Gashuunsukhait-Gantsmod cross-border railway reaches 54% completion www.gogo.mn
Installation of the railway superstructure for the Gashuunsukhait-Gantsmod cross-border railway project has officially begun, with overall construction progress reaching 54.15% as of September 14, 2026.
The project includes the installation of 32.6 km of railway superstructure. To date, 2.5 km of narrow-gauge superstructure has been installed, along with five turnouts and 2,304 reinforced concrete sleepers at three locations.
Under the project's second package, which covers the long bridge, 2,382 pile foundations, 291 intermediate piers, and 666 girders have been manufactured. Installation of 426 girders has been completed to date.
Published Date:2026-09-15