1 MONGOLIA TO HOST UNCCD COP17 WITH PARTICIPATION OF 10,000 DELEGATES WWW.MONTSAME.MN PUBLISHED:2025/09/19      2 CNN'S BLUEPRINT SPOTLIGHTS THE INNOVATORS PROPELLING MONGOLIA INTO A DIGITAL FUTURE WWW.CNN.COM PUBLISHED:2025/09/19      3 WHAT IS DRIVING CLOSER JAPAN-MONGOLIA TIES? WWW.THEDIPLOMAT.MN PUBLISHED:2025/09/19      4 INFRASTRUCTURE CONSTRUCTION CONTINUES AT HUNNU CITY WWW.MONTSAME.MN PUBLISHED:2025/09/19      5 MONGOLIAN ENVOY LAUDS PM MODI’S LEADERSHIP, HAILS INDIA’S GROWING STATURE IN WORLD WWW.OMMCOMNEWS.COM  PUBLISHED:2025/09/19      6 SONSY PARTNERS WITH TUNED GLOBAL TO LAUNCH MONGOLIA’S FIRST WORLD-CLASS MUSIC APP WWW.GOGO.MN PUBLISHED:2025/09/19      7 DEPRESSION IDENTIFIED AS LEADING CAUSE OF WORK INABILITY WWW.UBPOST.MN PUBLISHED:2025/09/19      8 MONETARY POLICY RATE MAINTAINED WWW.MONTSAME.MN PUBLISHED:2025/09/18      9 BUURULJUUT POWER PLANT’S SECOND UNIT SET FOR DECEMBER 2025 COMMISSIONING WWW.MONTSAME.MN PUBLISHED:2025/09/18      10 CAPITAL MARKETS MONGOLIA ANNOUNCES MONGOLIA INVESTMENT FORUM: LONDON 2025 AT THE LONDON STOCK EXCHANGE WWW.NEWSFILECORP.COM PUBLISHED:2025/09/18      ГАШУУНСУХАЙТЫН ТӨМӨР ЗАМЫН ХИЛ ХОЛБОЛТЫН ГЭРЭЭГ ШАЛГАХ УИХ-ЫН ТҮР ХОРОО БАЙГУУЛНА WWW.ITOIM.MN НИЙТЭЛСЭН:2025/09/19     О.НОМИНЧИМЭГ: БҮХ ТӨРЛИЙН ТАМХИЙГ ТУСГАЙ ЗӨВШӨӨРӨЛТЭЙ ОРУУЛЖ ИРЭХ, 21 НАС ХҮРЭЭГҮЙ ХҮНД ТАМХИ БОРЛУУЛАХГҮЙ ӨӨРЧЛӨЛТ ХИЙНЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2025/09/19     СЗХ: “ГОВЬ” КОМПАНИ ХХК БОЛОХ АЛБАН ЁСНЫ ХҮСЭЛТ ИРҮҮЛЭЭГҮЙ WWW.ITOIM.MN НИЙТЭЛСЭН:2025/09/19     ЗАСГИЙН ГАЗРЫН 80 МЯНГАН ӨРХИЙГ ОРОН СУУЦАНД ХАМРУУЛАХ ТӨЛӨВЛӨГӨӨ WWW.NEWS.MN НИЙТЭЛСЭН:2025/09/19     МОНГОЛООС 115 САЯ ЖИЛИЙН НАСТАЙ ХАМГИЙН БАГА СУДЛАГДСАН ҮЛЭГ ГҮРВЭЛИЙН ЧУЛУУЖСАН БҮТЭН ОЛДВОРЫГ ИЛРҮҮЛЛЭЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/09/19     ЗАСГИЙН ГАЗАР ХООРОНДЫН ТӨМӨР ЗАМЫН ХИЛ ХОЛБОЛТЫН ХЭЛЭЛЦЭЭРИЙН ЦААНА КОМПАНИ ХООРОНДЫН ГЭРЭЭГ АЛДАГДАЛТАЙ БАЙГУУЛЖЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2025/09/19     ИРГЭДЭЭС 45,2 ТЭРБУМЫГ ЗАЛИЛСАН "БЭЛТЭС МӨРӨН" ХХК-ИЙН 9 ХҮНД ОНООСОН 2-12 ЖИЛИЙН ХОРИХ ЯЛЫГ ХЭВЭЭР ҮЛДЭЭЛЭЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/09/19     Г.ЗАНДАНШАТАР: 1.2 ТЭРБУМ АМ.ДОЛЛАРЫГ ГАДААДАД 3 ХУВИЙН ХҮҮТЭЙ ХАДГАЛУУЛЖ БАЙНА WWW.GOGO.MN НИЙТЭЛСЭН:2025/09/18     З.ЦОГТГЭРЭЛ: БАГШ НАРЫН ЦАЛИНГ 3.5 САЯ ТӨГРӨГ БОЛГОХЫГ ШААРДАЖ ОРОН ДАЯАР ЖАГСАНА WWW.ITOIM.MN НИЙТЭЛСЭН:2025/09/18     МОНГОЛ, САУДЫН АРАБЫН ХООРОНД ШУУД НИСЛЭГ ҮЙЛДЭХ НӨХЦӨЛ БҮРДЛЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/09/18    

Inner Mongolia's capacity phase-out unlikely to hamper ferroalloy output: sources www.spglobal.com

The Inner Mongolia government's decision to eliminate ferroalloy capacity in the region is expected to have limited impact on China's total ferrosilicon production, as new or replaced capacity will likely fill the production gap, industry sources told S&P Global Platts Feb. 23.
Inner Mongolia -- a major coal-mining area in northern China -- said it has implemented a plan requiring its ferroalloy industry to phase out submerged arc furnace with power consumption capacity of 25,000 kilovolt-ampere (kVA) and below before the end of 2022, according to an energy-saving plan released in the week to Feb. 18.
Further, the industry will remove 3.14 million mt of ferroalloy capacity during 2021-2022, the plan showed. The plan marks development policies covering China's 14th five-year period (2021-2025).
Given the slew of replacement projects released by the local government so far, there is not a huge time lag between eliminating "backward capacity" and commissioning of new capacity, sources said.
Inner Mongolia will strictly control any new capacity installation by energy-intensive industries, including steel, ferroalloy, and aluminum during 2021-2025, the plan showed.
Closed-type submerged arc furnace should be used for new or expanded silicomanganese alloy, high-carbon ferromanganese and high-carbon ferrochrome projects, with power consumption capacity higher than 30,000 kVA, according to the plan.
Capacity replacement and reduction in energy consumption should be implemented within the region if it is necessary to build new capacity, with the capacity replacement ratio set to 1.25:1, the Inner Mongolia government said late 2021. The region's overall ferroalloy production capacity has been capped at around 14 million mt/year during 2021-2025.
It remains unclear when the replacement ferrosilicon capacity would come onstream, sources said, adding that "backward capacity" production is expected to continue until the end of 2022 in view of healthy profit margins in the industry.
In addition to the ferrosilicon plans, the region is looking to wash out pig iron furnace for steelmaking with effective volume below 1200 m3, converter with nominal capacity of 100 mt and electric arc furnace with nominal capacity of 100 mt (50 mt for alloy steel) before the end of 2023, according to the plan. The region will eliminate ironmaking capacity of 6.65 million mt/year and steelmaking capacity of 6.2 million mt/year in 2021-2023.
 
 
 
 
 


Published Date:2022-02-24