1 GAZPROM, MONGOLIA SIGN ENERGY MOU, PAVING PATH FOR POWER OF SIBERIA-2 WWW.OILPRICE.COM PUBLISHED:2025/08/27      2 MONGOLIA, US DISCUSS COOPERATION IN INVESTMENT, MINING, TOURISM, SPACE EXPLORATION WWW.MONTSAME.MN PUBLISHED:2025/08/27      3 MONGOLIA TO INCREASE COAL SUPPLY TO CHINA WWW.MONTSAME.MN PUBLISHED:2025/08/27      4 PM REAFFIRMS TRANSPARENCY IN BUDGET APPROVAL WWW.MONTSAME.MN PUBLISHED:2025/08/27      5 BUDGET 2026: SOCIAL INSURANCE AND WELFARE PENSIONS TO RISE BY 6% NEXT YEAR WWW.GOGO.MN PUBLISHED:2025/08/27      6 GAZPROM SIGNS MEMORANDUM OF COOPERATION WITH MONGOLIAN GOVT ON OIL AND GAS WWW.INTERFAX.COM PUBLISHED:2025/08/27      7 WATER-RELATED ACCIDENTS KILL 70 IN MONGOLIA THIS YEAR WWW.XINHUANET.COM PUBLISHED:2025/08/27      8 FITCH AFFIRMS MONGOLIAN MINING AT 'B+'; OUTLOOK STABLE WWW.FITCHRATINGS.COM  PUBLISHED:2025/08/26      9 20-DAY ODD-EVEN LICENSE PLATE RESTRICTION TO BEGIN ON AUGUST 27 WWW.GOGO.MN PUBLISHED:2025/08/26      10 WHY CHINESE INNER MONGOLIA BAOTOU STEEL UNION'S 40% PROFIT SURGE SIGNALS A STRONG BUY OPPORTUNITY WWW.AINVEST.COM  PUBLISHED:2025/08/26      ТӨГРӨГ НУУРЫН БҮЛЭГ ОРДЫГ ТӨРД БУЦААН АВАХААР ШИЙДВЭРЛЭЛЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2025/08/27     “ГАЗПРОМ”-ТОЙ ГАЗРЫН ТОСНЫ САЛБАРТ ХАМТРАН АЖИЛЛАНА WWW.EAGLE.MN НИЙТЭЛСЭН:2025/08/27     SXCOAL-ТАЙ ХАМТАРСНААР ХЭРЭГЛЭГЧДЭД ХАМГИЙН БОЛОМЖИТ ХУВИЛБАРЫГ САНАЛ БОЛГОХ БОЛОМЖТОЙ WWW.ITOIM.MN НИЙТЭЛСЭН:2025/08/27     "РИО ТИНТО"-ТОЙ ХИЙХ АРБИТРЫН МАРГААНД ЗГ-ЫГ Н.МЯГМАРААР АХЛУУЛСАН АЖЛЫН ХЭСЭГ ТӨЛӨӨЛНӨ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/08/27     ЭМЭЭЛТ ЭКО АЖ ҮЙЛДВЭРИЙН ПАРКИЙН ДЦС-ЫН ГЭРЭЭНД ГАРЫН ҮСЭГ ЗУРЖЭЭ WWW.NEWS.MN НИЙТЭЛСЭН:2025/08/27     "ЦЕМЕНТ ШОХОЙ" ХК-ИЙГ ТҮШИГЛЭН АЖ ҮЙЛДВЭРИЙН ПАРК БАЙГУУЛАХ САНАМЖ БИЧИГТ ГАРЫН ҮСЭГ ЗУРЛАА WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/08/27     ЭНХТАЙВАНЫ ГҮҮРИЙГ ШИНЭЧИЛЖ ЗАССАНААР 15-20 ЖИЛЭЭР НАСЖИЛТ НЭМЭГДЭНЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2025/08/27     ХЯТАДЫН ИМПОРТЫН НҮҮРСНИЙ 48 ХУВИЙГ МОНГОЛ УЛС, 29 ХУВИЙГ ОХУ-ААС НИЙЛҮҮЛЖЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2025/08/26     “ЦАЙРТ МИНЕРАЛ” КОМПАНИЙГ "ЭРДЭНЭТ"-ИЙГ ТҮШИГЛЭН БАЙГУУЛАХ ЗЭС ХАЙЛУУЛАХ ҮЙЛДВЭРИЙН СОНГОН ШАЛГАРУУЛАЛТАД ОРОЛЦУУЛАХААР УРЬЖЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2025/08/26     С.БЯМБАЦОГТ: ЗАСГИЙН ГАЗАР ОЮУ ТОЛГОЙН АСУУДЛЫН ЗАНГИЛААГ ТАЙЛНА WWW.ITOIM.MN НИЙТЭЛСЭН:2025/08/26    

Rio Tinto faces major engineering change at Oyu Tolgoi www.mining.com

Rio Tinto (LON: RIO) (ASX:RIO) has approved a shift in underground development at its Oyu Tolgoi copper-gold mine in Mongolia, pausing progress in the Entrée Resources (TSX: ETG) joint venture area due to ongoing delays in license transfers.
The company said the ramp up of production from Oyu Tolgoi remains on track to deliver an average of around 500,000 tonnes of copper from 2028 to 2036, with options including bringing Panel 1 or Panel 2 South into production first depending on the timing of the Entrée licence transfers.
“With lateral development work only just beginning in Panel 1, this is the right time to pivot and bring forward development in Panel 2 South to maintain our options,” Katie Jackson, chief executive of Rio Tinto Copper, said in a statement.
While limited development will continue in parts of Panel 1 outside the JV boundary, Rio Tinto confirmed that resources will now be reallocated to expedite progress in the more accessible Panel 2 South.
The development freeze in the Entrée JV area stems from a delay in transferring licences to Oyu Tolgoi LLC (OTLLC), the operating entity jointly owned by Rio Tinto (66%) and the Mongolian government (34%).
Entrée expressed disappointment over the holdup. CEO Stephen Scott noted that the transfer process began in February 2025 but remains incomplete.
“The parties have always intended for OTLLC to hold title to the Shivee Tolgoi and Javkhlant mining licenses on behalf of the JV participants,” Scott said. “It is a requirement of the 2008 JV agreement and contemplated in the 2009 Oyu Tolgoi investment agreement.”
He cautioned that any significant delay in development at Lift 1 Panel 1 could adversely impact the project’s cost, schedule, and Entrée’s financial position and share price.
As one of the world’s largest known copper-gold resources, Oyu Tolgoi plays a pivotal role in Rio Tinto’s growth strategy and Mongolia’s economic development.
Open pit mining at Oyu Tolgoi first started in 2011, and the copper concentrator, the largest industrial complex ever built in Mongolia, began processing mined ore into copper concentrate in 2013. Last year, underground production also kicked off, which is expected to elevate Oyu Tolgoi into one of the world’s top copper producers by 2030.



Published Date:2025-06-10