1 PRESIDENT KHURELSUKH WELCOMED BY PRESIDENT SERGIO MATTARELLA WWW.MONTSAME.MN PUBLISHED:2025/12/02      2 REAL ESTATE BROKERAGE FIRMS FACILITATE MNT 2.25 TRILLION IN PROPERTY SALES IN Q3 2025 WWW.MONTSAME.MN PUBLISHED:2025/12/02      3 TEAM MONGOLIA’S ATHLETIC PROWESS MAKES A SPLASH ON NETFLIX WWW.THEDIPLOMAT.COM PUBLISHED:2025/12/02      4 RUSSIA EXPECTS RATIFICATION OF EAEU TRADE AGREEMENT WITH MONGOLIA NO LATER THAN MID-2026 WWW.INTERFAX.COM PUBLISHED:2025/12/02      5 PRESIDENT KHURELSUKH ARRIVES IN ITALY FOR STATE VISIT WWW.MONTSAME.MN PUBLISHED:2025/12/01      6 INDIA WEIGHS MONGOLIAN COKING COAL IMPORTS DESPITE TRANSPORT HURDLES, SOURCE SAYS WWW.REUTERS.COM PUBLISHED:2025/12/01      7 SPONSORED HACKERS THREATEN GOVERNMENT’S SECURITY WWW.UBPOST.MN PUBLISHED:2025/12/01      8 PRESIDENT OF MONGOLIA TO PAY STATE VISIT TO ITALY WWW.QAZINFORM.COM  PUBLISHED:2025/11/30      9 PARLIAMENT APPROVES FIVE-YEAR DEVELOPMENT GUIDELINES OF MONGOLIA FOR 2026-2030 WWW.MONTSAME.MN PUBLISHED:2025/11/30      10 ‘MONGOLIA-UK INFRASTRUCTURE FORUM’ DISCUSSES DIGITAL CONSTRUCTION WWW.MONTSAME.MN PUBLISHED:2025/11/30      ИТАЛИ УЛСЫН ЕРӨНХИЙЛӨГЧ СЭРЖО МАТТАРЭЛЛА ИРЭХ ЖИЛ МОНГОЛД АЙЛЧИЛНА WWW.EAGLE.MN НИЙТЭЛСЭН:2025/12/02     ЕАЭЗХ-НЫ МОНГОЛТОЙ БАЙГУУЛСАН ХУДАЛДААНЫ ТҮР ХЭЛЭЛЦЭЭРИЙГ ИРЭХ ОНЫ ДУНД ҮЕЭС ХЭТРҮҮЛЭХГҮЙ БАТАЛНА WWW.ITOIM.MN НИЙТЭЛСЭН:2025/12/02     АВЛИГЫН АСУУДЛААР ГАДНЫН БАНКНЫ ХОРИГТ ОРСОН АХ, ДҮҮ ХОЁРЫН ОХИН КОМПАНИУД АЛТ, ГАЗРЫН ХОВОР ЭЛЕМЕНТИЙН ОРД ЭЗЭМШДЭГ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/12/02     РОЙТЕРС: ТЭЭВРИЙН ХҮНДРЭЛТЭЙ Ч МОНГОЛООС КОКСЖИХ НҮҮРСИЙГ ИМПОРТЛОХ АСУУДЛЫГ ЭНЭТХЭГ СУДАЛЖ БАЙНА WWW.ITOIM.MN НИЙТЭЛСЭН:2025/12/01     "ЭРДЭНЭС ТАВАНТОЛГОЙ" ХК ӨНГӨРСӨН САРД 2.4 ТОНН НҮҮРС БОРЛУУЛЖ, ТҮҮХЭН ДЭЭД АМЖИЛТАА ТОГТООЖЭЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/12/01     "ЦАГААН АЛТ" ХӨДӨЛГӨӨНӨӨР НООЛУУРЫН САЛБАРТ ₮28.7 ТЭРБУМЫН ХӨНГӨЛӨЛТТЭЙ ЗЭЭЛ ОЛГОЖЭЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/12/01     ИРЭХ ОНД НИЙСЛЭЛИЙН ЭРҮҮЛ МЭНДИЙН ГАЗАР, НИЙТИЙН ТЭЭВРИЙН БОДЛОГЫН ГАЗРЫГ ТАТАН БУУЛГАНА WWW.ITOIM.MN НИЙТЭЛСЭН:2025/12/01     SCMP: МОНГОЛ УЛС ШИНЭ ТӨМӨР ЗАМЫН ХОЛБОЛТУУДААР ЭДИЙН ЗАСГАА ТЭЛЭХИЙГ ЗОРЬЖ БАЙНА WWW.ITOIM.MN НИЙТЭЛСЭН:2025/12/01     МОНГОЛ УЛСЫН ЕРӨНХИЙЛӨГЧ У.ХҮРЭЛСҮХ БҮГД НАЙРАМДАХ ИТАЛИ УЛСАД ТӨРИЙН АЙЛЧЛАЛ ХИЙХЭЭР МОРДЛОО WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/11/30     МОНГОЛ УЛСЫН ХӨГЖЛИЙН ИРЭХ ТАВАН ЖИЛИЙН ҮНДСЭН ЧИГЛЭЛИЙГ БАТАЛЛАА WWW.GOGO.MN НИЙТЭЛСЭН:2025/11/30    

Talks with Rio Tinto on Oyu Tolgoi Project launches www.montsame.mn

The working group in charge of implementing the parliamentary resolution No.92 dated November 21, 2019, titled ‘Ensuring the interests of Mongolia in the exploitation of the Oyu Tolgoi gold-copper mine’ began the negotiations with Rio Tinto company delegates on April 12.
The government's working group, set up by the decree of the Prime Minister of Mongolia, has expressed its position to the investor side to terminate the Oyu Tolgoi Underground Mine Development and Financing Plan, also known as the ‘Dubai Agreement‘, and ensure the interest of Mongolia. This is because when the plan was first established, the initial cost estimates of the Oyu Tolgoi underground development plan were approved at USD 5.3 billion. Unfortunately, this cost estimate was increased by USD 1.4 billion or about 30 percent, reaching USD 6.75 billion, and the date when the first underground production to be achieved was extended by 22 months from the first estimation of January 2021. Moreover, it was calculated that Mongolia will not receive dividend payments until 2051 and will incur debts of USD 22 billion, which is prompting to reconsider the plan.
B.Solongoo, Deputy Chief of Cabinet Secretariat and a member of the working group, said during her interview with Mongolian National Broadcaster, “We will take all necessary measures to make the Oyu Tolgoi project as profitable as possible for the Mongolian side. I do not assume that the negotiations on this issue will end soon as the parliamentary resolution No. 92 commands very broad areas. In this regard, we have to work for the improvement of the entire framework agreement, such as the Investment Agreement of 2009, the Shareholders‘ Agreement of 2011, and to make the Oyu Tolgoi project more profitable for Mongolia as a whole."
She also said that independent experts are expected to make a conclusion on the issue of cost overrun in the underground development of Oyu Tolgoi by late June. Tax acts of MNT 377 billion and MNT 649.4 billion were imposed on Oyu Tolgoi LLC in 2018 and 2020 respectively. However, the company declined to accept the tax penalty of MNT 377 billion and initiated an arbitration proceeding at the London Court of International Arbitration.
"The government will defend its stance that the company must pay an appropriate amount of tax if it earns its income from Mongolia," stressed B. Solongoo.
80 percent of the total resources of the Oyu Tolgoi project will be mined underground. Currently, Oyu Tolgoi has an annual revenue of USD 1 billion from open-pit mining. With the opening of the underground mine, this revenue is expected to quadruple.