1 43,000 PASSENGER CARS IMPORTED IN THE FIRST HALF OF 2026 WWW.GOGO.MN PUBLISHED:2026/08/12      2 OIL REFINERY CONSTRUCTION TO BE INTENSIFIED AND LEGISLATIVE BOTTLENECKS REMOVED WWW.MONTSAME.MN PUBLISHED:2026/08/12      3 TEN YEARS OF 'HUNNU ROCK': THE HU LAUNCHES NEW WORLD TOUR WWW.MONTSAME.MN PUBLISHED:2026/08/12      4 NATIONAL AI COUNCIL ESTABLISHED TO DRIVE DIGITAL ECONOMY WWW.MONTSAME.MN PUBLISHED:2026/08/12      5 THE MAGIC OF MONGOLIA: WHY PEOPLE VISIT THE MOST SPARSELY POPULATED COUNTRY IN THE WORLD WWW.JACKSFLIGHTCLUB.COM PUBLISHED:2026/08/12      6 THE MOST EXPENSIVE MISTAKE MONGOLIAN COMPANIES KEEP MAKING AND CALLING IT A HIRING DECISION (BLOG) WWW.LAMBDA.GLOBAL PUBLISHED:2026/08/12      7 MONGOLIA SUCCESSFULLY TESTS INTERCITY FREIGHT TRANSPORT WITH HEAVY ELECTRIC TRUCKS FOR THE FIRST TIME WWW.OPEN.KG PUBLISHED:2026/08/12      8 MONGOLIA RATIONS GASOLINE AS FUEL SHORTAGES SEND DRIVERS INTO LONG LINES WWW.INTELLINEWS.COM PUBLISHED:2026/08/12      9 VIEWS EXCHANGED WITH ADB ON EDUCATION SECTOR REFORM AND COOPERATION WWW.MONTSAME.MN PUBLISHED:2026/08/12      10 “FOREIGNERS WHO LEARN ABOUT CHINGGIS KHAAN THROUGH HISTORY AND THE HU THROUGH MUSIC ARE BECOMING MORE INTERESTED IN THE MONGOLIAN LANGUAGE” WWW.GOGO.MN PUBLISHED:2026/08/12      Ц.САНДАГ-ОЧИР: МОНГОЛ УЛСЫН НИЙТ ГАЗАР НУТГИЙН 81.9 ХУВЬ ЦӨЛЖИЛТӨД ӨРТСӨН БАЙНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/08/12     МӨНГӨНИЙ БОДЛОГЫН ХҮҮГ 0.5 ХУВИАР ӨСГӨВ WWW.NEWS.MN НИЙТЭЛСЭН:2026/08/12     ШАТАХУУН ОЛГОДОГ ЗОХИЦУУЛАЛТЫГ БЯМБА ГАРАГААР ТАСАЛБАР БОЛГОНО WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/08/12     БАГАХАНГАЙ-ХӨШИГИЙН ХӨНДИЙ-ЭМЭЭЛТ ЧИГЛЭЛИЙН 214.9 КМ ТӨМӨР ЗАМ ИРЭХ САРД АШИГЛАЛТАД ОРНО WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/08/12     "НЕФТЬ БОЛОВСРУУЛАХ ҮЙЛДВЭРИЙГ ТҮШИГЛЭН ТЕХНОЛОГИЙН ПАРК БАЙГУУЛНА" WWW.NEWS.MN НИЙТЭЛСЭН:2026/08/12     “БАЯНХОШУУ ДЭД ТӨВ”-ИЙН ДАРААГИЙН 150 АЙЛЫН БАРИЛГЫН АЖИЛ 92 ХУВЬТАЙ БАЙНА WWW.GOGO.MN НИЙТЭЛСЭН:2026/08/12     НАЙМДУГААР САРЫН ШАТАХУУНЫ ХЭРЭГЛЭЭГ БҮРЭН ХАНГАХ НӨХЦӨЛ БҮРДЖЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/08/12     БАГАХАНГАЙ -ХӨШИГИЙН ХӨНДИЙ - ЭМЭЭЛТ ЧИГЛЭЛИЙН ТӨМӨР ЗАМЫН ТӨСЛИЙГ ХЭЛЭЛЦЭНЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/08/12     МОНГОЛ ДАХЬ ГАДААД АЖИЛЧДЫН ТОО 43 ХУВИАР ӨСЖЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/08/12     "ШАТАХУУНЫ НӨӨЦГҮЙ БОЛСОН УЛС, ОРНУУД ЗАЙНААС АЖИЛЛАХ БОДЛОГО ХЭРЭГЖҮҮЛЖ ЭХЭЛСЭН" WWW.GOGO.MN НИЙТЭЛСЭН:2026/08/12    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

Petro Matad spuds Red Deer-1 well in eastern Mongolia www.sharecast.com

Mongolian oil explorer Petro Matad announced on Monday that the Red Deer-1 exploration well in the Asgat Sag Basin of Block XX in eastern Mongolia was spudded on 4 August.

The AIM-traded firm said the well was being drilled with the Daton Petroleum Engineering and Oilfield Service rig, DXZ1.

It said the Red Deer-1 well was targeting a prospect with 48MMbo of mean prospective recoverable resource, and was planned to be drilled to a total depth of 2,100 metres.

The well was expected to take up to 35 days to complete.

In the event of a discovery, the company said would bring in a separate rig for testing.

A call-off testing contract had been signed, which ensured testing operations, if warranted, could commence soon after discovery.

Meanwhile, at Heron-1, Petro Matad said the first casing point at 551 metres was reached on schedule, and casing had been run and cemented.

The DQE rig 40105 was now ready to drill out cement, and then drill an eight-and-a-half inch hole to the prognosed total depth of 3,050 metres.

However, the provincial government had challenged Petro Matad's legal right to use the land at Heron-1 on the basis that a tripartite agreement between two central government agencies and the province had not been executed.

In all of Petro Matad's operations, the firm said it had followed the land permitting regulations as required under the production sharing contract, and in accordance with instructions from the Ministry of Mining and the industry regulator MRPAM.

The absence of a tripartite land use agreement between government agencies had never previously been an issue.

The board said it was working with the ministry, MRPAM and the provincial government to remedy that situation as soon as possible.

“The rig at Heron-1 has been put on standby whilst the situation is resolved,” the board said in its statement.

“All efforts are currently directed at fixing this interruption as quickly as possible in order to minimise rig standby costs.

“Daily standby costs are low by industry standards and are of the order of $12,000.”

Petro Matad said the Red Deer-1 well was located in a different province to that in which Heron-1 was located, and had not been affected.



Published Date:2019-08-06