1 BUILDING MONGOLIA'S NEW, OLD CAPITAL AT KHARKHORUM WWW.THEDIPLOMAT.COM PUBLISHED:2026/01/08      2 BACKED BY INDONESIAN TYCOON, THIS LISTED FIRM RUSHES TO ACQUIRE A MONGOLIAN MINE WWW.CNBCINDONESIA.COM PUBLISHED:2026/01/08      3 PREPARATORY WORK LAUNCHED TO BRING THE BORTEEG DEPOSIT INTO ECONOMIC CIRCULATION WWW.MONTSAME.MN PUBLISHED:2026/01/08      4 TOURISM ORGANISATIONS TO RECEIVE “STAR” RATINGS WWW.GOGO.MN PUBLISHED:2026/01/08      5 CITIZENS TO GET 6 SERVICES AFTER SWITCH TO UNIFIED EMERGENCY NUMBER “112” WWW.GOGO.MN PUBLISHED:2026/01/08      6 MONGOLIA TO HOST GLOBAL WORLD HORSE DAY CELEBRATION WWW.MONTSAME.MN PUBLISHED:2026/01/08      7 THIS SACRED SITE IS ONE OF THE WORLD’S OLDEST NATURE RESERVES WWW.NATIONALGEOGRAPHIC.COM PUBLISHED:2026/01/08      8 MONGOLIA’S TOURISM SURGE: 1 MILLION VISITORS TARGETED & $1.6 BILLION REVENUE IN 2026 – WHAT AIRLINES LIKE AIR CHINA & MARRIOTT ARE DOING TO CASH IN! WWW.TRAVELANDTOURWORLD.COM PUBLISHED:2026/01/07      9 NEW FLIGHTS FROM MONGOLIA TO SINGAPORE, VIETNAM, CHINA, AND EUROPE IN 2026: HOW THESE ROUTES ARE REVOLUTIONIZING TRAVEL! WWW.TRAVELANDTOURWORLD.COM PUBLISHED:2026/01/07      10 ‘ULAANBAATAR TRAM’ TO CONNECT ZUNJIN AND SUKHBAATAR SQUARE IN 29 MINUTES WWW.MONTSAME.MN PUBLISHED:2026/01/07      НИЙСЛЭЛИЙН 19 БАЙРШИЛД 11.7 КМ АВТО ЗАМЫН БОРООНЫ УС ЗАЙЛУУЛАХ ШУГАМ УГСАРНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/01/08     "БНХАУ-ЫН НЭГ КОМПАНИТАЙ ШАТАХУУНЫ ГЭРЭЭ БАЙГУУЛСАН" WWW.NEWS.MN НИЙТЭЛСЭН:2026/01/08     ЕРӨНХИЙ САЙД Г.ЗАНДАНШАТАР “РИО ТИНТО-Д ХАТУУ ШААРДЛАГА ХҮРГҮҮЛНЭ WWW.NEWS.MN НИЙТЭЛСЭН:2026/01/08     МОНГОЛ УЛСЫН ГАДААД ВАЛЮТЫН НӨӨЦИЙН ХЭМЖЭЭ 27.1 ХУВИАР ӨСЛӨӨ WWW.NEWS.MN НИЙТЭЛСЭН:2026/01/08     БОРТЭЭГИЙН ОРДЫГ ЭДИЙН ЗАСГИЙН ЭРГЭЛТЭД ОРУУЛАХ БЭЛТГЭЛ АЖИЛ ЭХЭЛЛЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/01/08     ЭНЭ ОНД НИЙСЛЭЛИЙН ХЭМЖЭЭНД ГАЗАР ЧӨЛӨӨЛӨХ БАЙРШЛУУД WWW.GOGO.MN НИЙТЭЛСЭН:2026/01/08     ГААЛИЙН ЕРӨНХИЙ ГАЗРЫГ П.ДЭЛГЭРНАРАН УДИРДАНА WWW.EGUUR.MN НИЙТЭЛСЭН:2026/01/08     ЗЭС, ЭРХ МЭДЭЛ, ЭРСДЭЛ: ДЭЛХИЙН ГЕОПОЛИТИКИЙН ШАТРЫН ӨРӨГ ДЭЭРХ МОНГОЛ УЛС WWW.EGUUR.MN НИЙТЭЛСЭН:2026/01/07     КАНАДЫН AIR TRANSAT КОМПАНИ ТОРОНТО-УЛААНБААТАР ЧИГЛЭЛД ШУУД НИСЛЭГ ҮЙЛДЭНЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/01/07     М БАНК СИНГАПУРЫН ХӨРӨНГИЙН БИРЖИД АНХНЫ БОНДОО ГАРГАЛАА WWW.GOGO.MN НИЙТЭЛСЭН:2026/01/07    

Brakes and controls for underground conveying system in Mongolia www.australianmining.com.au

SUR Engineering relies on German manufacturer Dellner Bubenzer to service the mining industry with brake systems and monitoring technology.
Dellner Bubenzer recently supplied brakes for three 7100 tonnes per hour conveying systems, each with an installed power of two 5500 kW gearless drives, for a copper mine in Mongolia.
The scope of supply was including floating calliper brakes SFR50, brake discs, hydraulic power units, UPS, BCC3000 closed loop control systems as well as the complete encoder technology.
The main parameters of the brake like pad wear, stroke (air gap) and brake pad temperature are continuously monitored.
The brakes stop the conveyor within 10 seconds in loaded or unloaded condition. Depending on the parameter, like load, speed etc., the HPU and control unit provide different braking levels and scenarios.
The controlled braking process minimises the conveyor belt tension and reduces stresses in the connected equipment. The system is also able to perform the pre-programmed ramps and stopping curves after a power outage.
Redundant controls and HPUs guarantee highest system availability. The environmental conditions need a compact set-up of the brake units. The spring applied, hydraulically released, fail-safe brakes are able to equalise axial movement of the connected shafts.


Published Date:2021-07-22