1 AUS-BRITISH MINER'S PLIGHT IN MONGOLIA HAS 'CHILLING EFFECT' ON INVESTMENT WWW.MININGMAGAZINE.COM  PUBLISHED:2025/04/03      2 ULAANBAATAR INTRODUCES ADVANCED AI SOFTWARE TO SUPPORT POLICE INVESTIGATION WWW.MONTSAME.MN PUBLISHED:2025/04/03      3 ION ENERGY SECURES $13.5M DEAL WWW.INSIDEMONGOLIA.MN PUBLISHED:2025/04/03      4 PROGRESS OF NATURAL GAS PIPELINE PROJECT PRESENTED TO CABINET WWW.MONTSAME.MN PUBLISHED:2025/04/03      5 ULAANBAATAR TO IMPLEMENT 24 MEGA PROJECTS UNDER INTERNATIONAL FIDIC CONTRACT STANDARDS WWW.MONTSAME.MN PUBLISHED:2025/04/03      6 INTERBANK TRANSACTIONS NOW USE IBAN NUMBERS WWW.MONTSAME.MN PUBLISHED:2025/04/03      7 MEERECOMPANY SIGNS MOU WITH THE MONGOLIAN CENTER FOR HEALTH DEVELOPMENT WWW.SURGICALROBOTICSTECHNOLOGY.COM PUBLISHED:2025/04/03      8 GOLD AND COPPER PRICES SURGE WWW.UBPOST.MN PUBLISHED:2025/04/02      9 REGISTRATION FOR THE ULAANBAATAR MARATHON 2025 IS NOW OPEN WWW.MONTSAME.MN PUBLISHED:2025/04/02      10 WHY DONALD TRUMP SHOULD MEET KIM JONG- UN AGAIN – IN MONGOLIA WWW.LOWYINSTITUTE.ORG  PUBLISHED:2025/04/02      I/01-IV/02-НД 16.3 САЯ ТОНН ЧУЛУУН НҮҮРС ЭКСПОРТОЛСОН НЬ ӨМНӨХ ОНЫ МӨН ҮЕЭС 10.5 ХУВИАР БУУРАВ WWW.BLOOMBERGTV.MN НИЙТЭЛСЭН:2025/04/04     “ТУУЛ-1” КОЛЛЕКТОРЫН ШУГАМ УГСРАЛТЫН АЖИЛ ЭХЭЛЛЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/04/04     ИПОТЕКИЙН ЗЭЭЛИЙН ДААТГАЛЫН ӨӨРЧЛӨГДСӨН ЗОХИЦУУЛАЛТ VIII/01-НЭЭС ХЭРЭГЖИНЭ WWW.BLOOMBERGTV.MN НИЙТЭЛСЭН:2025/04/03     “ASPIRE MINING” 2024 ОНД A$6.6 САЯЫН ЦЭВЭР АШИГТАЙ АЖИЛЛАСНАА ТАЙЛАГНАЛАА WWW.BLOOMBERGTV.MN НИЙТЭЛСЭН:2025/04/03     ЕАЭЗХ-ТОЙ ЧӨЛӨӨТ ХУДАЛДААНЫ ХЭЛЭЛЦЭЭР БАЙГУУЛСНААР ДНБ-ИЙ ӨСӨЛТ 6.1 ХУВИАР БУУРАХ ЭРСДЭЛТЭЙ WWW.BLOOMBERGTV.MN НИЙТЭЛСЭН:2025/04/03     НИЙСЛЭЛИЙН 18 БАЙРШИЛД ОЛОН ТҮВШНИЙ УУЛЗВАР БАРИНА WWW.EAGLE.MN НИЙТЭЛСЭН:2025/04/03     ХХОАТ-ЫГ 1 ХУВЬ БОЛГОХ САНАЛЫГ ТӨСВИЙН БАЙНГЫН ХОРООНД ШИЛЖҮҮЛЛЭЭ WWW.NEWS.MN НИЙТЭЛСЭН:2025/04/03     ГЕГ: АНУ-Д ХИЙСЭН ЭКСПОРТ 2024 ОНД $166.3 САЯ БОЛЖ, ӨМНӨХ ОНООС 4.5 ДАХИН ӨССӨН WWW.BLOOMBERGTV.MN НИЙТЭЛСЭН:2025/04/03     ХӨСҮТ: УЛААНБУРХНЫ 253 ТОХИОЛДОЛ БАТЛАГДАЖ, 7220 ХАВЬТАЛ БҮРТГЭГДЛЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2025/04/03     “JADE GAS” КОМПАНИ "УЛААН НУУР" ТАЛБАЙДАА ХОЁР ДАХЬ ХЭВТЭЭ ЦООНОГИЙН ӨРӨМДЛӨГӨӨ ЭХЛҮҮЛЭВ WWW.BLOOMBERGTV.MN НИЙТЭЛСЭН:2025/04/03    

Rio Tinto Hits Cost Blowout at Mongolia Copper Expansion www.reuters.com

(Reuters) - Rio Tinto on Tuesday flagged a cost blowout of up to $1.9 billion and a delay of up to 30 months at its Oyu Tolgoi underground copper mine in Mongolia, the miner's key growth project.

Rio said the delay stemmed from the project's challenging geology. It expected to determine the preferred mine design, along with a final estimate of cost in the second half of 2020, and was also reviewing the value of its investment.

The cost blowout was bigger than analysts had expected after the company had earlier flagged issues with the original mine design.

Rio said first production could be achieved between May 2022 and June 2023, a delay of 16 to 30 months, while the capital cost of the project was estimated at $6.5 billion to $7.2 billion, up from an original estimate of $5.3 billion.

"It is a world class orebody in terms of the size, the grade etc. What we are trying to work out now, is can it be developed and mined economically to convert what is a world class orebody into world class mine," said Glyn Lawcock, analyst at UBS.

"Overall, it was below our expectations for the quarter."

The news of the blowout came as Rio reported a 3.5% drop in second-quarter iron ore shipments, as disruptions caused by tropical cyclone Veronica in late March squeezed output in the April-June period.

The company shipped 85.4 million tonnes of the steelmaking ingredient in the quarter ended June 30, down from 88.5 million tonnes a year earlier. Brokerage UBS had estimated quarterly shipments of 85.2 million tonnes.

Veronica ravaged the coast of Western Australia earlier this year, damaging several iron ore export hubs and prompting Australia's biggest listed miners to cut their 2019 forecast for iron ore output.

Rio on Tuesday maintained its annual iron ore exports forecast in the 320 million to 330 million tonnes range.

In Mongolia, the miner said it had made significant progress at Oyu Tolgoi during 2019.

"The ground conditions are more challenging than expected and we are having to review our mine plan and consider a number of options," said Stephen McIntosh, Group executive, Growth & Innovation.

"Delays are not unusual for such a large and complex project," he added.

Rio said it was reviewing the carrying value of its investment in Oyu Tolgoi and would announce if any changes were needed at its half-year results on Aug. 1.

Rio Tinto shares were flat in early trade in a steady broader market.

(Reporting by Aditya Soni and Aby Jose Koilparambil in Bengaluru; Additional reporting by Melanie Burton in Melbourne; Editing by Shounak Dasgupta and Richard Pullin)



Published Date:2019-07-16