1 DRAFT LAW ON AMENDMENTS TO THE GENERAL LAW ON TAXATION TO BE SUBMITTED TO PARLIAMENT WWW.MONTSAME.MN PUBLISHED:2025/06/05      2 THE FALL OF MONGOLIA’S COALITION GOVERNMENT WWW.THEDIPLOMAT.COM  PUBLISHED:2025/06/05      3 REVISED DRAFT LAW ON VALUE ADDED TAX TO BE SUBMITTED TO PARLIAMENT WWW.MONTSAME.MN PUBLISHED:2025/06/05      4 MONGOLIA SOLAR TENDER: 19.8 MW SOLAR PLANT FOR A STUNNING FUTURE WWW.PVKNOWHOW.COM  PUBLISHED:2025/06/05      5 GOLD PURCHASE BY MONGOLIA'S CENTRAL BANK DOWN 29.3 PCT IN 1ST 5 MONTHS OF 2025 WWW.XINHUANET.COM PUBLISHED:2025/06/05      6 FOOD AND AGRICULTURE ORGANIZATION OF THE UNITED NATIONS APPOINTS NEW REPRESENTATIVE IN MONGOLIA WWW.GOGO.MN PUBLISHED:2025/06/05      7 MONGOLIA:REGULATORY SANDBOX FRAMEWORK HAS BEEN AMENDED AND APPROVED WWW.ASIAINSURANCEREVIEW.COM  PUBLISHED:2025/06/05      8 RESOURCE-RICH MONGOLIA FACES POLITICAL UNCERTAINTY AFTER THE PRIME MINISTER RESIGNS WWW.APNEWS.COM PUBLISHED:2025/06/04      9 WHY MONGOLIA’S PRIME MINISTER RESIGNED WWW.TIME.COM PUBLISHED:2025/06/04      10 MONGOLIA PM RESIGNS AFTER SON'S LUXURY HOLIDAY STIRS PUBLIC FURY WWW.BBC.COM PUBLISHED:2025/06/04      ЕРӨНХИЙ САЙДАД НЭР ДЭВШИГЧДИЙГ МАРГААШ ТОДРУУЛНА WWW.ZINDAA.MN  НИЙТЭЛСЭН:2025/06/05     МОНГОЛЫН ИРГЭД ОХУ РУУ ЗОРЧИХДОО ШИНЭ ЖУРАМ МӨРДӨНӨ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/06/05     АЛБАДАН ГАРГАСАН ГАДААДЫН ИРГЭДИЙН ТОО ӨМНӨХ ОНЫ МӨН ҮЕЭС 71 ХУВИАР ӨСЖЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2025/06/05     МОНГОЛБАНК ЗАСГИЙН ГАЗРЫН “ХАМЖИГЧ”-ААР АЖИЛЛАСНЫ АЛДАГДАЛ 3.6 ИХ НАЯД ТӨГРӨГТ ХҮРЧЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2025/06/05     НИЙГМИЙН ДААТГАЛЫН БАГЦ ХУУЛЬ: АЖИЛ ОЛГОГЧДЫН ТӨЛДӨГ НДШ-ЭЭС 2 ХҮРТЭЛХ ХУВИЙГ ХӨНГӨЛНӨ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/05     ДОТООДЫН МАХ, МАХАН БҮТЭЭГДЭХҮҮНИЙ ҮНЭ ЖИЛИЙН 18.2 ХУВИАР ӨССӨН НЬ ИНФЛЯЦИД НӨЛӨӨЛЖЭЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/05     2026 ОНЫ АЗИ ТИВИЙН ШАТРЫН АВАРГА ШАЛГАРУУЛАХ ТЭМЦЭЭНИЙГ МОНГОЛ УЛСАД ЗОХИОН БАЙГУУЛНА WWW.EAGLE.MN НИЙТЭЛСЭН:2025/06/05     ШИНЭ ЕРӨНХИЙ САЙД ТОМИЛОХ МАН-ЫН БАГА ХУРАЛ МАРГААШ БОЛНО WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/04     Н.УЧРАЛ: ТӨК-ИЙН ЗАХИРГААНЫ ОРОН ТОО, ТУЗ-ИЙН ТООГ БУУРУУЛНА WWW.NEWS.MN НИЙТЭЛСЭН:2025/06/04     ТАТВАРАА ТӨЛӨӨГҮЙ 103 МЯНГАН ЭЗЭМШИГЧ БАЙНА, БАРАГДУУЛААГҮЙ ТОХИОЛДОЛД ЗАМЫН ХӨДӨЛГӨӨНД ОРОЛЦУУЛАХГҮЙ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/04    

Rio Tint Q2 Iron Ore Shipments Down 3%; Says Mongolia Copper Mine To Cost More www.markets.businessinsider.com

(RTTNews) - Anglo-Australian mining giant Rio Tinto Plc (RTNTF, RIO, RIO.L, RTPPF) reported that Pilbara iron ore shipments in the second quarter were 3% lower than last year, due to recovery works following Tropical Cyclone Veronica. It reaffirmed its full-year shipment guidance.

The estimated cost of the company's underground copper mine in Mongolia increased up to $1.9 billion, and its first sustainable production could now be delayed by 16-30 months as mine design complications at the Oyu Tolgoi underground copper project, Rio Tinto said in a statement.

Meanwhile, Rio Tinto reported that Pilbara iron ore shipments of 85.4 million tonnes--100% basis-- in the second quarter were 3% lower than the second quarter of 2018. The shipments were impacted in April due to recovery works following Tropical Cyclone Veronica.

Rio Tinto said in June that it reduced Pilbara iron ore shipments guidance for fiscal year 2019 to a range of 320 million tonnes - 330 million tonnes from the previous outlook of 333 million tonnes - 343 million tonnes. But the company today reaffirmed its full-year shipment guidance.

The company said that Pilbara operations produced 79.7 million tonnes of iron ore in the second quarter, seven per cent lower than the previous year. Bauxite production of 13.4 million tonnes in the second quarter was 1% higher than the same period of 2018.

Aluminium production of 0.8 million tonnes was in line with the second quarter of 2018.

Rio Tinto, in an update on the schedule and cost of the Oyu Tolgoi underground project in Mongolia, said that enhanced geotechnical information and data modelling suggested that there may be some stability risks identified with the approved mine design and so a number of other mine design options are also under consideration to complete the Project.

Preliminary information now suggested that, depending on which mine design options are adopted, first sustainable production could be achieved between May 2022 and June 2023, a delay of 16 to 30 months compared to the original feasibility study guidance in 2016.

Rio Tinto now estimates the capital spend for the Oyu Tolgoi underground project to be $6.5 billion to $7.2 billion, an increase of $1.2 billion to $1.9 billion from the $5.3 billion previously disclose.

Separately, Rio Tinto said it completed the sale of its entire interest in the Rössing uranium mine in Namibia to China National Uranium Corporation Limited for an initial cash payment of $6.5 million plus a contingent payment of up to $100 million.