1 43,000 PASSENGER CARS IMPORTED IN THE FIRST HALF OF 2026 WWW.GOGO.MN PUBLISHED:2026/08/12      2 OIL REFINERY CONSTRUCTION TO BE INTENSIFIED AND LEGISLATIVE BOTTLENECKS REMOVED WWW.MONTSAME.MN PUBLISHED:2026/08/12      3 TEN YEARS OF 'HUNNU ROCK': THE HU LAUNCHES NEW WORLD TOUR WWW.MONTSAME.MN PUBLISHED:2026/08/12      4 NATIONAL AI COUNCIL ESTABLISHED TO DRIVE DIGITAL ECONOMY WWW.MONTSAME.MN PUBLISHED:2026/08/12      5 THE MAGIC OF MONGOLIA: WHY PEOPLE VISIT THE MOST SPARSELY POPULATED COUNTRY IN THE WORLD WWW.JACKSFLIGHTCLUB.COM PUBLISHED:2026/08/12      6 THE MOST EXPENSIVE MISTAKE MONGOLIAN COMPANIES KEEP MAKING AND CALLING IT A HIRING DECISION (BLOG) WWW.LAMBDA.GLOBAL PUBLISHED:2026/08/12      7 MONGOLIA SUCCESSFULLY TESTS INTERCITY FREIGHT TRANSPORT WITH HEAVY ELECTRIC TRUCKS FOR THE FIRST TIME WWW.OPEN.KG PUBLISHED:2026/08/12      8 MONGOLIA RATIONS GASOLINE AS FUEL SHORTAGES SEND DRIVERS INTO LONG LINES WWW.INTELLINEWS.COM PUBLISHED:2026/08/12      9 VIEWS EXCHANGED WITH ADB ON EDUCATION SECTOR REFORM AND COOPERATION WWW.MONTSAME.MN PUBLISHED:2026/08/12      10 “FOREIGNERS WHO LEARN ABOUT CHINGGIS KHAAN THROUGH HISTORY AND THE HU THROUGH MUSIC ARE BECOMING MORE INTERESTED IN THE MONGOLIAN LANGUAGE” WWW.GOGO.MN PUBLISHED:2026/08/12      Ц.САНДАГ-ОЧИР: МОНГОЛ УЛСЫН НИЙТ ГАЗАР НУТГИЙН 81.9 ХУВЬ ЦӨЛЖИЛТӨД ӨРТСӨН БАЙНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/08/12     МӨНГӨНИЙ БОДЛОГЫН ХҮҮГ 0.5 ХУВИАР ӨСГӨВ WWW.NEWS.MN НИЙТЭЛСЭН:2026/08/12     ШАТАХУУН ОЛГОДОГ ЗОХИЦУУЛАЛТЫГ БЯМБА ГАРАГААР ТАСАЛБАР БОЛГОНО WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/08/12     БАГАХАНГАЙ-ХӨШИГИЙН ХӨНДИЙ-ЭМЭЭЛТ ЧИГЛЭЛИЙН 214.9 КМ ТӨМӨР ЗАМ ИРЭХ САРД АШИГЛАЛТАД ОРНО WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/08/12     "НЕФТЬ БОЛОВСРУУЛАХ ҮЙЛДВЭРИЙГ ТҮШИГЛЭН ТЕХНОЛОГИЙН ПАРК БАЙГУУЛНА" WWW.NEWS.MN НИЙТЭЛСЭН:2026/08/12     “БАЯНХОШУУ ДЭД ТӨВ”-ИЙН ДАРААГИЙН 150 АЙЛЫН БАРИЛГЫН АЖИЛ 92 ХУВЬТАЙ БАЙНА WWW.GOGO.MN НИЙТЭЛСЭН:2026/08/12     НАЙМДУГААР САРЫН ШАТАХУУНЫ ХЭРЭГЛЭЭГ БҮРЭН ХАНГАХ НӨХЦӨЛ БҮРДЖЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/08/12     БАГАХАНГАЙ -ХӨШИГИЙН ХӨНДИЙ - ЭМЭЭЛТ ЧИГЛЭЛИЙН ТӨМӨР ЗАМЫН ТӨСЛИЙГ ХЭЛЭЛЦЭНЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/08/12     МОНГОЛ ДАХЬ ГАДААД АЖИЛЧДЫН ТОО 43 ХУВИАР ӨСЖЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/08/12     "ШАТАХУУНЫ НӨӨЦГҮЙ БОЛСОН УЛС, ОРНУУД ЗАЙНААС АЖИЛЛАХ БОДЛОГО ХЭРЭГЖҮҮЛЖ ЭХЭЛСЭН" WWW.GOGO.MN НИЙТЭЛСЭН:2026/08/12    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

Rio Tinto slows expansion of Oyu Tolgoi copper mine in Mongolia www.ft.com

Rio Tinto has slowed work on the underground expansion of its giant copper mine in Mongolia’s Gobi desert, raising the prospect of further delays at its most important project.

The Anglo-Australian miner said the movement of goods and people, including overseas contractors and technical experts, had become more difficult in Mongolia and across the Chinese border after the first case of the coronavirus was recorded in the country and the government took action to limit its spread.

As a result, work on a multibillion underground expansion of the Oyu Tolgoi copper mine had been slowed, Rio said.

“This is slowing down construction activity at the underground project,” said Arnaud Soirat, the head of Rio’s copper and diamonds business. “It is too early to determine the impact of this and the team is doing all they can to minimise the disruption in a challenging environment.”

The company said it would update the market once more information was available and that operations in the open pit at Oyu Tolgoi and deliveries to customers in China were continuing as normal.

The underground expansion of Oyu Tolgoi is Rio’s most important growth project and will increase its production of copper at a time when the shift to renewable energy is driving growing demand for the metal for use in electric vehicles and wind turbines.

But the project, aimed at increasing output to more than 500,000 ounces a year, has been dogged by problems.

Last year Rio warned of a 16 to 30-month delay to first production — which is now expected between May 2022 and June 2023 — and a cost blowout of $1.2bn-$1.9bn. The company blamed difficult ground conditions.

Rio expects to complete a new mine design by the end of June and reveal new cost and timing estimates in the second half of the year.

Shares in Rio fell 5.8 per cent to 3,082p, close to a three-year low.

“This is likely to be the first of many changes to the underlying project path, production profile and capex spending across not just Rio Tinto but the entire mining industry,” said Tyler Broda, analyst at RBC Capital Markets.

“Balance sheets in the sector generally remain very strong, but like almost all other industries, the potential for operational stoppages is likely to create a material build of working capital. We see the miners generally being in a strong relative position to cope but clearly these are volatile times and estimates and forecasts are likely to be changing rapidly.”

Canadian group Lundin Mining has announced the suspension of construction at its Neves-Corvo zinc expansion project in Portugal because of travel restrictions related to the coronavirus.



Published Date:2020-03-17