1 MONGOLIA MARKS CENTENNIAL WITH A NEW COURSE FOR CHANGE WWW.EASTASIAFORUM.ORG PUBLISHED:2024/12/20      2 E-MART OPENS FIFTH STORE IN ULAANBAATAR, MONGOLIA, TARGETING K-FOOD CRAZE WWW.BIZ.CHOSUN.COM PUBLISHED:2024/12/20      3 JAPAN AND MONGOLIA FORGE HISTORIC DEFENSE PACT UNDER THIRD NEIGHBOR STRATEGY WWW.ARMYRECOGNITION.COM  PUBLISHED:2024/12/20      4 CENTRAL BANK LOWERS ECONOMIC GROWTH FORECAST TO 5.2% WWW.UBPOST.MN PUBLISHED:2024/12/20      5 L. OYUN-ERDENE: EVERY CITIZEN WILL RECEIVE 350,000 MNT IN DIVIDENDS WWW.GOGO.MN PUBLISHED:2024/12/20      6 THE BILL TO ELIMINATE THE QUOTA FOR FOREIGN WORKERS IN MONGOLIA HAS BEEN SUBMITTED WWW.GOGO.MN PUBLISHED:2024/12/20      7 THE SECOND NATIONAL ONCOLOGY CENTER TO BE CONSTRUCTED IN ULAANBAATAR WWW.MONTSAME.MN PUBLISHED:2024/12/20      8 GREEN BOND ISSUED FOR WASTE RECYCLING WWW.MONTSAME.MN PUBLISHED:2024/12/19      9 BAGANUUR 50 MW BATTERY STORAGE POWER STATION SUPPLIES ENERGY TO CENTRAL SYSTEM WWW.MONTSAME.MN PUBLISHED:2024/12/19      10 THE PENSION AMOUNT INCREASED BY SIX PERCENT WWW.GOGO.MN PUBLISHED:2024/12/19      КОКС ХИМИЙН ҮЙЛДВЭРИЙН БҮТЭЭН БАЙГУУЛАЛТЫГ ИРЭХ ОНЫ ХОЁРДУГААР УЛИРАЛД ЭХЛҮҮЛНЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2024/12/20     "ЭРДЭНЭС ТАВАНТОЛГОЙ” ХК-ИЙН ХУВЬЦАА ЭЗЭМШИГЧ ИРГЭН БҮРД 135 МЯНГАН ТӨГРӨГ ӨНӨӨДӨР ОЛГОНО WWW.MONTSAME.MN НИЙТЭЛСЭН:2024/12/20     ХУРИМТЛАЛЫН САНГИЙН ОРЛОГО 2040 ОНД 38 ИХ НАЯДАД ХҮРЭХ ТӨСӨӨЛӨЛ ГАРСАН WWW.NEWS.MN НИЙТЭЛСЭН:2024/12/20     “ЭРДЭНЭС ОЮУ ТОЛГОЙ” ХХК-ИАС ХЭРЛЭН ТООНО ТӨСЛИЙГ ӨМНӨГОВЬ АЙМАГТ ТАНИЛЦУУЛЛАА WWW.EAGLE.MN НИЙТЭЛСЭН:2024/12/20     Л.ОЮУН-ЭРДЭНЭ: ХУРИМТЛАЛЫН САНГААС НЭГ ИРГЭНД 135 МЯНГАН ТӨГРӨГИЙН ХАДГАЛАМЖ ҮҮСЛЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2024/12/20     “ENTRÉE RESOURCES” 2 ЖИЛ ГАРУЙ ҮРГЭЛЖИЛСЭН АРБИТРЫН МАРГААНД ЯЛАЛТ БАЙГУУЛАВ WWW.BLOOMBERGTV.MN НИЙТЭЛСЭН:2024/12/20     “ORANO MINING”-ИЙН ГЭРЭЭ БОЛОН ГАШУУНСУХАЙТ-ГАНЦМОД БООМТЫН ТӨСЛИЙН АСУУДЛААР ЗАСГИЙН ГАЗАР ХУРАЛДАЖ БАЙНА WWW.BLOOMBERGTV.MN НИЙТЭЛСЭН:2024/12/20     АЖИЛЧДЫН САРЫН ГОЛЧ ЦАЛИН III УЛИРЛЫН БАЙДЛААР ₮2 САЯ ОРЧИМ БАЙНА WWW.BLOOMBERGTV.MN НИЙТЭЛСЭН:2024/12/19     PROGRESSIVE EQUITY RESEARCH: 2025 ОН “PETRO MATAD” КОМПАНИД ЭЭЛТЭЙ БАЙХААР БАЙНА WWW.BLOOMBERGTV.MN НИЙТЭЛСЭН:2024/12/19     2026 ОНЫГ ДУУСТАЛ ГАДААД АЖИЛТНЫ ТОО, ХУВЬ ХЭМЖЭЭГ ХЯЗГААРЛАХГҮЙ БАЙХ ХУУЛИЙН ТӨСӨЛ ӨРГӨН МЭДҮҮЛЭВ WWW.EAGLE.MN НИЙТЭЛСЭН:2024/12/19    

Mongolia asks Rio Tinto to mutually cancel Oyu Tolgoi deal www.mining.com

Mongolia’s government is said to be actively seeking to cancel a deal with Rio Tinto (ASX, LON, NYSE: RIO) governing a $6.75 billion expansion of the Oyu Tolgoi copper mine in the Gobi Desert, as it looks to replace it with a new agreement.
Rather than acting unilaterally, which would risk future foreign investment projects, local authorities have suggested Rio Tinto to mutually terminate the plan. The end goal, Financial Times reports, is to reach a new agreement more beneficial to Mongolia.
Ulaanbaatar threatened in early January to halt construction at the mine, arguing that delays and higher-than-expected costs had eroded the economic benefits the country had hoped for.
Rio had in 2019 flagged stability risks associated with the original project design, which translated into as much as an additional $1.9 billion cost and a 30-month delay.
The miner confirmed in December the new estimate for the long-awaited underground expansion, adding that production would begin in October 2022.
Erdenes Oyu Tolgoi LLC, the Mongolian state-owned company that owns a third of the mine, reacted to the new timeline and budget by saying that Rio had not delivered on its 2015 promises.
Erdenes’ interest in Oyu Tolgoi is technically held through a 34% in a Mongolian company called Oyu Tolgoi LLC. The remaining stake belongs to Canada’s Turquoise Hill Resources (TSX, NYSE: TRQ), which is 50.79% owned by Rio Tinto.
The best scenario for everyone involved in the mine development, which will make Oyu Tolgoi the world’s fourth-largest copper operation once completed, is uncertain.
The Mongolian Parliamentary Working Group, formed in 2019, recommended exploring possibilities for a production sharing agreement and/or replacement of the equity interest with a special royalty.
Multiple issues
Rio and Turquoise Hill are focused on bringing the underground expansion into production, but they have locked horns on the financing aspects. The Canadian miner scored a temporary, but key victory last week, after an arbitration tribunal handling the spat granted the Canadian miner interim relief.
The ruling prevents the mining giant from restricting Turquoise Hill’s talks on funding and other matters with its fellow stakeholders in Oyu Tolgoi.
The miners also have other issues to resolve, including extending an existing power agreement beyond March. The operation is powered by coal-fired electricity imported from neighbouring China via overhead cables.
Then there is a potential restructuring of Oyu Tolgoi’s management team, as well as the need to ratify a 2019 statement of resources and reserves and a feasibility study prepared in 2020.
All these topics need to be addressed before Rio Tinto makes a major mining decision — an undercut — in May.
The technique is part of an extraction method known as block caving. It involves creating an artificial cavern below the ore body, allowing it to progressively collapse under its own weight.
Oyu Tolgoi’s expansion cost blowout to hit up to $1.8 billion
The copper-gold mine is located in the South Gobi region of Mongolia, about 550 km south of the capital Ulaanbaatar. (Source: Rio Tinto.)
Rio Tinto’s decision will also be affected by the view of its brand-new boss, Jakob Stausholm, who only two weeks ago overhauled the senior leadership team and created two new roles.
The mining giant has repeatedly said the underground expansion is its most important growth project. Once completed, Oyu Tolgoi will churn out 480,000 tonnes of copper a year from 2028 to 2036.


Published Date:2021-02-09