1 SECURITIES TRADING REACHES MNT 1 TRILLION WWW.MONTSAME.MN PUBLISHED:2026/09/27      2 MINISTRIES MEET ICC DELEGATION WWW.UBPOST.MN PUBLISHED:2026/09/27      3 VERIFICATION DEMANDED OVER CITIZENSHIP OF CONTESTANT REPRESENTING MONGOLIA AT MISS GRAND INTERNATIONAL WWW.GOGO.MN PUBLISHED:2026/09/27      4 ULAANBAATAR DESIGNATES EIGHT SITES FOR AUTUMN TREE PLANTING WWW.GOGO.MN PUBLISHED:2026/09/27      5 OUTSTANDING BANK LOANS RISE 14.3 PERCENT WWW.MONTSAME.MN PUBLISHED:2026/09/24      6 CENTRAL ASIA AND MONGOLIA GROWTH TO REMAIN ROBUST WWW.EBRD.COM PUBLISHED:2026/09/24      7 A NEW OIL STORAGE FACILITY WITH A CAPACITY OF 16,000 CUBIC METERS HAS BEEN PUT INTO OPERATION IN MONGOLIA WWW.OPEN.KG PUBLISHED:2026/09/24      8 RUSSIA, MONGOLIA FORM WORKING GROUP TO EXAMINE FEASIBILITY OF A WESTERN RAIL CORRIDOR WWW.RUSSIASPIVOTTOASIA.COM PUBLISHED:2026/09/24      9 MONGOLIA SUBMITS CANDIDACY FOR UN SECURITY COUNCIL NON-PERMANENT SEAT FOR 2048–2049 WWW.MONTSAME.MN PUBLISHED:2026/09/24      10 ‘GASOLINE DISRUPTION MAY LAST 2 TO 3 YEARS’ WWW.UBPOST.MN PUBLISHED:2026/09/24      ЕРӨНХИЙ САЙД Н.УЧРАЛ ЯПОН УЛСАД АЛБАН ЁСНЫ АЙЛЧЛАЛ ХИЙХЭЭР МОРДЛОО WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/09/27     MININGWEEK 2026: НИЙТ ГАЗАР НУТГИЙНХАА 21 ХУВЬД АШИГТ МАЛТМАЛЫН ЛИЦЕНЗ ОЛГОХ БОЛОМЖТОЙ WWW.GOGO.MN НИЙТЭЛСЭН:2026/09/27     ДҮНЖИНГАРАВЫН УУЛЗВАРТ БОЛСОН ДЭЛБЭРЭЛТИЙН ХЭРГИЙГ НЭМЭЛТ МӨРДӨН БАЙЦААЛТ ХИЙЛГЭХЭЭР ПРОКУРОРТ БУЦААВ WWW.IKON.MN НИЙТЭЛСЭН:2026/09/27     “МОНГОЛЫН НОГООН, ХҮРТЭЭМЖТЭЙ ХОТУУД” ТӨСЛИЙГ ХЭРЭГЖҮҮЛЖ ЭХЭЛЛЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/09/27     АГААРЫН ТЭЭВРИЙН ХАМТЫН АЖИЛЛАГААГ ӨРГӨЖҮҮЛНЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/09/27     26 МЯНГАН ХҮН УРГАЦ ХУРААЛТАД ОРОЛЦОЖ БАЙНА WWW.NEWS.MN НИЙТЭЛСЭН:2026/09/27     ШҮҮХЭЭС НАЙРУУЛАГЧ Б.БААТАРТ ХИЛИЙН ХОРИГ ТАВЬЖЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/26     "ХӨРӨНГӨ ОРУУЛАГЧДЫН ГОМДЛЫГ 30 ХОНОГТ ШИЙДВЭРЛЭХ ШИНЭ ЗОХИЦУУЛАЛТ ХЭРЭГЖИЖ ЭХЭЛСЭН" WWW.NEWS.MN НИЙТЭЛСЭН:2026/09/24     “МЯНГАД НАР” 19.8 МВТ-ЫН НАРНЫ ЦАХИЛГААН СТАНЦЫН ГҮЙЦЭТГЭЛ 40 ХУВЬТАЙ БАЙНА WWW.EAGLE.MN НИЙТЭЛСЭН:2026/09/24     ГОВИЙН БҮСЭД ЗАРЛАСАН СЭРГЭЭГДЭХ ЭРЧИМ ХҮЧНИЙ АУКЦИОНД ГУРВАН КОМПАНИЙН ХАМТАРСАН ТҮНШЛЭЛ ШАЛГАРЛАА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/24    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

More Than 2,500 Engineers and Specialists Engaged in Bagakhangai-Hunnu City Railway Project www.montsame.mn

Approximately 2,500 specialists from around 110 domestic enterprises are participating in the construction of the Bagakhangai–Hunnu city Railway Project.
The railway's extended length is 151.2 kilometers, with an axle load capacity of 25 tons and an average annual freight capacity of 3.5 million tons.
The Government adopted a resolution on August 14, 2025, regarding “Certain measures related to the construction of branch railways,” which included implementing the Bagakhangai-Hunnu city branch Railway Project, relocating freight terminals from the Capital city center, and reorganizing logistics. The railway, branching from Bagakhangai station of Ulaanbaatar Railway JVC and passing through Sergelen soum of Tuv aimag to Khushig Valley, is planned to be of class III, with a total length of 102.5 kilometers and a gauge of 1,520 millimeters, and to include three stations, four sidings, and a 2.5-kilometer bridge structure.
The Project is being implemented in two phases. In the first phase, the upper and lower structures of 87.4 kilometers of railway from Bagakhangai station to Khushig station will be constructed. In the second phase, 14.6 kilometers of railway from Khushig station to Shuvuun Fabrik will be built. Construction work is proceeding in accordance with the plan. Specifically, the excavation works have reached 98.7 percent, the embankment works 91.6 percent, the girder bridges 76 percent, the culvert works 75.4 percent, and the track-laying 44.8 percent.
Upon the completion of this branch railway, goods transported to provinces and imported products will be received directly at the “Khushig Valley” and “Orgokh Uul” terminals without entering Ulaanbaatar. As a result, the heavy truck traffic load within the capital city is expected to be reduced by up to 50 percent.
Since there is no unified freight logistics center in the capital that meets international standards, freight and goods are currently distributed to Ulaanbaatar and 21 aimags through more than 10 terminals and over 300 branch lines located in the city center. This situation not only negatively impacts road damage, traffic congestion, and air, soil, and environmental pollution, but also increases the risk of hazardous goods passing through the city center.