1 MONGOLIA ADOPTS THE STANDARD EMPLOYMENT CONTRACT TEMPLATES WWW.ILO.ORG PUBLISHED:2025/06/11      2 EX-MONGOLIA LEADER URGES JAPAN LAWMAKERS TO END DEATH PENALTY WWW.ENGLISH.KYODONEWS.NET  PUBLISHED:2025/06/11      3 GLOBAL SHIFTS FOR STRATEGIC MINING REVENUE GROWTH HIGHLIGHTED WWW.UBPOST.MN PUBLISHED:2025/06/11      4 SILVER GEREGE DISCOVERED ON THE TERRITORY OF MONGOLIA FOR THE FIRST TIME WWW.MONTSAME.MN PUBLISHED:2025/06/11      5 RURAL RESIDENTS TO LEAD MORTGAGE QUEUE AS URBAN APPLICANTS FALL BEHIND WWW.UBPOST.MN PUBLISHED:2025/06/11      6 IAN MILLER, BRONCOS OUT TO WRITE MORE HISTORY FOR MONGOLIA IN BCL ASIA 2025 WWW.FIBA.BASKETBALL PUBLISHED:2025/06/11      7 MONGOLIA’S NEXT GOVERNMENT MAY FACE RISING FISCAL RISK WWW.FITCHRATINGS.COM PUBLISHED:2025/06/10      8 CORRUPTION SEEN AS BIGGER RISK TO MONGOLIAN DEMOCRACY THAN CHINESE, RUSSIAN INFLUENCE WWW.WASHINGTONTIMES.COM PUBLISHED:2025/06/10      9 MPP NOMINATES ZANDANSHATAR GOMBOJAV FOR PRIME MINISTER OF MONGOLIA WWW.MONTSAME.MN PUBLISHED:2025/06/10      10 RIO TINTO FACES MAJOR ENGINEERING CHANGE AT OYU TOLGOI WWW.MINING.COM PUBLISHED:2025/06/10      АЖЛЫН ХЭСЭГ "ТЭЦ-3"-ЫН ОСОЛД БҮХ ТҮВШНИЙ УДИРДЛАГА БОЛОН ЯАМ ХАРИУЦЛАГА ХҮЛЭЭХ ЁСТОЙ ГЭЖ ҮЗЖЭЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/11     ЕРӨНХИЙ САЙДЫГ МАРГААШ ТОМИЛНО WWW.EAGLE.MN НИЙТЭЛСЭН:2025/06/11     МОНГОЛ УЛСЫН ИХ ХУРЛЫН ТУХАЙ ХУУЛЬД НЭМЭЛТ ӨӨРЧЛӨЛТ ОРУУЛАХ ТУХАЙ ХУУЛИЙН ТӨСЛИЙГ ӨРГӨН МЭДҮҮЛЛЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/06/11     “ПЛЭЙТАЙМ” НААДМААР 100 МЯНГАН ҮЗЭГЧ ХҮЛЭЭН АВАХААР ЗЭХЖЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/06/11     СЭЛБЭ ДЭД ТӨВД 41 ГА ГАЗРЫГ ЭДИЙН ЗАСГИЙН ЭРГЭЛТЭД ОРУУЛЖ, ХУВИЙН ХЭВШИЛТЭЙ ХАМТАРНА WWW.GOGO.MN НИЙТЭЛСЭН:2025/06/11     УБТЗ-ЫН ВАГОНУУД МАШ ОЛОН ЖИЛИЙН НАСЖИЛТТАЙ, ХУГАЦАА НЬ ДУУСАЖ, ЗАСВАРЫН ХУГАЦАА НЬ БОЛЖЭЭ WWW.GOGO.MN НИЙТЭЛСЭН:2025/06/10     FINANCIAL REVIEW: МОНГОЛ "РИО ТИНТО"-ГИЙН ЗЭСИЙН УУРХАЙД ИНЖЕНЕРИЙН ТОМООХОН ӨӨРЧЛӨЛТ ХИЙХЭД ХҮРГЭЛЭЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/10     ҮНДСЭН ХӨРӨНГӨД ОРУУЛСАН ХӨРӨНГӨ ОРУУЛАЛТ, САНХҮҮГИЙН ДЭМЖЛЭГ, ХАНДИВЫН ЗАРДЛЫГ ТӨЛӨХ ТАТВАРЫН ДҮНГЭЭС ХАСАЖ ТООЦНО WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/06/10     АЛБАДАН ГАРГАХ АЖИЛЛАГААНД СААД УЧРУУЛСАН ШВЕДИЙН ИРГЭНИЙГ ХУЯГЛАН ГАРГАВ WWW.EAGLE.MN НИЙТЭЛСЭН:2025/06/10     Г.ЗАНДАНШАТАРЫГ ЕРӨНХИЙ САЙДААР ТОМИЛОХ САНАЛ ОРУУЛЛАА WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/06/10    

Rio Tinto faces major engineering change at Oyu Tolgoi www.mining.com

Rio Tinto (LON: RIO) (ASX:RIO) has approved a shift in underground development at its Oyu Tolgoi copper-gold mine in Mongolia, pausing progress in the Entrée Resources (TSX: ETG) joint venture area due to ongoing delays in license transfers.
The company said the ramp up of production from Oyu Tolgoi remains on track to deliver an average of around 500,000 tonnes of copper from 2028 to 2036, with options including bringing Panel 1 or Panel 2 South into production first depending on the timing of the Entrée licence transfers.
“With lateral development work only just beginning in Panel 1, this is the right time to pivot and bring forward development in Panel 2 South to maintain our options,” Katie Jackson, chief executive of Rio Tinto Copper, said in a statement.
While limited development will continue in parts of Panel 1 outside the JV boundary, Rio Tinto confirmed that resources will now be reallocated to expedite progress in the more accessible Panel 2 South.
The development freeze in the Entrée JV area stems from a delay in transferring licences to Oyu Tolgoi LLC (OTLLC), the operating entity jointly owned by Rio Tinto (66%) and the Mongolian government (34%).
Entrée expressed disappointment over the holdup. CEO Stephen Scott noted that the transfer process began in February 2025 but remains incomplete.
“The parties have always intended for OTLLC to hold title to the Shivee Tolgoi and Javkhlant mining licenses on behalf of the JV participants,” Scott said. “It is a requirement of the 2008 JV agreement and contemplated in the 2009 Oyu Tolgoi investment agreement.”
He cautioned that any significant delay in development at Lift 1 Panel 1 could adversely impact the project’s cost, schedule, and Entrée’s financial position and share price.
As one of the world’s largest known copper-gold resources, Oyu Tolgoi plays a pivotal role in Rio Tinto’s growth strategy and Mongolia’s economic development.
Open pit mining at Oyu Tolgoi first started in 2011, and the copper concentrator, the largest industrial complex ever built in Mongolia, began processing mined ore into copper concentrate in 2013. Last year, underground production also kicked off, which is expected to elevate Oyu Tolgoi into one of the world’s top copper producers by 2030.



Published Date:2025-06-10