1 D. DALAIJARGAL: URANIUM MINING PROJECT ADVANCES FAST WITH FRENCH FUNDING WWW.MONGOLIANMININGJOURNAL.COM  PUBLISHED:2025/12/05      2 MONGOLIA, INDIA TO ADVANCE STRATEGIC PARTNERSHIP IN DIGITAL DEVELOPMENT AND INNOVATION WWW.MONTSAME.MN PUBLISHED:2025/12/05      3 POPE LEO MEETS WITH THE PRESIDENT OF MONGOLIA WWW.VATICANNEWS.VA PUBLISHED:2025/12/05      4 NATIONAL PROTECTED AREA CONSULTATION TARGETS STRONGER RANGER SYSTEM WWW.MONTSAME.MN PUBLISHED:2025/12/05      5 RIO TINTO REVISES UP 2025 COPPER PRODUCTION FORECAST AS MONGOLIAN PROJECT ACCELERATES OPERATIONS WWW.NEWS.METAL.COM  PUBLISHED:2025/12/05      6 MONGOLIA CALLS PUBLIC HEARINGS AHEAD OF LIKELY PUSH TO RENEGOTIATE RIO TINTO TERMS ON GIANT COPPER MINE WWW.INTELLINEWS.COM PUBLISHED:2025/12/05      7 MONGOLIA RECEIVES HIGHEST NUMBER OF FOREIGN TOURISTS SINCE THE BEGINNING OF 2025 WWW.XINHUANET.COM PUBLISHED:2025/12/05      8 MONGOLIA SIGNALS READINESS TO CONTRIBUTE TO GLOBAL FIGHT AGAINST DESERTIFICATION WWW.QAZINFORM.COM PUBLISHED:2025/12/04      9 MONGOLIA’S FOREIGN EXCHANGE RESERVES REACH USD 6 BILLION WWW.MONTSAME.MN PUBLISHED:2025/12/04      10 FUEL SUPPLY STRENGTHENED AS DECEMBER PURCHASE ORDERS CONFIRMED WWW.MONTSAME.MN PUBLISHED:2025/12/04      МАЛ, ТЭЖЭЭВЭР АМЬТНЫ ТООЛЛОГО НЯМ ГАРАГТ ЭХЭЛНЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/12/05     Ш.РАДНААСЭД ЕРӨНХИЙ САЙДЫН АХЛАХ ЗӨВЛӨХ БОЛОВ WWW.NEWS.MN НИЙТЭЛСЭН:2025/12/05     АШИГТ МАЛТМАЛЫН 8 ЗӨВШӨӨРЛИЙН ХАРИУД ₮2.7 ТЭРБУМЫГ АВСАН Ш.ГАНХУЯГ, ӨГСӨН ЭДВАРД СҮРЭН НАРЫГ 1 САР ХОРИВ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/12/05     ЕРӨНХИЙЛӨГЧ У.ХҮРЭЛСҮХ ГЭГЭЭН ШИРЭЭТ УЛСЫН ТӨРИЙН ТЭРГҮҮНТЭЙ УУЛЗЛАА WWW.EAGLE.MN НИЙТЭЛСЭН:2025/12/05     ТАВАНТОЛГОЙ-ГАШУУНСУХАЙТ ЧИГЛЭЛИЙН ТӨМӨР ЗАМААР ТАВАН САРД 3 САЯ ТОНН НҮҮРС ТЭЭВЭРЛЭВ WWW.EGUUR.MN  НИЙТЭЛСЭН:2025/12/05     MONGOLIA FOCUS: МОНГОЛД ӨӨРИЙГӨӨ ЦЕНЗУРДЭХ ҮЗЭГДЭЛ НЭМЭГДСЭН НЬ АРДЧИЛЛЫН ЧАНАР ДОРОЙТОЖ БУЙН ИЛРЭЛ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/12/05     11575 АЙЛЫН ОРОН СУУЦ БАРИХ БОЛОМЖ БҮРДЭВ WWW.NEWS.MN  НИЙТЭЛСЭН:2025/12/05     Н.ЦЭРЭНСАМБУУ: ГАДААДЫН ХӨРӨНГӨ ОРУУЛАЛТААР БОР ТЭЭГИЙН ОРДЫГ ЭДИЙН ЗАСГИЙН ЭРГЭЛТЭД ОРУУЛНА WWW.EAGLE.MN НИЙТЭЛСЭН:2025/12/04     С.БЯМБАЦОГТ: ЗЭС ХАЙЛУУЛАХ ҮЙЛДВЭРИЙГ БАРИХ ХӨРӨНГӨ ОРУУЛАГЧИЙГ НЭЭЛТТЭЙ СОНГОН ШАЛГАРУУЛНА WWW.ITOIM.MN НИЙТЭЛСЭН:2025/12/04     NETFLIX-ИЙН МОНГОЛД ХИЙХ ШИНЭ НЭВТРҮҮЛГИЙН НӨЛӨӨ БА АЛГАН ДЭЭР ТАВЬСАН БОЛОМЖОО АШИГЛАХУЙ WWW.ITOIM.MN НИЙТЭЛСЭН:2025/12/04    

Oyu Tolgoi announces Shaft 2 construction completion www.montsame.mn

Ulaanbaatar /MONTSAME/. On December 13, today, Oyu Tolgoi LLC celebrated the completion of Shaft 2 of the world-class OT underground project in Khanbogd soum, Umnugobi aimag, which is a significant milestone for the project.

The ceremony was attended by national contractors who were crucial for the development of one of the world’s largest and most modern shafts project and other key stakeholders.

In special remarks delivered at the celebration event by Ambassador Batsukh Galsan, Chairman of the Board of Directors of Oyu Tolgoi LLC, highlighted the great support provided by the Government of Mongolia for this remarkable achievement, which increases Mongolia’s global competitiveness in terms of the mining and technology development.

Armando Torres, Chief Executive Officer of Oyu Tolgoi LLC said, “Shaft 2 construction – from sinking through to equipping – has taken three years and four months in total. Close to 50 national companies and 2,500 people worked safely on Shaft 2 for approximately 2.6 million hours to complete this critical and complex piece of infrastructure that will accelerate the underground development of our Oyu Tolgoi mine”.

Shaft 2 with a depth of 1,284 metres is the main production shaft and primary access point for people and materials and provides infrastructure for the materials handling system in the underground mine. Its production hoist is the largest Koepe (Friction) rope hoist system in the world with two 60 tonne capacity skips capable of hoisting 28,000 tonnes of ore per day at a maximum speed of 59km/hr.

Shaft 2 can carry 300 people per cage cycle versus a maximum of 60 people per cage cycle through Shaft 1. Shaft 2’s hoist rope-up process took 23 days by a team of approximately 500 people – one of the safest and most efficient rope-ups undertaken anywhere in the world.

Once Shaft 2 is fully commissioned and receives state licensing, it enables the following two important steps forward for the underground mine:

- Additional crews, materials and equipment to be transported and operate underground and,

- More rock to be removed from underground to enable further development and access to the ore body

From this point, the number of people working underground will no longer be constrained by the Service lift capacity of Shaft 1, but rather by volume of air moving through the underground via the existing ventilation (shafts 1, 2 and 5). Additional ventilation capacity is under construction with two more ventilation shafts - shaft 3 (intake) and 4 (exhaust). Currently, 700 people are able to work underground per shift.



Published Date:2019-12-16