1 DRAFT RESOLUTION ON STRATEGICALLY IMPORTANT PROJECTS SUBMITTED TO THE PARLIAMENT WWW.MONTSAME.MN PUBLISHED:2024/12/29      2 BATTLE FOR RESOURCES: FRANCE TARGETS MONGOLIA’S URANIUM WWW.NEWS.AZ PUBLISHED:2024/12/29      3 FINANCING AGREEMENT FOR “WHITE GOLD” NATIONAL PROGRAM SIGNED WWW.MONTSAME.MN PUBLISHED:2024/12/29      4 ‘INCREASED MONEY DISTRIBUTION DRIVES SURGE IN FOREIGN EXCHANGE OUTFLOW’ WWW.UBPOST.MN PUBLISHED:2024/12/29      5 EACH TOURIST WHO COMES TO MONGOLIA IN WINTER SPENDS 2-8 MILLION WWW.NEWS.MN PUBLISHED:2024/12/29      6 MONGOLIA TO ENHANCE SUPPORT FOR WOOL, CASHMERE, LEATHER PROCESSING INDUSTRIES WWW.XINHUANET.COM PUBLISHED:2024/12/29      7 MUSEUM VISITORS IN MONGOLIA SURGED BY 40 PERCENT, REACHING 1.1 MILLION WWW.MONTSAME.MN PUBLISHED:2024/12/29      8 COAL EXPORT OF MONGOLIA EXPECTED TO SURPASS 80 MILLION TONS WWW.MONTSAME.MN PUBLISHED:2024/12/26      9 MNT 4 TRILLION GENERATED IN THE FUTURE HERITAGE FUND OF MONGOLIA'S SOVEREIGN WEALTH FUND WWW.MONTSAME.MN PUBLISHED:2024/12/26      10 JOINT PROJECT TO IMPROVE ROAD MAINTENANCE IN MONGOLIA ONGOING WWW.MONTSAME.MN PUBLISHED:2024/12/26      ЭРҮҮЛ МЭНДИЙН ДААТГАЛЫН САНГИЙН ОРЛОГО 25.5 ХУВИАР НЭМЭГДЖЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2024/12/29     БӨӨРӨЛЖҮҮТ ЦАХИЛГААН СТАНЦ ЭРЧИМ ХҮЧНИЙ НЭГДСЭН СИСТЕМД АМЖИЛТТАЙ ХОЛБОГДЛОО WWW.EAGLE.MN НИЙТЭЛСЭН:2024/12/29     ТЭЭВРИЙН ХЭРЭГСЛИЙН УЛСЫН ДУГААРЫГ ЦАХИМААР АВАХ СИСТЕМ ЭНЭ САРЫН 30-НД НЭЭГДЭНЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2024/12/29     ЕРӨНХИЙЛӨГЧ У.ХҮРЭЛСҮХ ТӨРИЙН ДЭЭД ЦОЛ, ОДОН, МЕДАЛЬ ГАРДУУЛЛАА WWW.NEWS.MN НИЙТЭЛСЭН:2024/12/29     Б.МАНДАХБИЛЭГ: ГЕРМАН ДАХЬ МОНГОЛ СУДЛАЛЫН ТӨВҮҮДЭЭ БИД ИХ ТӨСӨВ ГАРГАЖ ДЭМЖИХ ЁСТОЙ WWW.MONTSAME.MN НИЙТЭЛСЭН:2024/12/29     БНСУ ХОЁР ДОЛОО ХОНОГИЙН ХУГАЦААНД ХОЁР УДИРДАГЧАА ОГЦРУУЛЛАА WWW.BLOOMBERGTV.MN НИЙТЭЛСЭН:2024/12/29     “ЦАГААН АЛТ” ҮНДЭСНИЙ ХӨТӨЛБӨРИЙН ЗЭЭЛИЙН САНХҮҮЖИЛТИЙН ГЭРЭЭНД ГАРЫН ҮСЭГ ЗУРЛАА WWW.EAGLE.MN НИЙТЭЛСЭН:2024/12/26     "ЧИНГИС ХААН" БАНКИНД БАЙРШУУЛСАН 100 ТЭРБУМЫГ АВАХ БОЛОМЖТОЙ" WWW.NEWS.MN НИЙТЭЛСЭН:2024/12/26     УЛСЫН НЭГДСЭН ТӨСВИЙН ОРЛОГО, ТУСЛАМЖИЙН ХЭМЖЭЭ 6.2 ИХ НАЯД ТӨГРӨГӨӨР НЭМЭГДЭВ WWW.MONTSAME.MN НИЙТЭЛСЭН:2024/12/26     МЕТРО БАРИХААР ГАЗРЫН ГАДАРГААС ДООШ 30 МЕТРИЙН ГҮНД 42 ЦЭГИЙГ ӨРӨМДЖЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2024/12/26    

Baganuur 50 MW Battery Storage Power Station Supplies Energy to Central System www.montsame.mn

Baganuur 50 MW Battery Storage Power Station has been completed and commissioned in Baganuur District, Ulaanbaatar city, supplying energy to the Central System.
This will allow the provision of electricity to approximately 25,000 households. The construction contract for the Plant was signed in September 2024, and on-site work began on September 15, 2024.
N. Batsaikhan, Deputy Director of "Monhorus International" LLC and Project Director of the Baganuur Battery Storage Power Station, said, "From the first of this month, we conducted testing and adjustments of the battery. On December 6, 2024, we began supplying energy to the central system for the first time. Initially, Blocks 1 and 2 supplied 25-30 MW of power, and then Blocks 3 and 4 were commissioned, bringing the total output to 40-50 MW supplied to the central system. To date, the Plant has delivered energy to the central system at full capacity twice, and over 12 days, it has supplied 1,800 MWh of electricity. When the Station operates at full capacity, it can provide electricity to around 25,000 households.”
J. Chen, an authorized representative of "Envision Energy" LLC, remarked, "Our company supplied 27 battery packages for the Baganuur Battery Storage Power Station. Each package consists of two parts. The Plant has the unique capability to charge during low-consumption nighttime hours and supply electricity during high-demand evening hours. This makes the Plant a clean green technology that does not emit carbon dioxide, serving as a renewable energy source. We aim at supplying higher-capacity battery storage plants and wind power plants in the future."
S. Khurelsukh, Executive Director of "Ulaanbaatar Energy" LLC, noted, "The testing and adjustments of the Plant have been completed, and the Plant is now operating at full capacity. During this period, no faults or interruptions have occurred in the equipment. Mongolian engineers actively participated in the Project and are now fully prepared to manage the Plant independently." as reported by the Public Relations and Communication Department of the Governor's Office of the Capital City.


Published Date:2024-12-19