1 DEPUTY PRIME MINISTER S.AMARSAIKHAN DISMISSED FOR VIOLATING ACCOUNTABILITY AGREEMENT WWW.GOGO.MN PUBLISHED:2025/10/29      2 STATE EMERGENCY COMMISSION ORDERS READINESS AMID FUEL-SHORTAGE RISKS WWW.GOGO.MN PUBLISHED:2025/10/29      3 WORLD BANK TO ASSIST MONGOLIA IN COP17 PREPARATIONS WWW.MONTSAME.MN PUBLISHED:2025/10/29      4 CRIMINAL INVESTIGATION LAUNCHED AGAINST MP D.AMARBAYASGALAN WWW.GOGO.MN PUBLISHED:2025/10/28      5 MONGOLIA AND GERMANY TO HOLD NEGOTIATIONS ON DEVELOPMENT COOPERATION WWW.MONTSAME.MN PUBLISHED:2025/10/28      6 MONGOLIAN HEALTH WORKERS BEGIN STRIKE AFTER EIGHT DAYS OF PROTEST WWW.ASIANEWS.NETWORK PUBLISHED:2025/10/28      7 STEPPE FIRE DESTROYS 800 HECTARES OF LAND IN EASTERN MONGOLIA WWW.XINHUANET.COM PUBLISHED:2025/10/28      8 MONGOLIA’S CORRUPTION PROBE AT OYU TOLGOI MINING OPERATIONS UNFOLDS WWW.DISCOVERYALERT.COM.AU PUBLISHED:2025/10/28      9 RIO TINTO AND SPIC QIYUAN BEGIN BATTERY-SWAP TRUCK TRIAL IN MONGOLIA WWW.MINING-TECHNOLOGY.COM PUBLISHED:2025/10/28      10 THE EUROPEAN UNION - MONGOLIA BUSINESS AND INVESTMENT FORUM LAUNCHES A NEW ERA OF ECONOMIC PARTNERSHIP WWW.EEAS.EUROPA.EU PUBLISHED:2025/10/28      "С.АМАРСАЙХАН ХАРИУЦЛАГЫН ГЭРЭЭ ЗӨРЧСӨН ТУЛ ЕРӨНХИЙ САЙД Г.ЗАНДАНШАТАР АЛБАН ТУШААЛААС НЬ ОГЦРУУЛСАН" WWW.EAGLE.MN НИЙТЭЛСЭН:2025/10/29     ЗГ: ГЭР БҮЛИЙН ТУХАЙ ХУУЛИЙН ШИНЭЧИЛСЭН НАЙРУУЛГЫГ ХЭЛЭЛЦЭНЭ WWW.NEWS.MN НИЙТЭЛСЭН:2025/10/29     ҮСХ: ДИЗЕЛИЙН ТҮЛШ ЛИТР ТУТАМДАА 74 ТӨГРӨГӨӨР ӨСӨЖ ₮3014 БОЛОВ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/10/29     ЭНЭ ОНЫ ЭХНИЙ 10 САРД 14,785 ХҮҮХЭД ХҮЧИРХИЙЛЭЛД ӨРТЖЭЭ WWW.NEWS.MN НИЙТЭЛСЭН:2025/10/29     РИО ТИНТО ГРУПП ОЮУТОЛГОЙ ХХК-Д АВЛИГЫН ЭСРЭГ ШАЛГАЛТ ЭХЛҮҮЛЭВ WWW.NEWS.MN НИЙТЭЛСЭН:2025/10/28     УОК: ЭРСДЭЛД БЭЛЭН БАЙХЫГ ҮҮРЭГ БОЛГОВ WWW.NEWS.MN НИЙТЭЛСЭН:2025/10/28     ЛАГ ШАТААХ ҮЙЛДВЭР ТӨСЛИЙГ ТӨР, ХУВИЙН ХЭВШЛИЙН ТҮНШЛЭЛЭЭР ХЭРЭГЖҮҮЛНЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/10/28     УЛААНБААТАР-СИНГАПУРЫН ЧИГЛЭЛД ШУУД НИСЛЭГ ҮЙЛДЭНЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/10/28     ЗАЙСАНГИЙН ГҮҮРИЙГ 54 ЖИЛИЙН ДАРАА БҮРЭН ШИНЭЧИЛЛЭЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/10/28     ЦЕГ-ЫН ДАРГААР Ж.БОЛДЫГ ТОМИЛЛОО WWW.ITOIM.MN НИЙТЭЛСЭН:2025/10/28    

Rio Tinto slows expansion of Oyu Tolgoi copper mine in Mongolia www.ft.com

Rio Tinto has slowed work on the underground expansion of its giant copper mine in Mongolia’s Gobi desert, raising the prospect of further delays at its most important project.

The Anglo-Australian miner said the movement of goods and people, including overseas contractors and technical experts, had become more difficult in Mongolia and across the Chinese border after the first case of the coronavirus was recorded in the country and the government took action to limit its spread.

As a result, work on a multibillion underground expansion of the Oyu Tolgoi copper mine had been slowed, Rio said.

“This is slowing down construction activity at the underground project,” said Arnaud Soirat, the head of Rio’s copper and diamonds business. “It is too early to determine the impact of this and the team is doing all they can to minimise the disruption in a challenging environment.”

The company said it would update the market once more information was available and that operations in the open pit at Oyu Tolgoi and deliveries to customers in China were continuing as normal.

The underground expansion of Oyu Tolgoi is Rio’s most important growth project and will increase its production of copper at a time when the shift to renewable energy is driving growing demand for the metal for use in electric vehicles and wind turbines.

But the project, aimed at increasing output to more than 500,000 ounces a year, has been dogged by problems.

Last year Rio warned of a 16 to 30-month delay to first production — which is now expected between May 2022 and June 2023 — and a cost blowout of $1.2bn-$1.9bn. The company blamed difficult ground conditions.

Rio expects to complete a new mine design by the end of June and reveal new cost and timing estimates in the second half of the year.

Shares in Rio fell 5.8 per cent to 3,082p, close to a three-year low.

“This is likely to be the first of many changes to the underlying project path, production profile and capex spending across not just Rio Tinto but the entire mining industry,” said Tyler Broda, analyst at RBC Capital Markets.

“Balance sheets in the sector generally remain very strong, but like almost all other industries, the potential for operational stoppages is likely to create a material build of working capital. We see the miners generally being in a strong relative position to cope but clearly these are volatile times and estimates and forecasts are likely to be changing rapidly.”

Canadian group Lundin Mining has announced the suspension of construction at its Neves-Corvo zinc expansion project in Portugal because of travel restrictions related to the coronavirus.



Published Date:2020-03-17