1 D. DALAIJARGAL: URANIUM MINING PROJECT ADVANCES FAST WITH FRENCH FUNDING WWW.MONGOLIANMININGJOURNAL.COM  PUBLISHED:2025/12/05      2 MONGOLIA, INDIA TO ADVANCE STRATEGIC PARTNERSHIP IN DIGITAL DEVELOPMENT AND INNOVATION WWW.MONTSAME.MN PUBLISHED:2025/12/05      3 POPE LEO MEETS WITH THE PRESIDENT OF MONGOLIA WWW.VATICANNEWS.VA PUBLISHED:2025/12/05      4 NATIONAL PROTECTED AREA CONSULTATION TARGETS STRONGER RANGER SYSTEM WWW.MONTSAME.MN PUBLISHED:2025/12/05      5 RIO TINTO REVISES UP 2025 COPPER PRODUCTION FORECAST AS MONGOLIAN PROJECT ACCELERATES OPERATIONS WWW.NEWS.METAL.COM  PUBLISHED:2025/12/05      6 MONGOLIA CALLS PUBLIC HEARINGS AHEAD OF LIKELY PUSH TO RENEGOTIATE RIO TINTO TERMS ON GIANT COPPER MINE WWW.INTELLINEWS.COM PUBLISHED:2025/12/05      7 MONGOLIA RECEIVES HIGHEST NUMBER OF FOREIGN TOURISTS SINCE THE BEGINNING OF 2025 WWW.XINHUANET.COM PUBLISHED:2025/12/05      8 MONGOLIA SIGNALS READINESS TO CONTRIBUTE TO GLOBAL FIGHT AGAINST DESERTIFICATION WWW.QAZINFORM.COM PUBLISHED:2025/12/04      9 MONGOLIA’S FOREIGN EXCHANGE RESERVES REACH USD 6 BILLION WWW.MONTSAME.MN PUBLISHED:2025/12/04      10 FUEL SUPPLY STRENGTHENED AS DECEMBER PURCHASE ORDERS CONFIRMED WWW.MONTSAME.MN PUBLISHED:2025/12/04      МАЛ, ТЭЖЭЭВЭР АМЬТНЫ ТООЛЛОГО НЯМ ГАРАГТ ЭХЭЛНЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/12/05     Ш.РАДНААСЭД ЕРӨНХИЙ САЙДЫН АХЛАХ ЗӨВЛӨХ БОЛОВ WWW.NEWS.MN НИЙТЭЛСЭН:2025/12/05     АШИГТ МАЛТМАЛЫН 8 ЗӨВШӨӨРЛИЙН ХАРИУД ₮2.7 ТЭРБУМЫГ АВСАН Ш.ГАНХУЯГ, ӨГСӨН ЭДВАРД СҮРЭН НАРЫГ 1 САР ХОРИВ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/12/05     ЕРӨНХИЙЛӨГЧ У.ХҮРЭЛСҮХ ГЭГЭЭН ШИРЭЭТ УЛСЫН ТӨРИЙН ТЭРГҮҮНТЭЙ УУЛЗЛАА WWW.EAGLE.MN НИЙТЭЛСЭН:2025/12/05     ТАВАНТОЛГОЙ-ГАШУУНСУХАЙТ ЧИГЛЭЛИЙН ТӨМӨР ЗАМААР ТАВАН САРД 3 САЯ ТОНН НҮҮРС ТЭЭВЭРЛЭВ WWW.EGUUR.MN  НИЙТЭЛСЭН:2025/12/05     MONGOLIA FOCUS: МОНГОЛД ӨӨРИЙГӨӨ ЦЕНЗУРДЭХ ҮЗЭГДЭЛ НЭМЭГДСЭН НЬ АРДЧИЛЛЫН ЧАНАР ДОРОЙТОЖ БУЙН ИЛРЭЛ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/12/05     11575 АЙЛЫН ОРОН СУУЦ БАРИХ БОЛОМЖ БҮРДЭВ WWW.NEWS.MN  НИЙТЭЛСЭН:2025/12/05     Н.ЦЭРЭНСАМБУУ: ГАДААДЫН ХӨРӨНГӨ ОРУУЛАЛТААР БОР ТЭЭГИЙН ОРДЫГ ЭДИЙН ЗАСГИЙН ЭРГЭЛТЭД ОРУУЛНА WWW.EAGLE.MN НИЙТЭЛСЭН:2025/12/04     С.БЯМБАЦОГТ: ЗЭС ХАЙЛУУЛАХ ҮЙЛДВЭРИЙГ БАРИХ ХӨРӨНГӨ ОРУУЛАГЧИЙГ НЭЭЛТТЭЙ СОНГОН ШАЛГАРУУЛНА WWW.ITOIM.MN НИЙТЭЛСЭН:2025/12/04     NETFLIX-ИЙН МОНГОЛД ХИЙХ ШИНЭ НЭВТРҮҮЛГИЙН НӨЛӨӨ БА АЛГАН ДЭЭР ТАВЬСАН БОЛОМЖОО АШИГЛАХУЙ WWW.ITOIM.MN НИЙТЭЛСЭН:2025/12/04    

Government to bear expenses of Tavan Tolgoi Power Plant project www.montsame.mn

Ulaanbaatar /MONTSAME/. At its regular weekly meeting held today, the cabinet decided to build 450 MW Tavan Tolgoi Power Plant (TTPP) in Umnugobi aimag between 2020 and 2024, based on a ready-made feasibility study of 2013, analyses on its water and coal supply and infrastructure facilities, and environment assessments, without changing its current location in the Tavan Tolgoi coal mining area.

The government is responsible for funding the TTPP project, which will be made available from every possible financial sources, including foreign loans, said Minister of Energy Ts.Davaasuren to the press after the cabinet meeting.

In 2018, the government reached an agreement with the Oyu Tolgoi LLC for the construction of the Tavan Tolgoi-based power solution for the Oyu Tolgoi copper-gold mine by June 30, 2023.

In February 2020, Turquoise Hill Resources, an international mining company, who owns 66 percent of the Oyu Tolgoi mine in Mongolia, has submitted a TTPP Feasibility Study, based on a 300 MW coal fired power plant to be located approximately 150 kilometers from the Oyu Tolgoi mine in Tsogttsetsii soum of Umnugobi aimag, with a total project cost estimate of up to USD 924 million.

However, according to Minister Davaasuren, the Oyu Tolgoi’s proposal on the TTPP project with development cost 2-3 times higher than world market prices is financially impossible to be realized. “It also has been considered that the date when Mongolia starts receiving dividends from Oyu Tolgoi could be postponed further due to the high cost of the TTPP construction” added the Minister.

The TTPP project with a payback period of 5 years will cost 30 percent less than Oyu Tolgoi’s proposed investment and the cost of energy generation is estimated to be 50 percent cheaper.

“Considering the fact that the annual spending on power purchase for Oyu Tolgoi from China to support its operations reaches USD 170-200 million and it is calculated to take around five years for the government of Mongolia to recover the cost of TTPP project investment, said Minister Davaasuren.

Once it is built, the TTPP holds a number of advantages of ensuring reliable power supply for the mining industry in southern Mongolia and increasing the economic benefits of the Oyu Tolgoi project by saving coal transportation costs. The state-run TTPP, which will supply electricity to the Oyu Tolgoi mine, will be established at the Erdenes Tavan Tolgoi JSC, government-owned company, reports the Cabinet Secretariat.



Published Date:2020-04-08