1 GOVERNMENT LAUNCHES FIRST RENEWABLE ENERGY BIDDING PROCESS FOR SOLAR, BATTERY PROJECTS WWW.MONTSAME.MN PUBLISHED:2026/05/13      2 DIRECT FLIGHTS BETWEEN ASTANA AND ULAANBAATAR TO LAUNCH IN JUNE WWW.MONTSAME.MN PUBLISHED:2026/05/13      3 TMK ENERGY REPORTS INCREASED GAS OUTPUT AT MONGOLIAN OPERATIONS DESPITE SETBACKS WWW.PETROLEUMAUSTRALIA.COM.AU PUBLISHED:2026/05/13      4 WHEN 1,500M OF FENCING WAS REMOVED FROM THE TRANS-MONGOLIAN RAILWAY, A LONG-LOST ANIMAL RECLAIMED ITS NATIVE LANDS WWW.DISCOVERWILDLIFE.COM PUBLISHED:2026/05/13      5 ADB CALLS FOR DEEPER REGIONAL COOPERATION AS ASIA FACES NEW CROSSROADS WWW.UBPOST.MN PUBLISHED:2026/05/13      6 THE PERSON WHO PUT MONGOLIA’S IMAGE ON THE WORLD STAGE: INTERVIEW WITH FOREIGN AFFAIRS MINISTER BATTSETSEG BATMUNKH WWW.MONTSAME.MN PUBLISHED:2026/05/13      7 KOREAN AIR EXPANDS MONGOLIA REFORESTATION PROGRAMME WWW.TRAVELDAILYNEWS.ASIA PUBLISHED:2026/05/13      8 GTJAI ASSISTS STATE BANK OF MONGOLIA IN COMPLETING A US$100 MILLION REG S BOND TAP ISSUANCE WWW.ACNNEWSWIRE.COM PUBLISHED:2026/05/12      9 BATSUMBEREL N. ELECTED MPP DEPUTY CHAIRMAN WWW.MONTSAME.MN PUBLISHED:2026/05/12      10 JICA TWO-STEP LOAN PROJECT DELIVERS LONG-TERM FINANCING TO MONGOLIAN SMES WWW.MONTSAME.MN PUBLISHED:2026/05/12      УЛСЫН ХЭМЖЭЭНД 44.6 МЯНГАН ГА ТАЛБАЙД ХАВРЫН ТАРИАЛАЛТ ХИЙЖЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/05/13     "ЭРДЭНЭС ТАВАНТОЛГОЙ" ХК-ИЙН БОРЛУУЛАЛТ 76, ЭКСПОРТ 58.7 ХУВИАР ӨСЛӨӨ WWW.NEWS.MN НИЙТЭЛСЭН:2026/05/13     ГИХГ-ЫН ДАРГААР Б.ЭНХСҮХИЙГ ТОМИЛОВ WWW.NEWS.MN НИЙТЭЛСЭН:2026/05/13     "МОНГОЛ УЛСАД АГААРЫН ХӨЛГИЙН ТҮЛШ НИЙЛҮҮЛЭХ ТУХАЙ" ХОЁР УЛСЫН ЗАСГИЙН ГАЗАР ХООРОНДЫН ХЭЛЭЛЦЭЭРТ ӨӨРЧЛӨЛТ ОРУУЛНА WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/05/13     "ЭРДЭНЭС ТАВАНТОЛГОЙ" ХК-ИЙН ЗАХИРЛААР ТОМИЛОГДСОН Б.ЧАГНААДОРЖ АЖЛАА АВЛАА WWW.NEWS.MN НИЙТЭЛСЭН:2026/05/13     ГАЗРЫН ТОС БОЛОВСРУУЛАХ ҮЙЛДВЭРИЙН БҮТЭЭН БАЙГУУЛАЛТЫГ ШУУРХАЙЛАХААР БОЛОВ WWW.NEWS.MN НИЙТЭЛСЭН:2026/05/13     ШИНЭ ОРОН СУУЦНЫ ҮНЭ ӨМНӨХ ОНООС 7.4 ХУВИАР ӨСЖЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/05/13     КАПИТАЛ БАНК БОЛОН ЧИНГИС ХААН БАНКНЫ ӨР ТӨЛБӨРТ ХҮЛЭЭН АВСАН ШУУД ХУДАЛДАН БОРЛУУЛАХ ХӨРӨНГИЙГ НЭЭЛТТЭЙ МЭДЭЭЛЛЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/05/13     НААДМААС ӨМНӨ ТӨСӨВТ ТОДОТГОЛ ХИЙНЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/05/13     СЭРГЭЭГДЭХ ЭРЧИМ ХҮЧНИЙ САЛБАРТ АНХ УДАА ӨРСӨЛДӨӨНТ СОНГОН ШАЛГАРУУЛАЛТ ЗАРЛАЛАА WWW.EAGLE.MN НИЙТЭЛСЭН:2026/05/12    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

Turnaround Track Installed as Construction Progresses on Ulaanbaatar’s First Urban Cable Car System www.montsame.mn

Ulaanbaatar is making visible progress on its first urban cable car system, a landmark infrastructure project designed to ease traffic, cut air pollution, and improve public transport connectivity. The Cable Car Transport Project – Line I, a 4.2 km route connecting the Yarmag area (Artsat Yarmag Station) to Unur khoroolol (Kharkhorin Station) via a crossing over the Tuul River, is currently under active construction.
A turnaround track, a key structural component enabling the movement of cables and cabins, has been installed at the Yarmag Station. Out of the planned 19 pylons (support towers), six have already been erected at the Yarmag and Kharkhorin sites.
Nearby, construction is ongoing on a garage facility that will house cable car cabins, with concrete foundation and structural works currently underway.
The project is being led by engineers from France's POMA Group, with Monnis Engineering serving as the local subcontractor.
According to the current timeline, concrete works will be completed by October 30, and all 19 support towers are scheduled for installation by November 2025. Interior work for technical systems, including plumbing, heating, ventilation, communication, and control systems, will begin in January 2026.
Notably, the cabins will feature heating systems for winter comfort, ventilation for summer operation, dual power supplies for reliability, and safety equipment to ensure secure and efficient service year-round.
The project is being managed by the Unified Project Management Authority, a state-owned enterprise acting as the client representative. The authority is working closely with contractors to ensure timely and efficient implementation.
Cable Car Transport Project – Line I:
Line Length: 4.2 km
Stations: 2 (6.45–42 meters in elevation)
Support Towers / Pylons: 19
Peak Capacity: 2,320 passengers per hour



Published Date:2025-10-08