1 OUTSTANDING BANK LOANS RISE 14.3 PERCENT WWW.MONTSAME.MN PUBLISHED:2026/09/24      2 CENTRAL ASIA AND MONGOLIA GROWTH TO REMAIN ROBUST WWW.EBRD.COM PUBLISHED:2026/09/24      3 A NEW OIL STORAGE FACILITY WITH A CAPACITY OF 16,000 CUBIC METERS HAS BEEN PUT INTO OPERATION IN MONGOLIA WWW.OPEN.KG PUBLISHED:2026/09/24      4 RUSSIA, MONGOLIA FORM WORKING GROUP TO EXAMINE FEASIBILITY OF A WESTERN RAIL CORRIDOR WWW.RUSSIASPIVOTTOASIA.COM PUBLISHED:2026/09/24      5 MONGOLIA SUBMITS CANDIDACY FOR UN SECURITY COUNCIL NON-PERMANENT SEAT FOR 2048–2049 WWW.MONTSAME.MN PUBLISHED:2026/09/24      6 ‘GASOLINE DISRUPTION MAY LAST 2 TO 3 YEARS’ WWW.UBPOST.MN PUBLISHED:2026/09/24      7 MONGOLIA, AUSTRALIA DISCUSS INCREASING OYU TOLGOI RETURNS AND LOCALIZING TECHNOLOGY WWW.GOGO.MN PUBLISHED:2026/09/24      8 PLAN PRESENTED TO REACH USD 5.5 BILLION FOREIGN INVESTMENT WWW.MONTSAME.MN PUBLISHED:2026/09/23      9 COAL PYROLYSIS PLANT TO BE BUILT IN BAGANUUR THROUGH PUBLIC-PRIVATE PARTNERSHIP WWW.MONTSAME.MN PUBLISHED:2026/09/23      10 TEMUULEN APPOINTED MINISTER OF JUSTICE AND INTERNAL AFFAIRS WWW.MONTSAME.MN PUBLISHED:2026/09/23      ШҮҮХЭЭС НАЙРУУЛАГЧ Б.БААТАРТ ХИЛИЙН ХОРИГ ТАВЬЖЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/26     "ХӨРӨНГӨ ОРУУЛАГЧДЫН ГОМДЛЫГ 30 ХОНОГТ ШИЙДВЭРЛЭХ ШИНЭ ЗОХИЦУУЛАЛТ ХЭРЭГЖИЖ ЭХЭЛСЭН" WWW.NEWS.MN НИЙТЭЛСЭН:2026/09/24     “МЯНГАД НАР” 19.8 МВТ-ЫН НАРНЫ ЦАХИЛГААН СТАНЦЫН ГҮЙЦЭТГЭЛ 40 ХУВЬТАЙ БАЙНА WWW.EAGLE.MN НИЙТЭЛСЭН:2026/09/24     ГОВИЙН БҮСЭД ЗАРЛАСАН СЭРГЭЭГДЭХ ЭРЧИМ ХҮЧНИЙ АУКЦИОНД ГУРВАН КОМПАНИЙН ХАМТАРСАН ТҮНШЛЭЛ ШАЛГАРЛАА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/24     ОРОН СУУЦНЫ ЗАЛИЛАГЧИД 2,779 ХҮНД 211.1 ТЭРБУМ ТӨГРӨГИЙН ХОХИРОЛ УЧРУУЛЖЭЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2026/09/24     ИПОТЕКИЙН ЗЭЭЛИЙН ХҮСЭЛТҮҮД 7-8 ЖИЛ ХҮЛЭЭХ ООЧЕР ҮҮСЧЭЭ WWW.NEWS.MN НИЙТЭЛСЭН:2026/09/24     ХӨРӨНГӨ ОРУУЛАГЧДЫН ГОМДОЛ ШИЙДВЭРЛЭЛТИЙГ ХӨРӨНГӨ ОРУУЛАЛТ, ХУДАЛДААНЫ ГАЗАРТ ШИЛЖҮҮЛЛЭЭ WWW.GOGO.MN НИЙТЭЛСЭН:2026/09/24     ЕРӨНХИЙЛӨГЧ У.ХҮРЭЛСҮХ НҮБ-ЫН ЕРӨНХИЙ НАРИЙН БИЧГИЙН ДАРГАТАЙ УУЛЗЛАА WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/09/24     Т.ДОРЖХАНД: СЭРГЭЭГДЭХ ЭРЧИМ ХҮЧ, ДАТА ТӨВ ЗЭРЭГ 5 САЛБАРТ ГАДНЫН ХӨРӨНГӨ ОРУУЛАЛТ ТАТАХ БОДЛОГО БАРИМТАЛНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/23     Ц.САНДАГ-ОЧИР: 2028 ОНД 600 МЯНГАН ТОНН САЙЖРУУЛСАН ТҮЛШ НИЙЛҮҮЛЭХ ХҮЧИН ЧАДАЛТАЙ ҮЙЛДВЭР АШИГЛАЛТАД ОРУУЛНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/23    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

Opening of Zuunbayan-Khangi railway set to deliver major boost to Mongolian exports and economy www.finance.yahoo.com

The Prime Minister of Mongolia, L. Oyun-Erdene, has today opened a major new rail link which will provide a significant boost to the country's export competitiveness and wider economy as part of the Government's 'New Recovery Policy'.
The Prime Minister of Mongolia L. Oyun-Erdene speaking at the opening of the Zuunbayan-Khangi railway on 25 November.
The Prime Minister of Mongolia L. Oyun-Erdene speaking at the opening of the Zuunbayan-Khangi railway on 25 November.
The Zuunbayan-Khangi railway, which runs for 226.9km across south eastern Mongolia, provides a vital connection between the Tavantolgoi-Zuunbayan railway and the Khangi-Mandal border crossing on the Mongolia-China border.
Through a further connection to a new railway under construction on the Chinese border, the transportation distance for freight across this important economic corridor will be almost halved, significantly boosting trade in minerals such as iron ore.
With construction of the Zuunbayan-Khangi railway only beginning in March 2022, the completion of this project is set to lead to a rapid 30% increase in Mongolian export freight volume, with annual freight volumes set to stabilise at around twice their current level of 10.4 million tonnes from 2025, significantly boosting state budget revenues and local employment.
Speaking following the opening, the Prime Minister of Mongolia, L. Oyun-Erdene, said:
"The new Zuunbayan-Khangi railway was built in just eight months, through a public-private-partnership investment model, and is Mongolia's new gateway for transporting mining export products competitively to the global marketplace.
" Today's opening marks a major milestone in the Government of Mongolia's 'New Recovery Policy', which is focused on strengthening the country's economy following the pandemic and making Mongolia into a leading Asian country by 2050."
Having no access to the sea, Mongolia relies on 42 dry-road border points for its trade, yet as of March this year only three of them were connected by railroads. The completion of this project delivers a second new railway crossing in the south of the country, and the ambition of the New Recovery Policy is to ensure that all border points are connected by roads, railways and highways in consecutive steps.
180 companies and over 3,500 workers took part in the construction of the railway.


Published Date:2022-11-28