1 SOLAR, EVS AND A BIG EXIT FROM COAL: 2024’S GOOD CLIMATE NEWS WWW.BLOOMBERG.COM PUBLISHED:2024/12/25      2 OVER 636,000 MONGOLIANS USE THE WHAT3WORDS APPLICATION WWW.MONTSAME.MN PUBLISHED:2024/12/25      3 CHINA EXPRESSES READINESS TO RESOLVE GASHUUNSUKHAIT-GANTSMOD CROSS-BORDER RAILWAY PROJECT ISSUES WWW.MONTSAME.MN PUBLISHED:2024/12/25      4 BOGD BANK AND FMO BEGIN COOPERATION TO SUPPORT SMES AND GREEN PROJECTS IN MONGOLIA WWW.MONTSAME.MN PUBLISHED:2024/12/25      5 THE BANK OF MONGOLIA: LEGAL REFORMS NEEDED TO ENSURE CENTRAL BANK INDEPENDENCE WWW.GOGO.MN PUBLISHED:2024/12/25      6 SNOW COVERS OVER 60 PCT OF MONGOLIAN TERRITORY WWW.XINHUANET.COM PUBLISHED:2024/12/24      7 DIGITAL TRANSFORMATION AND DEVELOPMENT OF ARTIFICIAL INTELLIGENCE DISCUSSED WWW.MONTSAME.MN PUBLISHED:2024/12/24      8 MONGOLIAN AND JAPANESE AIRPORTS TO EXCHANGE BEST PRACTICES AND ENHANCE SERVICE QUALITY WWW.MONTSAME.MN PUBLISHED:2024/12/24      9 MONGOLIA'S SOVEREIGN WEALTH FUND RENAMED “CHINGGIS FUND” WWW.MONTSAME.MN PUBLISHED:2024/12/24      10 DEFENSE MINISTRY OF MONGOLIA TO SUPPLY MEAT TO VIETNAMESE ARMY WWW.AKIPRESS.COM PUBLISHED:2024/12/24      ЭХЯ: ДЦС-3-ЫГ 300 МВТ-ААР ӨРГӨТГӨХ ТӨСЛИЙН ӨРТӨГ 1.3 ТЭРБУМ ЕВРО БАЙНА WWW.BLOOMBERGTV.MN НИЙТЭЛСЭН:2024/12/25     НҮҮРСНИЙ ЭКСПОРТЫГ 100 САЯ ТОННД ХҮРГЭХ ЗАМЫГ ЗАСАХ ГАШУУНСУХАЙТ-ГАНЦМОДЫН ХЭЛЭЛЦЭЭРИЙН ЭРГЭН ТОЙРОНД... WWW.BLOOMBERGTV.MN НИЙТЭЛСЭН:2024/12/25     ХЭРЭГЛЭЭНИЙ БАРАА, ҮЙЛЧИЛГЭЭНИЙ ҮНЭ 8.1 ХУВИАР НЭМЭГДЖЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2024/12/25     ЗГ: "ОРАНО МАЙНИНГ" ХХК ЭХНИЙ САНХҮҮЖИЛТЭЭР 500 САЯ ДОЛЛАРЫГ ГАРГАНА WWW.NEWS.MN НИЙТЭЛСЭН:2024/12/25     ОРОН СУУЦНЫ ҮНЭ 13 ХУВИАР НЭМЭГДЖЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2024/12/25     МОНГОЛБАНКНЫ ҮНЭТ ЦААСНЫ ҮЛДЭГДЭЛ ₮10.7 ИХ НАЯД БОЛЖ, ӨМНӨХ ОНЫ МӨН ҮЕЭС 21 ХУВИАР ӨСӨВ WWW.BLOOMBERGTV.MN НИЙТЭЛСЭН:2024/12/24     БНХАУ-ЫН ЗАСГИЙН ГАЗАР ГАШУУНСУХАЙТ-ГАНЦМОД БООМТЫН ТӨСЛИЙГ ОЛОН УЛСЫН ГЭРЭЭГЭЭР ШИЙДВЭРЛЭХЭД БЭЛЭН ГЭДГЭЭ ИЛЭРХИЙЛЛЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2024/12/24     НҮҮРСНИЙ ЭКСПОРТ 78.5 САЯ ТОННД ХҮРЭВ WWW.MONTSAME.MN НИЙТЭЛСЭН:2024/12/24     "НЭГ УУТ БЭЛЭГ 36-72 ШИРХЭГ ЁОТОНТОЙ ТЭНЦЭХ САХАР АГУУЛДАГ" WWW.NEWS.MN НИЙТЭЛСЭН:2024/12/24     НЭМЭЛТЭЭР ДАХИН ЗУРГААН ЧИГЛЭЛД ТУСГАЙ АВТОБУС ГАРГАНА WWW.MONTSAME.MN НИЙТЭЛСЭН:2024/12/24    

Rio Tint Q2 Iron Ore Shipments Down 3%; Says Mongolia Copper Mine To Cost More www.markets.businessinsider.com

(RTTNews) - Anglo-Australian mining giant Rio Tinto Plc (RTNTF, RIO, RIO.L, RTPPF) reported that Pilbara iron ore shipments in the second quarter were 3% lower than last year, due to recovery works following Tropical Cyclone Veronica. It reaffirmed its full-year shipment guidance.

The estimated cost of the company's underground copper mine in Mongolia increased up to $1.9 billion, and its first sustainable production could now be delayed by 16-30 months as mine design complications at the Oyu Tolgoi underground copper project, Rio Tinto said in a statement.

Meanwhile, Rio Tinto reported that Pilbara iron ore shipments of 85.4 million tonnes--100% basis-- in the second quarter were 3% lower than the second quarter of 2018. The shipments were impacted in April due to recovery works following Tropical Cyclone Veronica.

Rio Tinto said in June that it reduced Pilbara iron ore shipments guidance for fiscal year 2019 to a range of 320 million tonnes - 330 million tonnes from the previous outlook of 333 million tonnes - 343 million tonnes. But the company today reaffirmed its full-year shipment guidance.

The company said that Pilbara operations produced 79.7 million tonnes of iron ore in the second quarter, seven per cent lower than the previous year. Bauxite production of 13.4 million tonnes in the second quarter was 1% higher than the same period of 2018.

Aluminium production of 0.8 million tonnes was in line with the second quarter of 2018.

Rio Tinto, in an update on the schedule and cost of the Oyu Tolgoi underground project in Mongolia, said that enhanced geotechnical information and data modelling suggested that there may be some stability risks identified with the approved mine design and so a number of other mine design options are also under consideration to complete the Project.

Preliminary information now suggested that, depending on which mine design options are adopted, first sustainable production could be achieved between May 2022 and June 2023, a delay of 16 to 30 months compared to the original feasibility study guidance in 2016.

Rio Tinto now estimates the capital spend for the Oyu Tolgoi underground project to be $6.5 billion to $7.2 billion, an increase of $1.2 billion to $1.9 billion from the $5.3 billion previously disclose.

Separately, Rio Tinto said it completed the sale of its entire interest in the Rössing uranium mine in Namibia to China National Uranium Corporation Limited for an initial cash payment of $6.5 million plus a contingent payment of up to $100 million.



Published Date:2019-07-17