1 DRAFT LAW ON AMENDMENTS TO THE GENERAL LAW ON TAXATION TO BE SUBMITTED TO PARLIAMENT WWW.MONTSAME.MN PUBLISHED:2025/06/05      2 THE FALL OF MONGOLIA’S COALITION GOVERNMENT WWW.THEDIPLOMAT.COM  PUBLISHED:2025/06/05      3 REVISED DRAFT LAW ON VALUE ADDED TAX TO BE SUBMITTED TO PARLIAMENT WWW.MONTSAME.MN PUBLISHED:2025/06/05      4 MONGOLIA SOLAR TENDER: 19.8 MW SOLAR PLANT FOR A STUNNING FUTURE WWW.PVKNOWHOW.COM  PUBLISHED:2025/06/05      5 GOLD PURCHASE BY MONGOLIA'S CENTRAL BANK DOWN 29.3 PCT IN 1ST 5 MONTHS OF 2025 WWW.XINHUANET.COM PUBLISHED:2025/06/05      6 FOOD AND AGRICULTURE ORGANIZATION OF THE UNITED NATIONS APPOINTS NEW REPRESENTATIVE IN MONGOLIA WWW.GOGO.MN PUBLISHED:2025/06/05      7 MONGOLIA:REGULATORY SANDBOX FRAMEWORK HAS BEEN AMENDED AND APPROVED WWW.ASIAINSURANCEREVIEW.COM  PUBLISHED:2025/06/05      8 RESOURCE-RICH MONGOLIA FACES POLITICAL UNCERTAINTY AFTER THE PRIME MINISTER RESIGNS WWW.APNEWS.COM PUBLISHED:2025/06/04      9 WHY MONGOLIA’S PRIME MINISTER RESIGNED WWW.TIME.COM PUBLISHED:2025/06/04      10 MONGOLIA PM RESIGNS AFTER SON'S LUXURY HOLIDAY STIRS PUBLIC FURY WWW.BBC.COM PUBLISHED:2025/06/04      ЕРӨНХИЙ САЙДАД НЭР ДЭВШИГЧДИЙГ МАРГААШ ТОДРУУЛНА WWW.ZINDAA.MN  НИЙТЭЛСЭН:2025/06/05     МОНГОЛЫН ИРГЭД ОХУ РУУ ЗОРЧИХДОО ШИНЭ ЖУРАМ МӨРДӨНӨ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/06/05     АЛБАДАН ГАРГАСАН ГАДААДЫН ИРГЭДИЙН ТОО ӨМНӨХ ОНЫ МӨН ҮЕЭС 71 ХУВИАР ӨСЖЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2025/06/05     МОНГОЛБАНК ЗАСГИЙН ГАЗРЫН “ХАМЖИГЧ”-ААР АЖИЛЛАСНЫ АЛДАГДАЛ 3.6 ИХ НАЯД ТӨГРӨГТ ХҮРЧЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2025/06/05     НИЙГМИЙН ДААТГАЛЫН БАГЦ ХУУЛЬ: АЖИЛ ОЛГОГЧДЫН ТӨЛДӨГ НДШ-ЭЭС 2 ХҮРТЭЛХ ХУВИЙГ ХӨНГӨЛНӨ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/05     ДОТООДЫН МАХ, МАХАН БҮТЭЭГДЭХҮҮНИЙ ҮНЭ ЖИЛИЙН 18.2 ХУВИАР ӨССӨН НЬ ИНФЛЯЦИД НӨЛӨӨЛЖЭЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/05     2026 ОНЫ АЗИ ТИВИЙН ШАТРЫН АВАРГА ШАЛГАРУУЛАХ ТЭМЦЭЭНИЙГ МОНГОЛ УЛСАД ЗОХИОН БАЙГУУЛНА WWW.EAGLE.MN НИЙТЭЛСЭН:2025/06/05     ШИНЭ ЕРӨНХИЙ САЙД ТОМИЛОХ МАН-ЫН БАГА ХУРАЛ МАРГААШ БОЛНО WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/04     Н.УЧРАЛ: ТӨК-ИЙН ЗАХИРГААНЫ ОРОН ТОО, ТУЗ-ИЙН ТООГ БУУРУУЛНА WWW.NEWS.MN НИЙТЭЛСЭН:2025/06/04     ТАТВАРАА ТӨЛӨӨГҮЙ 103 МЯНГАН ЭЗЭМШИГЧ БАЙНА, БАРАГДУУЛААГҮЙ ТОХИОЛДОЛД ЗАМЫН ХӨДӨЛГӨӨНД ОРОЛЦУУЛАХГҮЙ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/04    

Speaker of Lok Sabha Visits “Mongol Refinery” LLC www.montsame.mn

The Speaker of the Lok Sabha, Lower House of the Parliament of India Om Birla, who is on an Official Visit to Mongolia visited the state-owned company “Mongol Refinery” LLC on July 7.
Dr. D. Altantsetseg, the Executive Director of the “Mongol Refinery” LLC, Mongolia's Consulting Engineer expressed gratitude to the government and parliament of India for all-round support to the establishment of the first oil refinery, which has specifically important to the economic development and energy independence of Mongolia and informed on the progress of the project.
The Government of Mongolia is implementing the Project to establish a grass root Oil Refinery Plant based on domestic crude in Dornogobi aimag, located in Southeastern part of the country, within the framework of the soft loan extended by the Government of India to ensure energy independency and expand the industry diversification.
Upon approving the Detailed Feasibility Study and selecting "Engineers India Limited" as Project Management Consultant in 2019, the design and engineering works have completed, and from this year on, the mechanical erection of the main technological facilities has started at full capacity.
Out of four main EPC packages planned for the project, the first package, which comprises of non-technological facilities, such as civil buildings (office-training center, first aid center, fire station, warehouse, laboratory, workshop, canteen, 30 thousand cubic meter underground water storage tank) is at the final stage, noted Executive Director Dr. D. Altantsetseg.
EPC 02 package consists of initial processing units, such as Atmospheric and Vacuum Distillation Units, Saturated Gas Plant, and utilities, including tank farms, product dispatching facilities, and the different types of auxiliary and supporting units, whereas a 35 MW Thermal Power Plant would be built as part of the EPC 03 package. The site works of these packages have commenced, informed the project implementers.