1 MAJOR STRATEGIC SECTOR PROJECTS TO BE IMPLEMENTED IN COOPERATION WITH WORLD BANK WWW.MONTSAME.MN PUBLISHED:2026/02/06      2 GOVERNMENT APPROVES NEW ADMINISTRATIVE BUILDING AT ULAANBAATAR INTERNATIONAL AIRPORT WWW.MONTSAME.MN PUBLISHED:2026/02/06      3 MONGOLIA’S CRISIS IS AN OPPORTUNITY TO TRANSFORM ITS SYSTEM WWW.JACOBIN.COM PUBLISHED:2026/02/06      4 MONGOLIA'S CENTRAL BANK BUYS 1.9 TONNES OF GOLD IN JANUARY WWW.XINHUANET.COM PUBLISHED:2026/02/06      5 TEAM MONGOLIA IS GEARING UP TO BE THE MOST FASHIONABLY WARM AT THE 2026 WINTER OLYMPICS. HERE'S WHY WWW.CREATORS.YAHOO.COM PUBLISHED:2026/02/06      6 ERDENE RAISES $28.7 MILLION TO ACCELERATE MONGOLIAN COPPER-GOLD EXPANSION WWW.TIPRANKS.COM  PUBLISHED:2026/02/06      7 HUNGARIAN OTP BANK EXPRESSES INTEREST IN OPERATING IN MONGOLIA WWW.MONTSAME.MN PUBLISHED:2026/02/06      8 OYU TOLGOI: MONGOLIA’S HIGH-STAKES CLASH WITH RIO TINTO WWW.THEDIPLOMAT.COM PUBLISHED:2026/02/05      9 MONGOLIA PREPARES INTERNATIONAL TENDER TO BUILD STEEL PLANT WWW.AZERTAG.AZ  PUBLISHED:2026/02/05      10 RUSSIAN DEPUTY PM EXPECTS AGREEMENTS ON FREE TRADE AREAS WITH UAE, MONGOLIA, INDONESIA TO TAKE EFFECT IN 2026 WWW.INTERFAX.COM PUBLISHED:2026/02/05      СОНГИНОХАЙРХАН ДҮҮРГИЙН БАРУУН САЛААНЫ ГОЛЫН АЙ САВД ХӨВ ЦӨӨРӨМ БАЙГУУЛНА WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/02/06     СТРАТЕГИЙН САЛБАРЫН ТОМООХОН ТӨСЛҮҮДИЙГ ДЭЛХИЙН БАНКТАЙ ХАМТРАН ХЭРЭГЖҮҮЛНЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/02/06     Ш.АЛТАНТУЯА АГСНЫ ГЭР БҮЛ 4.7 САЯ РИНГГИТИЙГ МАЛАЙЗАД БУЦААН ОЛГОЖЭЭ WWW.NEWS.MN НИЙТЭЛСЭН:2026/02/06     НИЙСЛЭЛИЙН ХЭМЖЭЭНД 4113 ТЕЛЕ КАМЕРЫГ НЭГДСЭН БОЛОН ДЭД ТӨВД ХОЛБОЛОО WWW.ITOIM.MN НИЙТЭЛСЭН:2026/02/06     МАНСУУРУУЛАХ БОДИСТОЙ ХОЛБООТОЙ ГЭМТ ХЭРЭГ 21.6 ХУВИАР ӨСЖЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/02/06     НИЙСЛЭЛИЙН УСНЫ ХАНГАМЖИЙГ НЭМЭГДҮҮЛЭХ ТӨСӨЛ ИРЭХ САРД ХЭРЭГЖИЖ ДУУСНА WWW.EAGLE.MN НИЙТЭЛСЭН:2026/02/06     МАЛ ХУЛГАЙЛЖ, БЭЛЧЭЭРТ НЬ НЯДАЛДАГ БҮЛЭГ ЭТГЭЭДИЙГ БАРИВЧИЛЖЭЭ WWW.NEWS.MN  НИЙТЭЛСЭН:2026/02/06     УНГАРЫН ОТП БАНК МОНГОЛД ҮЙЛ АЖИЛЛАГАА ЯВУУЛАХ ХҮСЭЛТЭЭ ИЛЭРХИЙЛЛЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/02/05     Г.ЗАНДАНШАТАР: ТӨСВИЙН ХӨРӨНГӨӨР ХАЙГУУЛ ХИЙСЭН ОРДУУДЫН ӨГӨӨЖИЙГ АРД ТҮМЭНД ХҮРТЭЭХ НЬ ЗҮЙ ЁСНЫ АСУУДАЛ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/02/05     БАЙГАЛЬ ОРЧНЫ АУДИТЫН ТУСГАЙ ЗӨВШӨӨРЛИЙГ ЦАХИМААР ОЛГОЖ ЭХЭЛЛЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/02/05    

Prime Minister Tasks to Start PC-04 Package Work of Oil Refinery www.montsame.mn

The Prime Minister of Mongolia Oyun-Erdene Luvsannamsrai tasked to start the EPC-04 Package Work of the Oil Refinery and commission the plant in 2027. The Government of Mongolia pursues the policy of intensifying the construction of the Oil Refinery. The Premier instructed to make up for the 13 months of work lost during the Covid-19, start the EPC-04 Package Work of the Oil Refinery, and intensify the work to put the plant into operation in 2027.
In 2016, the General Loan Agreement of USD 1 Billion was signed between the Government of Mongolia and the Export-Import (EXIM) Bank of the Republic of India. According to the Feasibility Study released at that time, it was concluded that the "Oil Refinery Construction Project" requires funding equivalent to USD 1 billion 236 million. Therefore, a loan agreement was signed in October 2019 to settle additional funding of USD 236 million from the Government of Mongolia.
The principal repayment of the loan was scheduled to be paid annually in the amount of USD 64.5 million starting from February 2023. However, as of February 2023, USD 112 million was taken out of the USD 1 billion loan. Therefore, a proposal to change the repayment schedule of the loan, which had been used to a minor extent, was made to the Indian side, sub-loan agreements have been signed on August 17, 2023, and the repayment has been postponed. The sub-loan agreement reduces the principal repayment of the loan from USD 64.5 million to USD 13.1 million. In addition, the period of exemption from the principal payment of 789.0 million US dollars, which is the financing of EPC-02 and EPC-03 Package Works, has been extended for another seven years.
With this agreement, the implementation of the four Package Works of "Oil Refinery Construction Project" that were regulated by one contract, which were dependent on each other and delayed, can be separated, thus enabling to intensify implementation of the Package Works.
Currently, EPC-04 Package Works, namely the construction and equipment works of the main plant, are pending. "Mongolian Oil Refinery" has announced that the budgeted cost of EPC-04 Package of USD 236 million will be increased by USD 422.0 million during the bidding process, making it a total of USD 648 million.
The Government of Mongolia confirmed the loan agreement for the initial cost of USD 236 million, and submitted a request for financing to the Export-Import Bank of the Republic of India in order to quickly start the work on the three facilities that will require the longest period of work in the EPC-04 Package: hydrocracking, sulfur separation facility, and hydrogen plant.