1 DEPUTY PRIME MINISTER S.AMARSAIKHAN DISMISSED FOR VIOLATING ACCOUNTABILITY AGREEMENT WWW.GOGO.MN PUBLISHED:2025/10/29      2 STATE EMERGENCY COMMISSION ORDERS READINESS AMID FUEL-SHORTAGE RISKS WWW.GOGO.MN PUBLISHED:2025/10/29      3 WORLD BANK TO ASSIST MONGOLIA IN COP17 PREPARATIONS WWW.MONTSAME.MN PUBLISHED:2025/10/29      4 CRIMINAL INVESTIGATION LAUNCHED AGAINST MP D.AMARBAYASGALAN WWW.GOGO.MN PUBLISHED:2025/10/28      5 MONGOLIA AND GERMANY TO HOLD NEGOTIATIONS ON DEVELOPMENT COOPERATION WWW.MONTSAME.MN PUBLISHED:2025/10/28      6 MONGOLIAN HEALTH WORKERS BEGIN STRIKE AFTER EIGHT DAYS OF PROTEST WWW.ASIANEWS.NETWORK PUBLISHED:2025/10/28      7 STEPPE FIRE DESTROYS 800 HECTARES OF LAND IN EASTERN MONGOLIA WWW.XINHUANET.COM PUBLISHED:2025/10/28      8 MONGOLIA’S CORRUPTION PROBE AT OYU TOLGOI MINING OPERATIONS UNFOLDS WWW.DISCOVERYALERT.COM.AU PUBLISHED:2025/10/28      9 RIO TINTO AND SPIC QIYUAN BEGIN BATTERY-SWAP TRUCK TRIAL IN MONGOLIA WWW.MINING-TECHNOLOGY.COM PUBLISHED:2025/10/28      10 THE EUROPEAN UNION - MONGOLIA BUSINESS AND INVESTMENT FORUM LAUNCHES A NEW ERA OF ECONOMIC PARTNERSHIP WWW.EEAS.EUROPA.EU PUBLISHED:2025/10/28      "С.АМАРСАЙХАН ХАРИУЦЛАГЫН ГЭРЭЭ ЗӨРЧСӨН ТУЛ ЕРӨНХИЙ САЙД Г.ЗАНДАНШАТАР АЛБАН ТУШААЛААС НЬ ОГЦРУУЛСАН" WWW.EAGLE.MN НИЙТЭЛСЭН:2025/10/29     ЗГ: ГЭР БҮЛИЙН ТУХАЙ ХУУЛИЙН ШИНЭЧИЛСЭН НАЙРУУЛГЫГ ХЭЛЭЛЦЭНЭ WWW.NEWS.MN НИЙТЭЛСЭН:2025/10/29     ҮСХ: ДИЗЕЛИЙН ТҮЛШ ЛИТР ТУТАМДАА 74 ТӨГРӨГӨӨР ӨСӨЖ ₮3014 БОЛОВ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/10/29     ЭНЭ ОНЫ ЭХНИЙ 10 САРД 14,785 ХҮҮХЭД ХҮЧИРХИЙЛЭЛД ӨРТЖЭЭ WWW.NEWS.MN НИЙТЭЛСЭН:2025/10/29     РИО ТИНТО ГРУПП ОЮУТОЛГОЙ ХХК-Д АВЛИГЫН ЭСРЭГ ШАЛГАЛТ ЭХЛҮҮЛЭВ WWW.NEWS.MN НИЙТЭЛСЭН:2025/10/28     УОК: ЭРСДЭЛД БЭЛЭН БАЙХЫГ ҮҮРЭГ БОЛГОВ WWW.NEWS.MN НИЙТЭЛСЭН:2025/10/28     ЛАГ ШАТААХ ҮЙЛДВЭР ТӨСЛИЙГ ТӨР, ХУВИЙН ХЭВШЛИЙН ТҮНШЛЭЛЭЭР ХЭРЭГЖҮҮЛНЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/10/28     УЛААНБААТАР-СИНГАПУРЫН ЧИГЛЭЛД ШУУД НИСЛЭГ ҮЙЛДЭНЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/10/28     ЗАЙСАНГИЙН ГҮҮРИЙГ 54 ЖИЛИЙН ДАРАА БҮРЭН ШИНЭЧИЛЛЭЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/10/28     ЦЕГ-ЫН ДАРГААР Ж.БОЛДЫГ ТОМИЛЛОО WWW.ITOIM.MN НИЙТЭЛСЭН:2025/10/28    

Turquoise Hill expects Oyu Tolgoi blowout to top $1.8bn www.mining.com

Canada’s Turquoise Hill Resources (TSX, NYSE: TRQ) said this week that an ongoing expansion of the giant Oyu Tolgoi copper-gold-silver mine in Mongolia is expected to cost as much as an additional $1.8 billion.

The Rio Tinto-controlled company and mine operator had expected the underground expansion to cost $5.3 billion when it was approved in 2015. Last year, however, Turquoise Hill flagged stability risks associated with the original project design, adding that amendments to it could increase costs by as much as an additional $1.9 billion.

The Vancouver-based miner also warned at the time of further delays of up to two and a half years, noting it wouldn’t know the exact scale of schedule and costs blowouts until mid-2020.

Oyu Tolgoi’s operator now says the expansion will need an estimated $1.5 billion, in a range of $1.3 billion to $1.8 billion. This may change due to any additional scheduling delays or increases in capital costs arising from the impacts of the covid-19 pandemic, it said.

In terms of project completion, Turquoise anticipates it would take two extra years than originally planned for the project to begin production, with a 21 to 29 months range.

“It is still a range. It is still fairly broad, but it is narrower (than the 2019 estimates), and importantly, it stayed within the range we have given,” chief executive officer Ulf Quellmann said.

Block caving
Turquoise Hill’s boss noted the company had selected block caving for the mine design, as it considers it a “more resilient mine plan that provides the best opportunity for success.”

Quellmann also said that the decision was based on an extensive trade-off analysis taking into account the reserve recovery, geotechnical, constructability, operability, schedule, as well as cost and value risks.

Turquoise Hill has $1.8 billion, which Quellmann says is sufficient to fund operations, underground and power development into the third quarter of 2021.

He also said that a definitive estimate will be published in the second half of the year.

Turquoise Hill is currently in discussions with Oyu Tolgoi’s 50.8%-owner, Rio Tinto (ASX, LON, NYSE: RIO), regarding a proposal for an interim $4 billion funding over and above the liquidity currently available.

The massive deposit was discovered in Mongolia’s south Gobi Desert in 2001. Rio Tinto gained control of it in 2012, with the government of Mongolia retaining one-third ownership of the asset.

The ongoing expansion is expected to lift production from 125,000–150,000 tonnes in 2019 to 560,000 tonnes at peak output, targeted for 2025. This would make it the biggest new copper mine to come on stream in several years.

Oyu Tolgoi produced 35,203 tonnes of copper and 26,154 ounces of gold in the first three months of this year, which puts it on track to achieve 2020 production guidance.

One of Rio Tinto’s top investors, US hedge fund Pentwater Capital, said in April it would push for a management shakeup at the operation, due to what it calls “a massive devaluation” of the asset.



Published Date:2020-05-17