1 GTJAI ASSISTS STATE BANK OF MONGOLIA IN COMPLETING A US$100 MILLION REG S BOND TAP ISSUANCE WWW.ACNNEWSWIRE.COM PUBLISHED:2026/05/12      2 BATSUMBEREL N. ELECTED MPP DEPUTY CHAIRMAN WWW.MONTSAME.MN PUBLISHED:2026/05/12      3 JICA TWO-STEP LOAN PROJECT DELIVERS LONG-TERM FINANCING TO MONGOLIAN SMES WWW.MONTSAME.MN PUBLISHED:2026/05/12      4 UN HIGH COMMISSIONER FOR HUMAN RIGHTS VOLKER TÜRK VISITING MONGOLIA WWW.GOGO.MN PUBLISHED:2026/05/12      5 ‘CLIMATE REFUGEES’ FLEEING RED DUST WWW.UBPOST.MN PUBLISHED:2026/05/12      6 NATIONAL RESILIENCE STRATEGY TO BE DEVELOPED, APPROVED FOLLOWING PRESIDENTIAL DIRECTIVE WWW.MONTSAME.MN PUBLISHED:2026/05/12      7 BOOK EXCHANGE PROGRAM LAUNCHED WITH U.S. LIBRARY OF CONGRESS WWW.MONTSAME.MN PUBLISHED:2026/05/12      8 CHINA-MONGOLIA MEGA RAILWAY PROJECT ENTERS CRITICAL PHASE WWW.CHINADAILY.COM.CN PUBLISHED:2026/05/12      9 MONGOLIA’S FOREIGN TRADE TURNOVER REACHES USD 10.5 BILLION WWW.MONTSAME.MN PUBLISHED:2026/05/12      10 ASIATIC WILD ASS RETURNS TO EASTERN MONGOLIA AFTER 65-YEAR ISOLATION FROM LANDSCAPE FENCING WWW.GOODNEWSNETWORK.ORG PUBLISHED:2026/05/12      СЭРГЭЭГДЭХ ЭРЧИМ ХҮЧНИЙ САЛБАРТ АНХ УДАА ӨРСӨЛДӨӨНТ СОНГОН ШАЛГАРУУЛАЛТ ЗАРЛАЛАА WWW.EAGLE.MN НИЙТЭЛСЭН:2026/05/12     АТГ: ШААРДЛАГА ХАНГААГҮЙ КОМПАНИД 6.5 ТЭРБУМЫН САНХҮҮЖИЛТ ОЛГОСОН ХЭРГИЙГ ШҮҮХЭД ШИЛЖҮҮЛЭВ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/05/12     Б.БАТЦЭЦЭГ: БРАЗИЛ, ИСПАНИ, КЕНИ УЛСАД ЭЛЧИН САЙДЫН ЯАМАА НЭЭНЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/05/12     “ХАО ГАН” КОМПАНИ МОНГОЛ РУУ 6.5 САЯ ТОНН ЖИМС, ХҮНСНИЙ НОГОО ЭКСПОРТОЛЖЭЭ WWW.NEWS.MN НИЙТЭЛСЭН:2026/05/12     МОНГОЛ, БНХАУ-ЫН ХАМТАРСАН ҮЙЛДВЭРЛЭЛ, ХУДАЛДААНЫ ЧӨЛӨӨТ БҮСИЙГ ХӨГЖҮҮЛНЭ WWW.NEWS.MN НИЙТЭЛСЭН:2026/05/12     НИЙТИЙН АЛБАН ТУШААЛТАН ХАХУУЛЬ АВСАН ХЭРГҮҮДИЙГ ШҮҮХЭД ШИЛЖҮҮЛЭВ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/05/12     "РИО ТИНТО"-Д МЕНЕЖМЕНТИЙН ТӨЛБӨРИЙГ БУУРУУЛАХ СОНИРХОЛ АЛГА WWW.EGUUR.MN НИЙТЭЛСЭН:2026/05/12     МАНАЙ ТӨРИЙН БАЙГАА ЦАРАЙГ ЗАСГИЙН ХЯНАГЧ, ЯАМНЫ БЭЛТГЭСЭН ЭМГЭНЭЛ ХАРУУЛАВ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/05/12     "2033 ОН ГЭХЭД 23 КМ УРТ ҮЕРИЙН ХАМГААЛАЛТЫН ДАЛАНГ ШИНЭЭР БАРИНА" WWW.NEWS.MN НИЙТЭЛСЭН:2026/05/12     "МОНГОЛ УЛС НЭН ХӨНГӨЛӨЛТТЭЙ ЗЭЭЛ АВАХ БОЛОМЖ ХУМИГДАЖ БАЙНА" WWW.NEWS.MN НИЙТЭЛСЭН:2026/05/12    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

World's largest ore chute created in Sudbury www.northernontariobusiness.com

A manufacturing shop in Greater Sudbury has created the largest ore chute in the world, which will soon be shipped out and installed in one of the largest copper and gold mining operations in the world, the Rio Tinto Oyu Tolgoi mine in Mongolia.

The massive steel chute, as big as a house and with built-in safety features, was manufactured at Variant Mining Technologies in Lively. It is the prototype for several other chutes that will be installed at the mine in the coming months and years.

An ore chute is a device that allows chunks of rock (muck) to be transported by force of gravity from one level of the mine to another level. The chute is used to control the flow of muck, or waste rock, so that haulage equipment such as scooptrams, ore trucks or even underground rail cars can be loaded quickly and safely.

Variant’s website describes the company as a global leader in loading chute systems, which can explain why company designers decided to go so big.

“The size of the chute was driven by the size of the material they are actually processing and the tonnage that will be processed," said Variant general manager Paul Chamberland.

"(The throat) is 800 by 800 by 1,200 millimetres, which is the maximum dimension of rock we are working with, and the tonnage is an instantaneous rate of 10,000 tonnes per hour."

Despite its size, Chamberland said the entire chute can be broken down into individual modules, making it easier to be moved. He added that the dismantled components can be transported down a mine ramp or loaded onto the cage in the mine shaft. That way the chute can be bolted back together and installed deep in the mine.

Want to read more stories about business in the North? Subscribe to our newsletter.

The project has been a few years in the making, according to Derek Meloche, Variant’s manager of business development and sales.

“So we started pursuing the client in 2016, which was our first trip to Mongolia,” said Meloche.

“Strategically, we believe that to conduct business in certain countries you need representation there to do it effectively. So we went over there with the intent of finding a partner, which we have found. We have a partner in Ulaanbaatar, which is Mongolia’s capital city.”

He said he was pleased that Ulaanbaatar is a large manufacturing hub with enough technical and industrial expertise to carry on the work.

“Our contract for Rio Tinto is to build five of these systems. We have four them being built in parallel to this one being built in Canada,” said Meloche.

He said Rio Tinto wanted the prototype put together in Sudbury so that all the functional testing could be carried out on such things as the electrical, mechanical and hydraulic engineering. He said that took place in February.

Meloche said there were challenges for Variant, not just in functionality, but also in safety designs.

“This will be the first of its kind," Meloche said. "It is a patent-pending chute with the arc gate on the end of the lip. That is a fallen object protection for operators coming through the loading zone.”

Meloche credited Rio Tinto for putting such a high priority on safety that Variant developed new technological solutions to meet that need.

Chamberland said it was something that Variant anticipated.

“The design of this chute is all oriented towards safety. This a design we worked on for some time and basically it was the biggest selling feature with the client. We already had a design that was control-reliable and functionally safe, developed by the time this project came out for tender,” said Chamberland.

“So that is a pretty big challenge in the mining environment. There are a lot of factors that are difficult to predict. We have quite a bit of experience working in that environment with this product. So we had a pretty good understanding of what we were up against."

Meloche said the project is a success for the Variant team and the hope is that the new chute will be adopted by other mines in Canada. Variant held an event in May to showcase the chute to a select group of mining professionals. He said mining insiders will be watching the project closely over the next few years to gauge the long-term success of the project.

“This is the early stages of this particular operation in Mongolia,” said Meloche. “By the end of the day, there will be 29 to 38 systems going into this particular mine over the next seven years. So we received the order for the first five, to develop the technologies and work out any kinks and find adjustments to make it technically perfect.”

From there he said Variant will continue to move forward on building the best mining chutes available.

Len Gillis is the editor of Sudbury Mining Solutions Journal. This story will appear in the September edition of that publication.