1 MONGOLIA PUSHES TO COMPLETE RAIL BYPASS AROUND ULAANBAATAR WWW.INTELLINEWS.COM PUBLISHED:2026/08/19      2 BUDGET DEFICIT HITS 3-YEAR HIGH WWW.UBPOST.MN PUBLISHED:2026/08/19      3 CITY NEEDS A CONSTRUCTION HEIGHT LIMIT LAW WWW.UBPOST.MN PUBLISHED:2026/08/19      4 MONGOLIA TO RAISE MINIMUM WAGE TO MNT 1 MILLION FROM 2027 WWW.GOGO.MN PUBLISHED:2026/08/18      5 OVER 700 JOURNALISTS ACCREDITED TO COVER COP17 WWW.MONTSAME.MN PUBLISHED:2026/08/18      6 MONGOLIA: WORLD GATHERS TO SEEK ACCORD ON TACKLING DESERTIFICATION WWW.ASIANEWS.IT PUBLISHED:2026/08/18      7 MONGOLIA’S FUEL SUPPLY RETURNS TO NORMAL, RESTRICTIONS ON LICENCE PLATES AND PURCHASE LIMITS LIFTED WWW.ASIANEWS.NETWORK PUBLISHED:2026/08/18      8 SAUDI ARABIA HANDS LAND DEGRADATION BATON TO MONGOLIA WWW.ARABNEWS.COM PUBLISHED:2026/08/18      9 CHINA SHARES DESERTIFICATION-CONTROL EXPERTISE AT UNCCD COP17 IN MONGOLIA WWW.GLOBALTIMES.CN PUBLISHED:2026/08/18      10 UNCCD COP17 OPENS IN MONGOLIA'S CAPITAL WWW.XINHUANET.COM PUBLISHED:2026/08/17      ТӨРӨЛТ 3.8 ХУВИАР БУУРЧ, НАС БАРАЛТ 1.4 ХУВИАР ӨСЖЭЭ WWW.GOGO.MN НИЙТЭЛСЭН:2026/08/19     Б.ПҮРЭВДАГВА: ДУГААРЫН ХЯЗГААРЛАЛТААР ЗАМЫН ХӨДӨЛГӨӨНД ОРОЛЦООГҮЙ ӨДРҮҮДИЙГ ТАТВАРААС ХАСАХ ТООЦООЛОЛ ХИЙЖ БАЙНА WWW.EAGLE.MN НИЙТЭЛСЭН:2026/08/19     МОНГОЛ ОРНЫ НУТАГ ДЭВСГЭРИЙН 81.9 ХУВЬ НЬ ЦӨЛЖИЛТӨД ӨРТӨӨД БАЙНА WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/08/18     ҮСХ: АЖИЛГҮЙ ИРГЭДИЙН ТОО ӨМНӨХ ОНЫ МӨН ҮЕЭС 13.4 МЯНГААР ӨССӨН WWW.EAGLE.MN НИЙТЭЛСЭН:2026/08/18     Б.ДАВААДАЛАЙ: УУЛ УУРХАЙН САЛБАР ШАТАХУУНЫ ХҮНДРЭЛГҮЙ, ЭКСПОРТ, ОРЛОГО ХАРЬЦАНГУЙ САЙН БАЙНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/08/18     ҮСХ: ГАДААД ХУДАЛДАА 5 ТЭРБУМ ДОЛЛАРЫН АШИГТАЙ ГАРЛАА WWW.NEWS.MN НИЙТЭЛСЭН:2026/08/18     Ү.ОЮУНЗУЛ: COP17 ХУРЛЫН БҮТЭЭН БАЙГУУЛАЛТ НИЙСЛЭЛИЙН ӨМЧ БОЛОН ҮЛДЭНЭ WWW.NEWS.MN НИЙТЭЛСЭН:2026/08/18     Б.ДАШПҮРЭВ: ӨНӨӨДРӨӨС НИЙСЛЭЛИЙН ШТС-УУДЫН 90 ХУВИЙГ 24 ЦАГААР АЖИЛЛУУЛНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/08/17     ХЯТАДЫН С919 ОЛОН УЛСЫН АНХНЫ НИСЛЭГЭЭ ЯАГААД МОНГОЛ УЛСААС ЭХЛҮҮЛСЭН БЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/08/17     COP17 ЭХЭЛЛЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/08/17    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

Equipment and Components Being Installed for Oil Refinery Project www.montsame.mn

At its regular session, the Cabinet approved amendments to the Engineering, Procurement, and Construction (EPC) contracts for the Oil Refinery Project being implemented in Altanshiree soum of Dornogobi aimag with a concessional loan from the Government of India. The amendments concern only technical and process-related matters and do not affect the contract price for the Crude Distillation Unit (CDU), Vacuum Distillation Unit (VDU), and storage tanks (MEIL, EPC 02), or the Captive Power Plant (EPC 03).

The Oil Refinery Project is being carried out in four EPC packages.

Work under the EPC 01 package was completed in 2024, and the related facilities have already been commissioned.
Orders for equipment under EPC 02, EPC 03, and EPC 04 packages have been placed, and machinery, equipment, and components manufactured in India and other countries have arrived at the refinery site. Construction and installation works are currently underway.
Construction and installation of the main technological, auxiliary, and support facilities included in EPC 02 are planned to be completed in 2026.
EPC 03, which covers the refinery’s thermal power plant, has reached 44.4% completion in engineering, procurement, and construction works.