Winter Preparation of Heat Supply System at 90 Percent www.montsame.mn
Ulaanbaatar Heating Network state-owned JSC transmits heating from four power plants of the capital city to consumers through 370 km thermal lines. In the 2023-2024 heating season, the company will deliver 3,501 kcal of thermal energy to 13,400 buildings and facilities.
In accordance with the master and regular repair plans approved this year, comprehensive repair and maintenance are being conducted on 15 trunk and branch lines' equipment. In respect of the plan implementation, the repair of the central trunk line has been completed, the repair of electrical equipment of pump stations is at 95 percent, and consumer line equipment work is at 73 percent. In other words, the preparation of the heat supply equipment has been accomplished at 90 percent.
The landscaping related to the renovation of the heating network, which is financed by the World Bank, will be completed by September 4, said the Executive Director of Ulaanbaatar Heating Network JSC G. Bayarsaikhan.
Published Date:2023-08-30