 WHY MONGOLIA’S PRIME MINISTER RESIGNED WWW.TIME.COM PUBLISHED:2025/06/04      10 MONGOLIA PM RESIGNS AFTER SON'S LUXURY HOLIDAY STIRS PUBLIC FURY WWW.BBC.COM PUBLISHED:2025/06/04      ЕРӨНХИЙ САЙДАД НЭР ДЭВШИГЧДИЙГ МАРГААШ ТОДРУУЛНА WWW.ZINDAA.MN  НИЙТЭЛСЭН:2025/06/05     МОНГОЛЫН ИРГЭД ОХУ РУУ ЗОРЧИХДОО ШИНЭ ЖУРАМ МӨРДӨНӨ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/06/05     АЛБАДАН ГАРГАСАН ГАДААДЫН ИРГЭДИЙН ТОО ӨМНӨХ ОНЫ МӨН ҮЕЭС 71 ХУВИАР ӨСЖЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2025/06/05     МОНГОЛБАНК ЗАСГИЙН ГАЗРЫН “ХАМЖИГЧ”-ААР АЖИЛЛАСНЫ АЛДАГДАЛ 3.6 ИХ НАЯД ТӨГРӨГТ ХҮРЧЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2025/06/05     НИЙГМИЙН ДААТГАЛЫН БАГЦ ХУУЛЬ: АЖИЛ ОЛГОГЧДЫН ТӨЛДӨГ НДШ-ЭЭС 2 ХҮРТЭЛХ ХУВИЙГ ХӨНГӨЛНӨ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/05     ДОТООДЫН МАХ, МАХАН БҮТЭЭГДЭХҮҮНИЙ ҮНЭ ЖИЛИЙН 18.2 ХУВИАР ӨССӨН НЬ ИНФЛЯЦИД НӨЛӨӨЛЖЭЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/05     2026 ОНЫ АЗИ ТИВИЙН ШАТРЫН АВАРГА ШАЛГАРУУЛАХ ТЭМЦЭЭНИЙГ МОНГОЛ УЛСАД ЗОХИОН БАЙГУУЛНА WWW.EAGLE.MN НИЙТЭЛСЭН:2025/06/05     ШИНЭ ЕРӨНХИЙ САЙД ТОМИЛОХ МАН-ЫН БАГА ХУРАЛ МАРГААШ БОЛНО WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/04     Н.УЧРАЛ: ТӨК-ИЙН ЗАХИРГААНЫ ОРОН ТОО, ТУЗ-ИЙН ТООГ БУУРУУЛНА WWW.NEWS.MN НИЙТЭЛСЭН:2025/06/04     ТАТВАРАА ТӨЛӨӨГҮЙ 103 МЯНГАН ЭЗЭМШИГЧ БАЙНА, БАРАГДУУЛААГҮЙ ТОХИОЛДОЛД ЗАМЫН ХӨДӨЛГӨӨНД ОРОЛЦУУЛАХГҮЙ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/04    

Sharp : Builds Mega Solar Plant near New Ulaanbaatar International Airport, Mongolia www.marketscreener.com

Sharp Energy Solutions Corporation (SESJ)*1 announces the completion of a mega solar power plant in Khushight Khundii, Sergelen district, Tuv province, Mongolia with partners including renewable energy company Sermsang Power Corporation*2 and Tenuun Gerel Construction LLC*3.

The power plant is located approximately 14 km southwest of the New Ulaanbaatar International Airport, which is currently under construction. Plans are to supply the electricity generated by the power plant to the central grid system which connected also capital of Ulaanbaatar and the new airport. In general, the longer the distance between a power plant and the facilities it is supplying, the greater the electricity loss. However, this new power plant will be able to efficiently supply electricity to the new airport and urban parts of Ulaanbaatar, areas predicted to see rising electricity consumption.

This power plant was constructed after selection as one of the Joint Crediting Mechanism (JCM) Model Projects*4 financially supported by the Ministry of the Environment, Japan.

The project is implementing under the cooperation between the Government of Mongolia and Japan. The 16.4 MW-dc solar power plant will generate 23,134 MWh per year, thus allowing reduction of greenhouse gas (GHG) emissions of 18,438 t-CO2 per year.

Mongolia's government aims to have renewable energy account for 30% of the country's energy mix by 2030, representing a 14% drop in greenhouse gas emissions compared to a BAU*5 scenario. Sharp remains committed to spreading the use of renewable energy in Mongolia.

Country

Mongolia

Location

Khushight Khundii, Sergelen district, Tuv province

Output (module capacity)

Approx. 16.4 MW-dc

Annual power generation capacity (estimate)

Approx. 23,134 MWh/year

Avoided greenhouse gas emissions (estimate)

Approx. 18,438 t-CO2/year

Start of operation

Mid June 2019

*1 SESJ is a subsidiary of Sharp Corporation, specializing in energy solutions such as the sales of PV systems and the installation of electrical equipment.
Headquarters: Yao, Osaka Prefecture; President: Hiroshi Sasaoka

*2 Sermsang Power Corporation invests, develops, and operates renewable energy projects currently in Thailand, Japan, Mongolia, Vietnam, with over 200 equity MW.
Headquarters: Bangkok, Thailand; CEO: Varut Tummavaranukub

*3 Tenuun Gerel Construction's main business is developing and operating solar power plants.
Headquarters: Ulaanbaatar, Mongolia; Representative: Odbaatar Sukhbaatar

*4 Ministry of the Environment, Japan has been implementing the 'JCM Model Projects,' which provides financial supports covering up to half of the initial investment costs. The purpose of this model projects is to financially support the implementation of projects which reduce GHG emissions by utilizing leading low carbon technologies in developing countries, and in return, to acquire JCM credits for achievement of Japan's GHG emission reduction and the partner countries emission reduction target.

*5 BAU (business as usual) means projections of greenhouse gas emissions based on the energy mix up to the present.



Published Date:2019-06-13