1 43,000 PASSENGER CARS IMPORTED IN THE FIRST HALF OF 2026 WWW.GOGO.MN PUBLISHED:2026/08/12      2 OIL REFINERY CONSTRUCTION TO BE INTENSIFIED AND LEGISLATIVE BOTTLENECKS REMOVED WWW.MONTSAME.MN PUBLISHED:2026/08/12      3 TEN YEARS OF 'HUNNU ROCK': THE HU LAUNCHES NEW WORLD TOUR WWW.MONTSAME.MN PUBLISHED:2026/08/12      4 NATIONAL AI COUNCIL ESTABLISHED TO DRIVE DIGITAL ECONOMY WWW.MONTSAME.MN PUBLISHED:2026/08/12      5 THE MAGIC OF MONGOLIA: WHY PEOPLE VISIT THE MOST SPARSELY POPULATED COUNTRY IN THE WORLD WWW.JACKSFLIGHTCLUB.COM PUBLISHED:2026/08/12      6 THE MOST EXPENSIVE MISTAKE MONGOLIAN COMPANIES KEEP MAKING AND CALLING IT A HIRING DECISION (BLOG) WWW.LAMBDA.GLOBAL PUBLISHED:2026/08/12      7 MONGOLIA SUCCESSFULLY TESTS INTERCITY FREIGHT TRANSPORT WITH HEAVY ELECTRIC TRUCKS FOR THE FIRST TIME WWW.OPEN.KG PUBLISHED:2026/08/12      8 MONGOLIA RATIONS GASOLINE AS FUEL SHORTAGES SEND DRIVERS INTO LONG LINES WWW.INTELLINEWS.COM PUBLISHED:2026/08/12      9 VIEWS EXCHANGED WITH ADB ON EDUCATION SECTOR REFORM AND COOPERATION WWW.MONTSAME.MN PUBLISHED:2026/08/12      10 “FOREIGNERS WHO LEARN ABOUT CHINGGIS KHAAN THROUGH HISTORY AND THE HU THROUGH MUSIC ARE BECOMING MORE INTERESTED IN THE MONGOLIAN LANGUAGE” WWW.GOGO.MN PUBLISHED:2026/08/12      Ц.САНДАГ-ОЧИР: МОНГОЛ УЛСЫН НИЙТ ГАЗАР НУТГИЙН 81.9 ХУВЬ ЦӨЛЖИЛТӨД ӨРТСӨН БАЙНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/08/12     МӨНГӨНИЙ БОДЛОГЫН ХҮҮГ 0.5 ХУВИАР ӨСГӨВ WWW.NEWS.MN НИЙТЭЛСЭН:2026/08/12     ШАТАХУУН ОЛГОДОГ ЗОХИЦУУЛАЛТЫГ БЯМБА ГАРАГААР ТАСАЛБАР БОЛГОНО WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/08/12     БАГАХАНГАЙ-ХӨШИГИЙН ХӨНДИЙ-ЭМЭЭЛТ ЧИГЛЭЛИЙН 214.9 КМ ТӨМӨР ЗАМ ИРЭХ САРД АШИГЛАЛТАД ОРНО WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/08/12     "НЕФТЬ БОЛОВСРУУЛАХ ҮЙЛДВЭРИЙГ ТҮШИГЛЭН ТЕХНОЛОГИЙН ПАРК БАЙГУУЛНА" WWW.NEWS.MN НИЙТЭЛСЭН:2026/08/12     “БАЯНХОШУУ ДЭД ТӨВ”-ИЙН ДАРААГИЙН 150 АЙЛЫН БАРИЛГЫН АЖИЛ 92 ХУВЬТАЙ БАЙНА WWW.GOGO.MN НИЙТЭЛСЭН:2026/08/12     НАЙМДУГААР САРЫН ШАТАХУУНЫ ХЭРЭГЛЭЭГ БҮРЭН ХАНГАХ НӨХЦӨЛ БҮРДЖЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/08/12     БАГАХАНГАЙ -ХӨШИГИЙН ХӨНДИЙ - ЭМЭЭЛТ ЧИГЛЭЛИЙН ТӨМӨР ЗАМЫН ТӨСЛИЙГ ХЭЛЭЛЦЭНЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/08/12     МОНГОЛ ДАХЬ ГАДААД АЖИЛЧДЫН ТОО 43 ХУВИАР ӨСЖЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/08/12     "ШАТАХУУНЫ НӨӨЦГҮЙ БОЛСОН УЛС, ОРНУУД ЗАЙНААС АЖИЛЛАХ БОДЛОГО ХЭРЭГЖҮҮЛЖ ЭХЭЛСЭН" WWW.GOGO.MN НИЙТЭЛСЭН:2026/08/12    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

More Than 2,500 Engineers and Specialists Engaged in Bagakhangai-Hunnu City Railway Project www.montsame.mn

Approximately 2,500 specialists from around 110 domestic enterprises are participating in the construction of the Bagakhangai–Hunnu city Railway Project.
The railway's extended length is 151.2 kilometers, with an axle load capacity of 25 tons and an average annual freight capacity of 3.5 million tons.
The Government adopted a resolution on August 14, 2025, regarding “Certain measures related to the construction of branch railways,” which included implementing the Bagakhangai-Hunnu city branch Railway Project, relocating freight terminals from the Capital city center, and reorganizing logistics. The railway, branching from Bagakhangai station of Ulaanbaatar Railway JVC and passing through Sergelen soum of Tuv aimag to Khushig Valley, is planned to be of class III, with a total length of 102.5 kilometers and a gauge of 1,520 millimeters, and to include three stations, four sidings, and a 2.5-kilometer bridge structure.
The Project is being implemented in two phases. In the first phase, the upper and lower structures of 87.4 kilometers of railway from Bagakhangai station to Khushig station will be constructed. In the second phase, 14.6 kilometers of railway from Khushig station to Shuvuun Fabrik will be built. Construction work is proceeding in accordance with the plan. Specifically, the excavation works have reached 98.7 percent, the embankment works 91.6 percent, the girder bridges 76 percent, the culvert works 75.4 percent, and the track-laying 44.8 percent.
Upon the completion of this branch railway, goods transported to provinces and imported products will be received directly at the “Khushig Valley” and “Orgokh Uul” terminals without entering Ulaanbaatar. As a result, the heavy truck traffic load within the capital city is expected to be reduced by up to 50 percent.
Since there is no unified freight logistics center in the capital that meets international standards, freight and goods are currently distributed to Ulaanbaatar and 21 aimags through more than 10 terminals and over 300 branch lines located in the city center. This situation not only negatively impacts road damage, traffic congestion, and air, soil, and environmental pollution, but also increases the risk of hazardous goods passing through the city center.



Published Date:2025-09-21