1 MONGOLIA’S FIRST LARGE-SCALE WASTEWATER RECYCLING PLANT OPENS WWW.MONTSAME.MN PUBLISHED:2026/03/17      2 ULAANBAATAR READY TO ACCEPT PRIVATE INITIATIVES TO REDUCE AIR POLLUTION AND TRAFFIC CONGESTION WWW.GOGO.MN PUBLISHED:2026/03/17      3 ‘WE ARE BEING SILENCED’: MONGOLIAN POLITICIANS FACE JAIL AFTER VOTE CALLING FOR PM TO RESIGN WWW.THEGUARDIAN.COM PUBLISHED:2026/03/17      4 KOREA COMPLETES PRE-FEASIBILITY STUDY FOR MONGOLIA RAIL PROJECT WWW.EN.SEDAILY.COM PUBLISHED:2026/03/17      5 ULAANBAATAR TO EXPAND COOPERATION WITH FRANCE IN URBAN DEVELOPMENT WWW.MONTSAME.MN PUBLISHED:2026/03/17      6 SPRING SESSION TO TACKLE ECONOMIC CHALLENGES, TAX REFORM, GOVERNANCE ISSUES WWW.MONTSAME.MN PUBLISHED:2026/03/17      7 MONGOLIAN MINING CORPORATION ANNOUNCES 2025 ANNUAL RESULTS WWW.STOCKTITAN.NET PUBLISHED:2026/03/17      8 SOLAR POWER PLANT TO BE BUILT IN THE WESTERN REGION WWW.MONTSAME.MN PUBLISHED:2026/03/17      9 ECONOMIC GROWTH REMAINS STRONG AS FOREIGN INVESTMENT DECLINES WWW.MONTSAME.MN PUBLISHED:2026/03/17      10 HILTON ENTERS MONGOLIA WITH THE SIGNING OF CONRAD ULAANBAATAR, MARKING A NEW CHAPTER FOR LUXURY HOSPITALITY IN THE CAPITAL WWW.MARKETSCREENER.COM PUBLISHED:2026/03/17      "ЧИНГИС АЭРЛАЙНС ЮНИТИ" ХХК ATR 72-600 ЗАГВАРЫН АНХНЫ АГААРЫН ХӨЛГӨӨ МОРОККОГООС ХҮЛЭЭН АВЛАА WWW.GOGO.MN НИЙТЭЛСЭН:2026/03/18     С.ШААРИЙБУУГ ДЭМЖИХ АЖЛЫН ХЭСГИЙГ БАТАЛЛАА WWW.NEWS.MN НИЙТЭЛСЭН:2026/03/18     АЖ ҮЙЛДВЭРИЙН САЛБАРЫН ҮЙЛДВЭРЛЭЛ 54 ХУВИАР НЭМЭГДЖЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/03/18     “ОЮУТОЛГОЙН ШИНЭ ХЭЛЭЛЦЭЭ: МОНГОЛЫН ТАЛ ЭНЭ УДАА БУЦАХГҮЙ” WWW.EAGLE.MN НИЙТЭЛСЭН:2026/03/17     Х.ГАНХУЯГ: "ШИНЭ ХОРШОО"-ГООР 894 ТЭРБУМЫН ЗЭЭЛ ОЛГОСОН. ЦААШИД ЗЭЭЛИЙГ ТҮР ЗОГСООНО WWW.EGUUR.MN НИЙТЭЛСЭН:2026/03/17     САРЫН ДУНДАЖ ЦАЛИН ₮2.8 САЯ, ГОЛЧ ЦАЛИН 2.4 САЯ ТӨГРӨГ БАЙНА WWW.EGUUR.MN НИЙТЭЛСЭН:2026/03/17     МОНГОЛ, АНУ-ЫН ХАРИЛЦАА, ХАМТЫН АЖИЛЛАГААГ БҮХИЙ Л САЛБАРТ ӨРГӨЖҮҮЛЭХЭД ОНЦГОЙ АНХААРЧ АЖИЛЛАХАА ИЛЭРХИЙЛЭВ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/03/17     АНУ-ЫН МЯНГАНЫ СОРИЛТЫН КОРПОРАЦ МОНГОЛД ДАХИН БУЦАЛТГҮЙ ТУСЛАМЖ ҮЗҮҮЛЭХ ҮҮ? WWW.EAGLE.MN НИЙТЭЛСЭН:2026/03/17     БАРУУН БҮСЭД СЭРГЭЭГДЭХ ЭРЧИМ ХҮЧНИЙ НАРНЫ ЦАХИЛГААН СТАНЦ БАРИНА WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/03/17     ТРАССТ ӨРТӨЖ БУЙ ГАЗАР АШИГЛАГЧДЫН ГАЗАР АШИГЛАХ ЭРХИЙГ ХЭСЭГЧЛЭН ЦУЦАЛНА WWW.GOGO.MN НИЙТЭЛСЭН:2026/03/16    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

Oyu Tolgoi releases Q4 Production Report and 2016 Scorecard www.mongolia.goog.mn

Oyu Tolgoi today announced an update on its production for the fourth quarter of 2016 and, released the latest edition of its Performance Scorecard.

Oyu Tolgoi performed better than target on safety in 2016, and continuing to be one of the leading safety performers across Rio Tinto and peers in the broader mining industry.
Armando Torres, Managing Director – Oyu Tolgoi, said, “The Oyu Tolgoi team delivered a strong performance over 2016 despite significant operational and market challenges. Our safety performance continues to be one of the best in Rio Tinto – and indeed, across our global mining peers, achieving an All Injury Frequency Rate of 0.22 for the year. Oyu Tolgoi also achieved record setting performance in the open pit operation, and underground development continues to progress well – establishing a strong foundation for the year ahead.”
Oyu Tolgoi’s open pit mining and concentrator operations in 2016 achieved record levels for material mined and ore treated, and exceeded both copper and gold production guidance for the year. Concentrator performance during the fourth quarter was strong with the highest throughput since production began.
During Q4’16, progress continued in key areas of underground development with the national workforce working on the underground project crossing 2,000 personnel; Shafts 2 and 5 related activities and construction of critical on-site facilities continued, and the bulk excavation component for the conveyor-to-surface work stream was completed. Lateral development rates are progressing well with a further increase expected in 2017, when additional underground crushing capacity is added.
Oyu Tolgoi is expected to produce 130,000 to 160,000 tonnes of copper in concentrates and 100,000 to 140,000 ounces of gold in concentrates for 2017.
Q4’16 Scorecard
Oyu Tolgoi’s total in-country spend since 2010 crossed US$6.1 billion at the end of Q4 – demonstrating a strong, continuing commitment to local content in both operations and underground development, including US$760 million total spend in country in 2016.
The company continued its world-class environment performance, achieving an annual average water recycling rate of 86.2 per cent, and using only 0.423 cubic metres of water per tonne of ore processed – one-third the usage of comparable operations worldwide.
At the end of 2016, 93.5 per cent of Oyu Tolgoi’s total workforce was Mongolian, including 96 per cent Mongolian employees at the open pit mining and concentrator operations; and with South Gobi residents comprising 22 per cent of the total workforce.
Oyu Tolgoi continued its strong contribution to the South Gobi community in 2016 achieving procurement spends of US$69 million, and investing US$9.7 million in sustainable development and community infrastructure projects in the region. Two major infrastructure projects saw significant progress in the last quarter, with the Bayan-Ovoo Primary Health Care Center, a two-story building with 10 beds, a surgery and birthing room, and employing 18 staff, including doctors and nurses completed, and the Khanbogd bulk water treatment plant nearing commissioning.



Published Date:2017-01-25