1 DEPUTY PRIME MINISTER S.AMARSAIKHAN DISMISSED FOR VIOLATING ACCOUNTABILITY AGREEMENT WWW.GOGO.MN PUBLISHED:2025/10/29      2 STATE EMERGENCY COMMISSION ORDERS READINESS AMID FUEL-SHORTAGE RISKS WWW.GOGO.MN PUBLISHED:2025/10/29      3 WORLD BANK TO ASSIST MONGOLIA IN COP17 PREPARATIONS WWW.MONTSAME.MN PUBLISHED:2025/10/29      4 CRIMINAL INVESTIGATION LAUNCHED AGAINST MP D.AMARBAYASGALAN WWW.GOGO.MN PUBLISHED:2025/10/28      5 MONGOLIA AND GERMANY TO HOLD NEGOTIATIONS ON DEVELOPMENT COOPERATION WWW.MONTSAME.MN PUBLISHED:2025/10/28      6 MONGOLIAN HEALTH WORKERS BEGIN STRIKE AFTER EIGHT DAYS OF PROTEST WWW.ASIANEWS.NETWORK PUBLISHED:2025/10/28      7 STEPPE FIRE DESTROYS 800 HECTARES OF LAND IN EASTERN MONGOLIA WWW.XINHUANET.COM PUBLISHED:2025/10/28      8 MONGOLIA’S CORRUPTION PROBE AT OYU TOLGOI MINING OPERATIONS UNFOLDS WWW.DISCOVERYALERT.COM.AU PUBLISHED:2025/10/28      9 RIO TINTO AND SPIC QIYUAN BEGIN BATTERY-SWAP TRUCK TRIAL IN MONGOLIA WWW.MINING-TECHNOLOGY.COM PUBLISHED:2025/10/28      10 THE EUROPEAN UNION - MONGOLIA BUSINESS AND INVESTMENT FORUM LAUNCHES A NEW ERA OF ECONOMIC PARTNERSHIP WWW.EEAS.EUROPA.EU PUBLISHED:2025/10/28      "С.АМАРСАЙХАН ХАРИУЦЛАГЫН ГЭРЭЭ ЗӨРЧСӨН ТУЛ ЕРӨНХИЙ САЙД Г.ЗАНДАНШАТАР АЛБАН ТУШААЛААС НЬ ОГЦРУУЛСАН" WWW.EAGLE.MN НИЙТЭЛСЭН:2025/10/29     ЗГ: ГЭР БҮЛИЙН ТУХАЙ ХУУЛИЙН ШИНЭЧИЛСЭН НАЙРУУЛГЫГ ХЭЛЭЛЦЭНЭ WWW.NEWS.MN НИЙТЭЛСЭН:2025/10/29     ҮСХ: ДИЗЕЛИЙН ТҮЛШ ЛИТР ТУТАМДАА 74 ТӨГРӨГӨӨР ӨСӨЖ ₮3014 БОЛОВ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/10/29     ЭНЭ ОНЫ ЭХНИЙ 10 САРД 14,785 ХҮҮХЭД ХҮЧИРХИЙЛЭЛД ӨРТЖЭЭ WWW.NEWS.MN НИЙТЭЛСЭН:2025/10/29     РИО ТИНТО ГРУПП ОЮУТОЛГОЙ ХХК-Д АВЛИГЫН ЭСРЭГ ШАЛГАЛТ ЭХЛҮҮЛЭВ WWW.NEWS.MN НИЙТЭЛСЭН:2025/10/28     УОК: ЭРСДЭЛД БЭЛЭН БАЙХЫГ ҮҮРЭГ БОЛГОВ WWW.NEWS.MN НИЙТЭЛСЭН:2025/10/28     ЛАГ ШАТААХ ҮЙЛДВЭР ТӨСЛИЙГ ТӨР, ХУВИЙН ХЭВШЛИЙН ТҮНШЛЭЛЭЭР ХЭРЭГЖҮҮЛНЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/10/28     УЛААНБААТАР-СИНГАПУРЫН ЧИГЛЭЛД ШУУД НИСЛЭГ ҮЙЛДЭНЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/10/28     ЗАЙСАНГИЙН ГҮҮРИЙГ 54 ЖИЛИЙН ДАРАА БҮРЭН ШИНЭЧИЛЛЭЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/10/28     ЦЕГ-ЫН ДАРГААР Ж.БОЛДЫГ ТОМИЛЛОО WWW.ITOIM.MN НИЙТЭЛСЭН:2025/10/28    

Rio Tinto Hits Cost Blowout at Mongolia Copper Expansion www.reuters.com

(Reuters) - Rio Tinto on Tuesday flagged a cost blowout of up to $1.9 billion and a delay of up to 30 months at its Oyu Tolgoi underground copper mine in Mongolia, the miner's key growth project.

Rio said the delay stemmed from the project's challenging geology. It expected to determine the preferred mine design, along with a final estimate of cost in the second half of 2020, and was also reviewing the value of its investment.

The cost blowout was bigger than analysts had expected after the company had earlier flagged issues with the original mine design.

Rio said first production could be achieved between May 2022 and June 2023, a delay of 16 to 30 months, while the capital cost of the project was estimated at $6.5 billion to $7.2 billion, up from an original estimate of $5.3 billion.

"It is a world class orebody in terms of the size, the grade etc. What we are trying to work out now, is can it be developed and mined economically to convert what is a world class orebody into world class mine," said Glyn Lawcock, analyst at UBS.

"Overall, it was below our expectations for the quarter."

The news of the blowout came as Rio reported a 3.5% drop in second-quarter iron ore shipments, as disruptions caused by tropical cyclone Veronica in late March squeezed output in the April-June period.

The company shipped 85.4 million tonnes of the steelmaking ingredient in the quarter ended June 30, down from 88.5 million tonnes a year earlier. Brokerage UBS had estimated quarterly shipments of 85.2 million tonnes.

Veronica ravaged the coast of Western Australia earlier this year, damaging several iron ore export hubs and prompting Australia's biggest listed miners to cut their 2019 forecast for iron ore output.

Rio on Tuesday maintained its annual iron ore exports forecast in the 320 million to 330 million tonnes range.

In Mongolia, the miner said it had made significant progress at Oyu Tolgoi during 2019.

"The ground conditions are more challenging than expected and we are having to review our mine plan and consider a number of options," said Stephen McIntosh, Group executive, Growth & Innovation.

"Delays are not unusual for such a large and complex project," he added.

Rio said it was reviewing the carrying value of its investment in Oyu Tolgoi and would announce if any changes were needed at its half-year results on Aug. 1.

Rio Tinto shares were flat in early trade in a steady broader market.

(Reporting by Aditya Soni and Aby Jose Koilparambil in Bengaluru; Additional reporting by Melanie Burton in Melbourne; Editing by Shounak Dasgupta and Richard Pullin)