1 MONGOLIA MARKS CENTENNIAL WITH A NEW COURSE FOR CHANGE WWW.EASTASIAFORUM.ORG PUBLISHED:2024/12/20      2 E-MART OPENS FIFTH STORE IN ULAANBAATAR, MONGOLIA, TARGETING K-FOOD CRAZE WWW.BIZ.CHOSUN.COM PUBLISHED:2024/12/20      3 JAPAN AND MONGOLIA FORGE HISTORIC DEFENSE PACT UNDER THIRD NEIGHBOR STRATEGY WWW.ARMYRECOGNITION.COM  PUBLISHED:2024/12/20      4 CENTRAL BANK LOWERS ECONOMIC GROWTH FORECAST TO 5.2% WWW.UBPOST.MN PUBLISHED:2024/12/20      5 L. OYUN-ERDENE: EVERY CITIZEN WILL RECEIVE 350,000 MNT IN DIVIDENDS WWW.GOGO.MN PUBLISHED:2024/12/20      6 THE BILL TO ELIMINATE THE QUOTA FOR FOREIGN WORKERS IN MONGOLIA HAS BEEN SUBMITTED WWW.GOGO.MN PUBLISHED:2024/12/20      7 THE SECOND NATIONAL ONCOLOGY CENTER TO BE CONSTRUCTED IN ULAANBAATAR WWW.MONTSAME.MN PUBLISHED:2024/12/20      8 GREEN BOND ISSUED FOR WASTE RECYCLING WWW.MONTSAME.MN PUBLISHED:2024/12/19      9 BAGANUUR 50 MW BATTERY STORAGE POWER STATION SUPPLIES ENERGY TO CENTRAL SYSTEM WWW.MONTSAME.MN PUBLISHED:2024/12/19      10 THE PENSION AMOUNT INCREASED BY SIX PERCENT WWW.GOGO.MN PUBLISHED:2024/12/19      КОКС ХИМИЙН ҮЙЛДВЭРИЙН БҮТЭЭН БАЙГУУЛАЛТЫГ ИРЭХ ОНЫ ХОЁРДУГААР УЛИРАЛД ЭХЛҮҮЛНЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2024/12/20     "ЭРДЭНЭС ТАВАНТОЛГОЙ” ХК-ИЙН ХУВЬЦАА ЭЗЭМШИГЧ ИРГЭН БҮРД 135 МЯНГАН ТӨГРӨГ ӨНӨӨДӨР ОЛГОНО WWW.MONTSAME.MN НИЙТЭЛСЭН:2024/12/20     ХУРИМТЛАЛЫН САНГИЙН ОРЛОГО 2040 ОНД 38 ИХ НАЯДАД ХҮРЭХ ТӨСӨӨЛӨЛ ГАРСАН WWW.NEWS.MN НИЙТЭЛСЭН:2024/12/20     “ЭРДЭНЭС ОЮУ ТОЛГОЙ” ХХК-ИАС ХЭРЛЭН ТООНО ТӨСЛИЙГ ӨМНӨГОВЬ АЙМАГТ ТАНИЛЦУУЛЛАА WWW.EAGLE.MN НИЙТЭЛСЭН:2024/12/20     Л.ОЮУН-ЭРДЭНЭ: ХУРИМТЛАЛЫН САНГААС НЭГ ИРГЭНД 135 МЯНГАН ТӨГРӨГИЙН ХАДГАЛАМЖ ҮҮСЛЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2024/12/20     “ENTRÉE RESOURCES” 2 ЖИЛ ГАРУЙ ҮРГЭЛЖИЛСЭН АРБИТРЫН МАРГААНД ЯЛАЛТ БАЙГУУЛАВ WWW.BLOOMBERGTV.MN НИЙТЭЛСЭН:2024/12/20     “ORANO MINING”-ИЙН ГЭРЭЭ БОЛОН ГАШУУНСУХАЙТ-ГАНЦМОД БООМТЫН ТӨСЛИЙН АСУУДЛААР ЗАСГИЙН ГАЗАР ХУРАЛДАЖ БАЙНА WWW.BLOOMBERGTV.MN НИЙТЭЛСЭН:2024/12/20     АЖИЛЧДЫН САРЫН ГОЛЧ ЦАЛИН III УЛИРЛЫН БАЙДЛААР ₮2 САЯ ОРЧИМ БАЙНА WWW.BLOOMBERGTV.MN НИЙТЭЛСЭН:2024/12/19     PROGRESSIVE EQUITY RESEARCH: 2025 ОН “PETRO MATAD” КОМПАНИД ЭЭЛТЭЙ БАЙХААР БАЙНА WWW.BLOOMBERGTV.MN НИЙТЭЛСЭН:2024/12/19     2026 ОНЫГ ДУУСТАЛ ГАДААД АЖИЛТНЫ ТОО, ХУВЬ ХЭМЖЭЭГ ХЯЗГААРЛАХГҮЙ БАЙХ ХУУЛИЙН ТӨСӨЛ ӨРГӨН МЭДҮҮЛЭВ WWW.EAGLE.MN НИЙТЭЛСЭН:2024/12/19    

Speaker of Lok Sabha Visits “Mongol Refinery” LLC www.montsame.mn

The Speaker of the Lok Sabha, Lower House of the Parliament of India Om Birla, who is on an Official Visit to Mongolia visited the state-owned company “Mongol Refinery” LLC on July 7.
Dr. D. Altantsetseg, the Executive Director of the “Mongol Refinery” LLC, Mongolia's Consulting Engineer expressed gratitude to the government and parliament of India for all-round support to the establishment of the first oil refinery, which has specifically important to the economic development and energy independence of Mongolia and informed on the progress of the project.
The Government of Mongolia is implementing the Project to establish a grass root Oil Refinery Plant based on domestic crude in Dornogobi aimag, located in Southeastern part of the country, within the framework of the soft loan extended by the Government of India to ensure energy independency and expand the industry diversification.
Upon approving the Detailed Feasibility Study and selecting "Engineers India Limited" as Project Management Consultant in 2019, the design and engineering works have completed, and from this year on, the mechanical erection of the main technological facilities has started at full capacity.
Out of four main EPC packages planned for the project, the first package, which comprises of non-technological facilities, such as civil buildings (office-training center, first aid center, fire station, warehouse, laboratory, workshop, canteen, 30 thousand cubic meter underground water storage tank) is at the final stage, noted Executive Director Dr. D. Altantsetseg.
EPC 02 package consists of initial processing units, such as Atmospheric and Vacuum Distillation Units, Saturated Gas Plant, and utilities, including tank farms, product dispatching facilities, and the different types of auxiliary and supporting units, whereas a 35 MW Thermal Power Plant would be built as part of the EPC 03 package. The site works of these packages have commenced, informed the project implementers.


Published Date:2023-07-09